The FPSO Almirante Barroso has achieved full production in record time

The floating production vessel is producing 150 thousand barrels of oil a day in the Búzios field (Santos basin), after around five months

Petrobras Agency
25/10/2023 15:05
The FPSO Almirante Barroso has achieved full production in record time Imagem: Petrobras Agency Visualizações: 2247 (0) (0) (0) (0)

The floating production vessel, Almirante Barroso, which operates in the Búzios field, in the pre-salt layer of the Santos Basin, reached full production (150 thousand barrels of oil per day (bpd)) this Tuesday, Oct 24th.  This output was achieved in record time: it has been 146 days (less than five months) since the start of production. Petrobras’s previous record was the FPSO P-76, which reached full output in less than eight months, also in the Búzios field. The Almirante Barroso is a floating production storage and offloading unit (FPSO). It began commercial production on May 31st, this year.

The project's underwater system has reduced the average well interconnection time by 15%, by incorporating a new solution for installing rigid pipelines, which has contributed directly to the record ramp-up time.

The platform has been chartered from Modec and is located 180 km off the coast of Rio de Janeiro, at a depth of 1900 meters. Petrobras is the field operator and has an 88.99% stake in the shared Búzios deposit, alongside its partners, CNOOC - 7.34% and CNODC - 3.67%.

“Thanks to the commitment of our technicians and use of new technology, we are continuing to see exceptional results from Búzios, with eleven high production units operating there, equipped with the most modern decarbonization technologies”, stated Carlos Travassos, the Director of Engineering, Technology and Innovation.

Record Holders – Reached Full Production

- The FPSO Almirante Barroso in the Búzios field, in the Santos Basin – Full production in 146 days (less than five months) – Production at 150 thousand barrels per day.

- The FPSO P-76, in the Búzios field, in the Santos Basin – Full production in 234 days (less than eight months).

- The FPSO Guanabara in the Mero field, in the Santos Basin – Full production in 249 days (less than eight months) – Production at 180 thousand barrels per day.

 

Most Read Today
see see
People
Julia Cruz Appointed as New Secretary of Green Economy, ...
03/07/25
Sustainability
ABB among TIME’s World’s Most Sustainable Companies
03/07/25
Biofuels
Brazil Can Lead the Decarbonization of International Tra...
03/07/25
Pre-Salt
Oil States signs contracts to supply rigid jumpers for S...
03/07/25
Electric Energy
SMEs: Seven Tips for Joining the Free Energy Market
03/07/25
Energy Transition
CCEE Highlights Leadership in Energy Transition at EVEX ...
03/07/25
Award
WPC Energy Announces Vicki Hollub as Recipient of the Pr...
01/07/25
ANP
Final Results of the PRH-ANP 2025 Announced
01/07/25
Wind Energy
New Provisional Measure Will Not Be Enough to Counter Ha...
30/06/25
International
Oil discovery in the Johan Castberg area in the Barents Sea
30/06/25
Fuels
Gasoline Drops Just 0.78% in June Despite Petrobras' 5.6...
30/06/25
Event
Brazil Advances Energy Transition with E30 and B15, Rein...
30/06/25
People
Patricia Pradal Appointed as New President of Chevron So...
30/06/25
Results
ANP Releases Consolidated Data for the Regulated Sector ...
30/06/25
Ethanol
Ethanol Prices Rise in the Last Week of June
30/06/25
People
Fulkrum appoints Louisa Poole as Chief Financial Officer
26/06/25
International Company News
Johan Castberg producing at full capacity
25/06/25
Decarbonization
EPE to Launch Analysis on Decarbonization of Brazilian E...
13/06/25
FIRJAN
At the Launch of the Rio Oil Yearbook, Business Leaders ...
13/06/25
Permanent Offer
ANP to Hold 5th Cycle of the Permanent Concession Offer ...
13/06/25
Award
Unique Group Celebrates Prestigious Wins at 2025 cHeRrie...
13/06/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.