The implementation of the Tanque Novo Wind Project, in Bahia, continues at full steam ahead and its inauguration is confirmed by CGN Brasil for next April. The port-logistics operation completed at the Enseada industrial and logistics complex, located in Maragojipe, in the Recôncavo region of Bahia, was one of the pillars of the success of the operation. In total, 40 wind turbines manufactured by Goldwind were received, stored in the complex's 750,000 m2 bonded area and transported to their destination, approximately 1,000 km away from the complex. The entire operation was carried out in record time, taking into account the shipment in China until the final landing in the southern region of Bahia. With one detail: the success of the activities had a great contribution thanks to an innovation by an engineer from Bahia.
Inspired by a surfboard, he came up with the idea of inverting the set (truck, supports and blades) and created a pair of devices that, once placed on the special trailer that transports the blades when disembarking the ship, made it possible to reverse the side of the sweep of the shovel, which is 76 meters long and weighs 22 tons.
“Conventional transport is carried out with the tail towards the back of the special trailer. With the shovel inverted, we made it possible for the sweep to be from the front, eliminating possible interference within the industrial complex”, reveals Danilo Oliveira, mechanical engineer at Enseada with an MBA in Lean Manufacturing and developer of the solution.
Still according to him, the innovation was conceived together with company professionals, simulated in engineering software and tested on the Enseada pier before execution, guaranteeing a safe, productive and faultless operation in all stages of the port-logistic contract.
Regional development
From the first moment of the operation, the focus on productivity and safety were prioritized. “The wind turbines were moved in a meticulous port operation and were temporarily stored in our bonded yard. Finally, through road transport, our client gradually transported the sets to the south of Bahia”, details Mário Moura, Director of Operations at Enseada.
Another highlight of the contract, says Enseada's Business Director, Carlos Tsubake, is the consolidation of the terminal as a pole that attracts new business opportunities and generates employment and income, contributing to sustainable regional development. “Bahia has, in Enseada, a world-class naval, port-logistics and industrial complex, the result of a private investment of BRL 3 billion, which is ready to generate even more qualified jobs in the state”, guarantees Tsubake.
Leadership
The Tanque Novo Wind Complex is located in the municipalities of Tanque Novo and Caetité, both in the southern region of Bahia. Soon, the Complex will have a total of 40 wind turbines distributed in seven wind farms, with a total installed capacity of 180 MW. The implementation of the Park will consolidate Bahia's national leadership in wind energy generation, with more than 30% of national production. In December, Goldwind concluded with its client CGN Brasil, in record time, 50% of the installation of wind turbines and by April 100% will be finished, increasing the installed capacity.
For the CEO of CGN Brasil, Yao Zhigang, the achievement will guarantee the state a leading position in the generation of clean and renewable energy in the country, which demonstrates the success of the policy defended and implemented 10 years ago by the Government of Bahia. “We are implementing one of the most modern and productive wind farms in Brazil and the Government of Bahia has been a fundamental partner in the success of the operation”, said Yao Zhigang.