Brazil

Hull of P-66 platform leaves shipyard in Rio Grande do Sul

Luschi
11/04/2014 17:55
Hull of P-66 platform leaves shipyard in Rio Grande do Sul Imagem: Petrobras Agency Visualizações: 1699 (0) (0) (0) (0)

 

Hull of P-66 platform leaves shipyard in Rio Grande do Sul
Petrobras recently commenced the removal of the hull of P-66 platform in the Rio Grande Shipyard, 
Brazil. The operation required dredging to open the gate, which was conducted by LUSCHI. "About 
30,000 cubic meters of sediment were dredged in less than 20 days using a hopper dredge and a 
very powerful submersible pump for inaccessible places," says Roberto Britto, director of logistics 
LUSCHI. 
 
The dredging activities have started in March, alongside the works of partial flooding of the dry 
dock and inspection of the hull. The complete filling of the dock was taken on April 4, when the 
climatic conditions are presented adequate, until it reaches about 14 meters depth needed to open 
the door-boat. 
 
This platform is the first of eight replicant FPSOs (Floating Production Storage and Offloading) to be 
built for the development of the pre-salt projects, in the prolific Santos basin. This unit will have a 
processing capacity of 150,000 bpd of oil and 6 million m³/day of natural gas. 

Petrobras recently commenced the removal of the hull of P-66 platform in the Rio Grande Shipyard, Brazil. The operation required dredging to open the gate, which was conducted by LUSCHI. "About 30,000 cubic meters of sediment were dredged in less than 20 days using a hopper dredge and a very powerful submersible pump for inaccessible places," says Roberto Britto, director of logistics Luschi.

 

The dredging activities have started in March, alongside the works of partial flooding of the dry dock and inspection of the hull. The complete filling of the dock was taken on April 4, when the climatic conditions are presented adequate, until it reaches about 14 meters depth needed to open the door-boat. 

 

This platform is the first of eight replicant FPSOs (Floating Production Storage and Offloading) to be built for the development of the pre-salt projects, in the prolific Santos basin. This unit will have a processing capacity of 150,000 bpd of oil and 6 million m³/day of natural gas. 

 

Most Read Today
see see
OTC Brasil 2025
Port of Açu and SISTAC Sign Agreement to Provide Decommi...
29/10/25
Royalties
Royalties from August Production Distributed to States a...
29/10/25
OTC Brasil 2025
iUP Innovation Connections Links Innovation Strategy to ...
29/10/25
ANP
Permanent Production Sharing Offer: Registered Companies...
29/10/25
OTC Brasil 2025
Firjan Showcases Technology and Innovation Solutions for...
29/10/25
OTC Brasil 2025
O&G exploration is key to social development and a just ...
28/10/25
OTC Brasil 2025
Experts warn regulatory instability threatens US$100 bil...
28/10/25
International Company News
Sercel Awarded Major Contract by ONGC to Supply Sercel 5...
28/10/25
Record
Petrobras announces production record of FPSO Almirante ...
28/10/25
OTC Brasil 2025
Event brings together global offshore industry leaders a...
28/10/25
OTC Brasil 2025
Petrobras participates in OTC Brasil 2025, in Rio de Janeiro
28/10/25
Petrobras
Petrobras produced 3.14 million barrels of oil equivalen...
27/10/25
FIRJAN
By 2035+, Rio de Janeiro State’s Energy Potential Could ...
23/10/25
Pre-Salt
PPSA to auction in December the first share of governmen...
23/10/25
Auction
Petrobras wins auction and leases RDJ07 terminal at the ...
23/10/25
Permanent Offer
Equinor acquires two new blocks in the Campos Basin duri...
23/10/25
OTC Brasil 2025
OTC Brasil 2025 Kicks Off in One Week with a Packed Prog...
22/10/25
Agreement
Wärtsilä Lifecycle agreement renewed to maintain safe, r...
22/10/25
Petrobras
Petrobras receives operating license for deepwater explo...
20/10/25
Equatorial Margin
License Grant for Drilling in the Equatorial Margin Is P...
20/10/25
Equatorial Margin
ABESPetro Statement on the Licensing of the Equatorial M...
20/10/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2