Gulf of Mexico

InterMoor successfully completes life-of-field service operations in Gomez field

Gomez field is located in Mississippi Canyon Block 711.

InterMoor
06/03/2014 14:17
Visualizações: 1724 (0) (0) (0) (0)

 

InterMoor, an Acteon company, has successfully completed decommissioning operations of the Innovator platform in Gomez field, Mississippi Canyon Block 711, Gulf of Mexico. 
The scope of work, conducted in water depths of 910 m, involved disconnecting 10 risers/umbilicals; disconnecting 12 mooring lines and then towing the Innovator to Ingleside, Texas. InterMoor developed special procedures for disconnection and towing, procured rigging and tow equipment for all vessels including the Anchor Handling Vessel (AHV), FPU and tug vessels, and provided essential personnel for the AHV and FPU throughout all phases of operations.
InterMoor’s involvement with the Innovator platform dates prior to 2006 when it was a mobile offshore drilling unit (MODU) known as the Rowan Midland. At that time, the MODU was being converted by ATP to a production platform, and InterMoor provided the mooring design, project management, procurement, installation and hook-up of the mooring system. The 12-leg mooring system consisted of suction embedded plate anchors (SEPLA), stud link chain, subsea connectors and polyester mooring ropes. This was leading-edge technology at the time, as it was only the third permanent polyester mooring system installed in the Gulf of Mexico and the first permanent SEPLA mooring.
InterMoor’s next assignment on the Innovator was in 2011, providing mooring line inspection, change-out of all rig wires, and upgrading five of the mooring legs due to new Metocean regulations and possible life extension. InterMoor performed the upgraded mooring analyses, provided regulatory interface and procured the upgrade mooring components.
The success of the decommissioning programme was a result of InterMoor’s detailed understanding of the Innovator platform’s mooring system, which was gained during the operations in 2006 and 2011. Tom Fulton, InterMoor president, said, “The successful decommissioning of the Innovator proves InterMoor’s technical and operational capabilities for complete floating platform decommissioning in deep water. At a time when many operators are looking at life-of-field solutions, we are proud to have played a role at crucial times throughout the development and decommissioning of this offshore asset.”

InterMoor, an Acteon company, has successfully completed decommissioning operations of the Innovator platform in Gomez field, Mississippi Canyon Block 711, Gulf of Mexico. 


The scope of work, conducted in water depths of 910 m, involved disconnecting 10 risers/umbilicals; disconnecting 12 mooring lines and then towing the Innovator to Ingleside, Texas. InterMoor developed special procedures for disconnection and towing, procured rigging and tow equipment for all vessels including the Anchor Handling Vessel (AHV), FPU and tug vessels, and provided essential personnel for the AHV and FPU throughout all phases of operations.


InterMoor’s involvement with the Innovator platform dates prior to 2006 when it was a mobile offshore drilling unit (MODU) known as the Rowan Midland. At that time, the MODU was being converted by ATP to a production platform, and InterMoor provided the mooring design, project management, procurement, installation and hook-up of the mooring system. The 12-leg mooring system consisted of suction embedded plate anchors (SEPLA), stud link chain, subsea connectors and polyester mooring ropes. This was leading-edge technology at the time, as it was only the third permanent polyester mooring system installed in the Gulf of Mexico and the first permanent SEPLA mooring.


InterMoor’s next assignment on the Innovator was in 2011, providing mooring line inspection, change-out of all rig wires, and upgrading five of the mooring legs due to new Metocean regulations and possible life extension. InterMoor performed the upgraded mooring analyses, provided regulatory interface and procured the upgrade mooring components.


The success of the decommissioning programme was a result of InterMoor’s detailed understanding of the Innovator platform’s mooring system, which was gained during the operations in 2006 and 2011. Tom Fulton, InterMoor president, said, “The successful decommissioning of the Innovator proves InterMoor’s technical and operational capabilities for complete floating platform decommissioning in deep water. At a time when many operators are looking at life-of-field solutions, we are proud to have played a role at crucial times throughout the development and decommissioning of this offshore asset.”

 

Most Read Today
see see
Memorandum of Understanding
Wärtsilä and Abu Dhabi Maritime Academy explore collabor...
12/02/26
Pre-Salt
Petrobras platform P-79 arrives at the Búzios field
12/02/26
Results
Petrobras’ oil and gas production rises 11% and reaches ...
12/02/26
Permanent Offer
Comprehensive and Unprecedented Joint Statement Speeds U...
12/02/26
PPSA
MME and MMA Clear Strategic Pre-Salt Areas, Enabling the...
12/02/26
Biomethane
Biomethane in Focus with Debate on Credit, Regulation, a...
12/02/26
People
Mario Ferreira is the New Commercial Manager at Wiz Corp...
11/02/26
Visas Agreement
Brazil implements electronic VISIT Visa for Chinese citizens
22/01/26
Biofuels
Sifaeg Highlights New Investment Cycle and the Consolida...
21/01/26
Drilling
Foresea’s Norbe IX Drillship Undergoes Scheduled Mainten...
21/01/26
State of Ceará
Companies from Ceará lead the H2MOVER-Pecém project, sel...
08/01/26
Maritime Support
Ambipar carries out more than 600 port and maritime emer...
07/01/26
Petrobras
Petrobras celebrates 20 years of the Santos Basin Unit
07/01/26
Pelotas Basin
TGS launches maritime safety application for operations ...
07/01/26
Diesel
Petrobras and Vale move forward with fuel supply partnership
07/01/26
ANP
In November, Brazil produced 4.921 million boe/d
07/01/26
Offshore Operations
Crew training and connectivity are the true enablers of ...
23/12/25
Recognition
IBP Wins the “Events Oscar” Once Again with ROG.e 2024
11/12/25
FIRJAN
Rio Could Generate 676,000 New Jobs by Stimulating Nine ...
11/12/25
Inland Navigation
Grease-Free Revolution in Latin America’s Workboat Sector
10/12/25
PPSA
Production-Sharing Contracts to Produce 2 Million Barrel...
10/12/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.