Ensco-107 jack-up rig to begin Maari drilling in April

Drilling program is expected to run well into 2015.

OMV New Zealand
28/03/2014 14:07
Visualizações: 229 (0) (0) (0) (0)

 

OMV New Zealand, on behalf of its Maari JV partners has announced that the jack-up drilling rig Ensco-107 has been unloaded from the heavy lift vessel Talisman in Admiralty Bay and is now on its way to the Maari field in the Taranaki Basin.
A blessing of the rig was performed by Ngati Koata and Ngati Ruanui in Admiralty Bay prior to its floating off and journey to Maari. The tow to the Maari field will take around 18 hours before the rig begins the final approach to the set up position for moving alongside the Maari Wellhead Platform.
“The focus of the Maari Growth project is to access untapped oil accumulations in the permit and to better drain the existing reservoirs,” explained Peter Zeilinger, Managing  Director of OMV New Zealand.
“This should help stabilise the natural production decline we are seeing at the field and allow us to continue production at Maari for at least another 10 years.”
The drilling program of five wells is expected to run well into 2015 and will keep a workforce of more than 250 personnel occupied on and offshore to safely deliver the project.
The Ensco-107 is returning to familiar waters at the Maari field. It drilled the field’s original production and water injection wells as well as the Manaia-1 well which, at eight kilometres long still holds the record for the longest well drilled in New Zealand.
“The Maari Growth project is part of a joint venture investment programme in excess of NZ$400 million. Its goal is to improve the recovery from the Maari and Manaia reservoirs, and also find and appraise near field opportunities to a development stage. 
“While the Maari Growth programme is separate from our exploration and appraisal programme with the Kan Tan IV, together they represent a considerable commitment to development in the Taranaki Basin in particular and in New Zealand in general.” The rig is expected to start drilling in April.

OMV New Zealand, on behalf of its Maari JV partners has announced that the jack-up drilling rig Ensco-107 has been unloaded from the heavy lift vessel Talisman in Admiralty Bay and is now on its way to the Maari field in the Taranaki Basin. A blessing of the rig was performed by Ngati Koata and Ngati Ruanui in Admiralty Bay prior to its floating off and journey to Maari. The tow to the Maari field will take around 18 hours before the rig begins the final approach to the set up position for moving alongside the Maari Wellhead Platform.

 

“The focus of the Maari Growth project is to access untapped oil accumulations in the permit and to better drain the existing reservoirs,” explained Peter Zeilinger, Managing  Director of OMV New Zealand. “This should help stabilise the natural production decline we are seeing at the field and allow us to continue production at Maari for at least another 10 years.”

 

The drilling program of five wells is expected to run well into 2015 and will keep a workforce of more than 250 personnel occupied on and offshore to safely deliver the project. The Ensco-107 is returning to familiar waters at the Maari field. It drilled the field’s original production and water injection wells as well as the Manaia-1 well which, at eight kilometres long still holds the record for the longest well drilled in New Zealand.


“The Maari Growth project is part of a joint venture investment programme in excess of NZ$400 million. Its goal is to improve the recovery from the Maari and Manaia reservoirs, and also find and appraise near field opportunities to a development stage. “While the Maari Growth programme is separate from our exploration and appraisal programme with the Kan Tan IV, together they represent a considerable commitment to development in the Taranaki Basin in particular and in New Zealand in general.” The rig is expected to start drilling in April.

 

Most Read Today
see see
ROG.e 2026
Petrobras president advocates active exploration and exp...
25/09/26
ROG.e 2026
Nikki Martin, president and CEO of EnerGeo Alliance, spo...
25/09/26
ROG.e 2026
Oil States Highlights Integration Between Engineering, M...
25/09/26
ROG.e 2026
Port of Açu and OceanPact sign agreement for expansion o...
25/09/26
ROG.e 2026
Lumina’s Role and the Impact of ROG.e 2026 on the Energy...
25/09/26
ROG.e 2026
Leaders Identify Brazil as a Pillar of Energy Security a...
24/09/26
ROG.e 2026
Firjan SENAI and Sebrae Rio Connect Small Businesses wit...
24/09/26
ROG.e 2026
PPSA Study Identifies Best Practices to Support Investme...
24/09/26
ROG.e 2026
ROG.e 2026 Reinforces the DE&I Agenda in the Energy Sect...
24/09/26
ROG.e 2026
IBP Launches Publication on Energy Companies’ Socio-envi...
23/09/26
ROG.e 2026
Industry Giants and Independent Producers Accelerate Pro...
22/09/26
ROG.e 2026
Firjan Attends ROG.e 2026 Opening Ceremony and Signs Tec...
22/09/26
ROG.e 2026
ROG.e 2026 Opening Ceremony Highlights Just Energy Trans...
21/09/26
ROG.e 2026
Global Leaders Position Brazil as a Hub of Stability, At...
21/09/26
ROG.e 2026
Exclusive Interview: Pelagus targets Brazil to strengthe...
21/09/26
ROG.e 2026
At ROG.e, Firjan SENAI Holds the 30th Edition of the Sup...
21/09/26
ROG.e 2026
ROG.e 2026 kicks off next Monday (21) with global energy...
19/09/26
ROG.e 2026
Camorim invests R$ 250 million in 2026 to expand fleet a...
18/09/26
ROG.e 2026
Firjan SENAI SESI Presents New Technologies at ROG.e Dev...
18/09/26
ADIPEC 2026
ADIPEC 2026 to mobilise investment in resilient, intelli...
18/09/26
Acquisition
CoreMarine takes a decisive step to expand its offshore ...
17/09/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2