North Sea

GDF Suez: Second Juliet field well comes on stream

The field is a subsea development on the western flank.

GDF Suez
13/03/2014 19:00
Visualizações: 2092 (0) (0) (0) (0)

 

GDF SUEZ has started gas production from the second of two development wells on the Juliet field in the North Sea, on the 9th of March.
The Juliet field is a subsea development on the western flank of the Southern Gas Basin, 39 km east of the Lincolnshire coastline in the United Kingdom. This follows first gas from the initial development well on 5th January 2014.
The field is now producing at its plateau rate of 80mmscfg/d. This is the equivalent to 400,000 bbls a month. The fast track project has been executed and successfully delivered in a time frame of less than 18 months from sanction to first gas.
Jean-claude Perdigues, General Manager GDF SUEZ E&P UK said: “The start-up of the second Juliet well is a significant step in the evolution of GDF SUEZ in the UK as it marks the transition of the Juliet development to a fully producing asset. It also underpins our commitment to continuously developing the potential of the United Kingdom Continental Shelf (UKCS) and the value that can be derived in a mature region through the efficient use of existing infrastructure.”
Produced gas is being transported by a 22 km pipeline to the Pickerill A platform and then transported onshore via the existing export pipeline to the Theddlethorpe gas terminal.
The Juliet field was discovered by GDF SUEZ E&P UK in December 2008 by vertical well 47/14b-10 which found a dry gas accumulation. The Juliet reservoir is considered to be fully appraised Rotliegendes Leman Sandstone reservoir with gross associated reserves of 11.6 Mboe.
The field lies in Block 47/14b, licence P614. Juliet is a strategic key development in one of GDF SUEZ’ core growth areas in the UKCS. GDF SUEZ is also operator of the Cygnus field and the UK licence operator of the Orca field in the Southern North Sea, as well as the operator of a number of exploration licences in the area.

GDF SUEZ has started gas production from the second of two development wells on the Juliet field in the North Sea, on the 9th of March.


The Juliet field is a subsea development on the western flank of the Southern Gas Basin, 39 km east of the Lincolnshire coastline in the United Kingdom. This follows first gas from the initial development well on 5th January 2014.


The field is now producing at its plateau rate of 80mmscfg/d. This is the equivalent to 400,000 bbls a month. The fast track project has been executed and successfully delivered in a time frame of less than 18 months from sanction to first gas.Jean-claude Perdigues, General Manager GDF SUEZ E&P UK said: “The start-up of the second Juliet well is a significant step in the evolution of GDF SUEZ in the UK as it marks the transition of the Juliet development to a fully producing asset. It also underpins our commitment to continuously developing the potential of the United Kingdom Continental Shelf (UKCS) and the value that can be derived in a mature region through the efficient use of existing infrastructure.”


Produced gas is being transported by a 22 km pipeline to the Pickerill A platform and then transported onshore via the existing export pipeline to the Theddlethorpe gas terminal.


The Juliet field was discovered by GDF SUEZ E&P UK in December 2008 by vertical well 47/14b-10 which found a dry gas accumulation. The Juliet reservoir is considered to be fully appraised Rotliegendes Leman Sandstone reservoir with gross associated reserves of 11.6 Mboe.


The field lies in Block 47/14b, licence P614. Juliet is a strategic key development in one of GDF SUEZ’ core growth areas in the UKCS. GDF SUEZ is also operator of the Cygnus field and the UK licence operator of the Orca field in the Southern North Sea, as well as the operator of a number of exploration licences in the area.

Most Read Today
see see
FIRJAN
Agrega + Indústria brings together entities, companies, ...
29/07/26
SOG 2026
ABPIP brings to Sergipe Oil & Gas a debate on strengthen...
28/07/26
Event
BR Aviation presents its portfolio of customized solutio...
23/07/26
Royalties
Royalties: amounts referring to May production distribut...
23/07/26
Fuels
Fuel and lubricants sector registers 1.8% drop in June, ...
22/07/26
IBP
Studies point to redundancy of the export tax and extra ...
22/07/26
PPSA
7th Spot Auction: PPSA markets cargoes from Atapu and Ba...
20/07/26
Results
Union oil production reaches 244 thousand barrels per da...
17/07/26
State of Ceará
Natural gas arrives in Cariri (CE) and strengthens econo...
16/07/26
Terminals
Vast announces contract extension with PETRONAS Brasil u...
15/07/26
International
War, oil and the dollar: how global fluctuations impact ...
13/07/26
ANP
Third-party access to natural gas flow pipelines and pro...
10/07/26
Agreement
ANP and Petrobras sign agreement to bring 335 offshore w...
07/07/26
Logistics
Vast Infraestrutura and Petrobras strengthen partnership...
07/07/26
IBP Positioning
Change of the instrument does not fix the illegalities o...
07/07/26
Energy Summit
Energy Summit 2026: Embrapii technologies strengthen Bra...
22/06/26
Energy Summit
Biodiesel and renewable fuels move to the center of the ...
22/06/26
Natural Gas
ANP extends public consultation on the calculation of th...
22/06/26
Rio de Janeiro
Firjan’s Oil Yearbook in Rio highlights that positive pr...
22/06/26
Biomethane
With a market five times larger since 2020, the biometha...
22/06/26
Petrobras
Petrobras approves investment in bio-jet fuel and renewa...
22/06/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.