Raia Project Reaches New Milestones in One of Brazil’s Major Natural Gas Developments

T&B Petroleum/Press Office Equinor
06/08/2026 12:10
Raia Project Reaches New Milestones in One of Brazil’s Major Natural Gas Developments Imagem: Disclosure Equinor Visualizações: 1347 (0) (0) (0) (0)

The Raia project, operated by Equinor in partnership with Repsol Sinopec and Petrobras, has reached important milestones in its development in the pre-salt of the Campos Basin. The project has completed the installation of the ultra-deepwater section of the gas pipeline that will connect the field to the coast of Rio de Janeiro state, recorded the arrival of the Saturn jack-up barge on the coast of Macaé, Rio de Janeiro, to support the pipeline installation campaign, and delivered its first production well.

The World’s Deepest Gas Pipeline

Equinor has completed the installation of 186 kilometers of Raia’s natural gas export pipeline in ultra-deep waters, using pipes manufactured by Tenaris with 99% Brazilian steel. At its deepest point, the pipeline reaches 2,735 meters below the surface, making it the deepest gas pipeline in the world.

During the installation, more than 600 professionals worked daily aboard the Saipem vessel.

The milestone reinforces the progress of the project schedule, with operations expected to begin in 2028. Once production begins, Raia will have the capacity to transport 16 million cubic meters of natural gas per day, potentially accounting for 15% of Brazil’s projected total gas demand.

First Well Delivered

Another important milestone for the project was the delivery of the first production well, PDA-P14. Located approximately 200 kilometers from the coast in the Campos Basin, the well is part of the Raia development, which brings together the pre-salt discoveries of Pão de Açúcar, Gávea, and Seat and has recoverable reserves of natural gas and oil/condensate exceeding one billion barrels of oil equivalent (boe).

Completed ahead of the established target, PDA-P14 reinforces the technical capabilities of the teams involved in executing a highly complex project.

Saturn in Position

The project also recorded the arrival of the Saturn jack-up barge in the Macaé region. The unit is supporting the pipeline installation campaign through horizontal directional drilling (HDD), which will connect the offshore and onshore sections of the pipeline.

The arrival of the Saturn marks the beginning of a new phase of the campaign, including pilot-hole drilling, hole enlargement, and pipe pulling operations, which precede the final installation of the infrastructure. The mobilization of the unit contributes to the safe progress of the development schedule.

Innovative Concept

The gas produced at Raia will be transported through the pipeline to Cabiúnas, in Macaé, where it will be connected to the national gas transportation system. This will be the first time in Brazil that gas is conditioned offshore and delivered directly to the transportation system, without the need for an onshore processing plant.

The project represents a strategic milestone not only for Equinor but also for Brazil’s energy system itself, as one of the country’s major natural gas projects.

About Raia – Raia is one of Brazil’s major natural gas projects and is operated by Equinor (35%) in partnership with Repsol Sinopec Brasil (35%) and Petrobras (30%). Together with its partners, Equinor will invest approximately US$9 billion in the project’s development. In addition, the project’s FPSO is expected to rank among the world’s most efficient in terms of carbon intensity, with average CO₂ emissions of approximately 6 kg per barrel of oil equivalent.

Most Read
see see
International Company News
OES Group Returns to Private Ownership Following Managem...
01/09/26
Products and Services
RiverTough Bearings and Seals
27/08/26
Pre-Salt
Petrobras platforms P-80 and P-82, which will operate in...
27/08/26
Royalties
Values related to June production were distributed to st...
27/08/26
People
bp appoints Felipe Arbelaez head of country for Brazil
27/08/26
ROG.e 2026
ROG.e 2026 brings global leaders together to discuss the...
26/08/26
Pre-Salt
Búzios field sets monthly and daily natural gas export r...
26/08/26
Navalshore
Firjan SENAI presents the Supplier Opportunities Network...
17/08/26
Equatorial Margin
Morpho Well: Petrobras discovers hydrocarbons in ultra-d...
15/08/26
Power Generation
Campo Grande hosts four days of debates on bioenergy and...
12/08/26
International
KPMG: fossil fuel consumption falls, despite oil's signi...
12/08/26
Fenasucro
Fenasucro & Agrocana opening highlights Brazil's leaders...
12/08/26
Event
IBP and BIP bring together leaders to discuss technology...
11/08/26
Event
Asset Management gains prominence in corporate strategy;...
11/08/26
Macaé
Foresea takes part in WSOP 2026 and reinforces that safe...
11/08/26
Sergipe-Alagoas Basin
Siemens Energy advances offshore expansion in Brazil wit...
10/08/26
Campos Basin
Raia Project Reaches New Milestones in One of Brazil’s M...
06/08/26
Permanent Offer
ANP Takes Part in Ceremony Marking the Signing of Contra...
05/08/26
SOG 2026
ABPIP Strengthens Territorial Development Agenda in Serg...
04/08/26
SOG 2026
SOG26 Surpasses the Previous Edition and Reinforces Serg...
03/08/26
People
Shell Brasil Begins a New Leadership Cycle with João San...
03/08/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2