Beginning of end for Brazil's last wind grid-bottleneck

Seven wind farms totalling 168MW have begun tests ahead of commercial operation in Brazil’s northeast

Recharge
10/11/2014 17:38
Visualizações: 2250 (0) (0) (0) (0)

Seven wind farms totalling 168MW have begun tests ahead of commercial operation in Brazil’s northeast– starting a process that will eliminate the last major transmission bottleneck in the country's wind sector.

Power regulator Aneel authorised the start of tests at the Macacos 1 complex – made up of the Pedra Preta, Macacos and Costa Branca plants of 20.7MW each, and the 16.1MW Juremas facility.

 

They sold power in the renewables auction of 2010 and should have come online in early 2014.

 

Macacos was ready in April this year, but has been awaiting conclusion of the João Câmara 3 substation by ETN, a unit of federal power company Chesf. The grid link was concluded at the end of October.

 

The wind farms are all controlled by renewables company CPFL Energias Renováveis, including two that it recently incorporated in a joint-venture with local developer DESA.

 

The time lag between starting tests and commercial commissioning is around a month in Brazil.

 

Aneel also cleared tests to begin at Campos dos Ventos 2, Eurus 1 and Eurus 3, all 30MW, the last two formerly owned by DESA.

 

Those plants are also connected through the same substation and had sold power at the reserve auction of 2010. They should have come online in January 2013.

 

Several other wind farms linked to the João Câmara 3 substation should come enter service in the next few weeks, eliminating the last big transmission bottleneck for wind power in Brazil.

 

More than 800MW of wind will eventually be linked to the grid via the same connection.

 

Since 2013, the government has changed its auction rules to ensure that all winning projects have guaranteed grid connection.

 

This year Brazil decided to auction transmission lines ahead of power auctions to ensure a smoother expansion of the country's wind power capacity.


Siemens supplied the turbines for the Macacos complex.


Wobben (Enercon) supplied the turbines for Campos dos Ventos 2 and GE supplied the machines for Eurus 1 and 3.

Most Read Today
see see
Recognition
IBP Wins the “Events Oscar” Once Again with ROG.e 2024
11/12/25
FIRJAN
Rio Could Generate 676,000 New Jobs by Stimulating Nine ...
11/12/25
Inland Navigation
Grease-Free Revolution in Latin America’s Workboat Sector
10/12/25
PPSA
Production-Sharing Contracts to Produce 2 Million Barrel...
10/12/25
Recognition
National Public Transparency Program Grants Transpetro I...
10/12/25
Logistics
Transpetro expands its logistics operations with the int...
09/12/25
Auction
PPSA raises around R$ 8.8 billion from the sale of the F...
08/12/25
PPSA
Petrobras announces results of PPSA’s Non-Contracted Are...
08/12/25
Niterói
Niterói concludes second edition of Tomorrow Blue Econom...
02/12/25
Recognition
ABS Consulting Earns Third Elev8 GovCon Honor for Excell...
22/11/25
Award
Aed Energy Wins at the 2025 Energy Storage Awards
22/11/25
Mossoró Oil & Gas Energy 2025
PetroSupply Meeting to Boost Business at Mossoró Oil & G...
21/11/25
Results
Union’s Oil Production Reached 174 Thousand Barrels per ...
21/11/25
International Company News
TGS Extends Agreement with the Government of the Federal...
21/11/25
Company News
Belga Marine and Global Maritime Announce Strategic Part...
21/11/25
Niterói
Tomorrow Blue Economy sets Niterói in motion in the coun...
13/11/25
Cop30
ANP Participates in the Event and Advances Measures for ...
13/11/25
FIRJAN
Enaex 2025 Discusses Reindustrialization, Brazil’s Compe...
13/11/25
Mossoró Oil & Gas Energy 2025
Mossoró Oil & Gas Energy to Feature Strategic Debates in...
13/11/25
Company News
Norsul becomes the first company in Latin America to ado...
11/11/25
ADIPEC 2025
From energy to intelligence to impact: ADIPEC 2025 sets ...
07/11/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.