Auction

Chinese company wins energy transmission auction

Agência Brasil
20/07/2015 17:54
Chinese company wins energy transmission auction Imagem: Free Images Visualizações: 1656 (0) (0) (0) (0)

China's State Grid Brazil Holding S.A. will build and operate the 2,550km-long transmission line conveying power from the Belo Monte hydroelectric power plant, in the northern state of Pará, to southeast Brazil. The company won an auction held friday (Jul 17) on the São Paulo Stock Exchange (Bovespa) by the Brazilian Electricity Regulatory Agency (ANEEL).

 

The firm agreed to receive as the Annual Revenue Allowed (the amount to which the company will be entitled for providing the public service, referred to as RAP in the Portuguese acronym) $314.90 million, 19% lower than the maximum previously established. Another contestant, Abengoa Concessões Brasil Holding S.A., bid $334.34 million, 14% below the highest value allowed.

 

The concession is to last 30 years starting from the contract signing date. Investments are estimated at $2.23 billion, and works are due to end in 50 months. New direct jobs should total some 16.8 thousand.

 

The energy produced at the Belo Monte hydroelectric facility will be transmitted to the Rio Terminal Station, in Rio de Janeiro state. The project includes a power boost for Rio's metropolitan region and higher reliability for the systems serving the country's north and southeast regions.

Most Read Today
see see
Recognition
IBP Wins the “Events Oscar” Once Again with ROG.e 2024
11/12/25
FIRJAN
Rio Could Generate 676,000 New Jobs by Stimulating Nine ...
11/12/25
Products and Services
Grease-Free Revolution in Latin America’s Workboat Sector
10/12/25
PPSA
Production-Sharing Contracts to Produce 2 Million Barrel...
10/12/25
Recognition
National Public Transparency Program Grants Transpetro I...
10/12/25
Logistics
Transpetro expands its logistics operations with the int...
09/12/25
Auction
PPSA raises around R$ 8.8 billion from the sale of the F...
08/12/25
PPSA
Petrobras announces results of PPSA’s Non-Contracted Are...
08/12/25
Niterói
Niterói concludes second edition of Tomorrow Blue Econom...
02/12/25
Recognition
ABS Consulting Earns Third Elev8 GovCon Honor for Excell...
22/11/25
Award
Aed Energy Wins at the 2025 Energy Storage Awards
22/11/25
Mossoró Oil & Gas Energy 2025
PetroSupply Meeting to Boost Business at Mossoró Oil & G...
21/11/25
Results
Union’s Oil Production Reached 174 Thousand Barrels per ...
21/11/25
International Company News
TGS Extends Agreement with the Government of the Federal...
21/11/25
Company News
Belga Marine and Global Maritime Announce Strategic Part...
21/11/25
Niterói
Tomorrow Blue Economy sets Niterói in motion in the coun...
13/11/25
Cop30
ANP Participates in the Event and Advances Measures for ...
13/11/25
FIRJAN
Enaex 2025 Discusses Reindustrialization, Brazil’s Compe...
13/11/25
Mossoró Oil & Gas Energy 2025
Mossoró Oil & Gas Energy to Feature Strategic Debates in...
13/11/25
Company News
Norsul becomes the first company in Latin America to ado...
11/11/25
ADIPEC 2025
From energy to intelligence to impact: ADIPEC 2025 sets ...
07/11/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.