Lukoil achieves offshore Caspian early installation targets

Development drilling should also start next year, with first oil slated for the end of 2015.

Lukoil
17/12/2013 20:19
Visualizações: 1114 (0) (0) (0) (0)

 

Assembly has been completed of bearing blocks for the main offshore installations at Lukoil’s Vladimir Filanovsky field in the Russian sector of the Caspian Sea.
These are the ice-resistant stationary platform, the central processing platform, the living quarters module platform, and the riser block.
A transport/installation barge with a 400-ton capacity crane fixed the bearing blocks to the seafloor via piles of more than 2 m (6.5 ft) dia. and wall thickness of up to 80 mm (3.1-in.), driven to a depth of 60 m (197 ft). The piles are designed to withstand extreme ice and wave loads.
Additionally, 77 km (48 mi) of subsea oil pipeline and 61 km (38 mi) of subsea gas pipeline have been installed, along with 40 km (25 mi) of inter-field oil pipelines and 40 km of inter-field gas lines, connecting V.Filanovsky with the producing Yu.Korchagin field.
In 2014, topside sections will be mounted on the bearing blocks, and construction will start of onshore gas pipelines to the Stavrolen petrochemical enterprise in Budennovsk, and an oil pipeline to oil intake facilities close to the Komsomolskaya oil pumping station owned by the Caspian Pipeline Consortium.
Development drilling should also start next year, with first oil slated for the end of 2015.

Assembly has been completed of bearing blocks for the main offshore installations at Lukoil’s Vladimir Filanovsky field in the Russian sector of the Caspian Sea.These are the ice-resistant stationary platform, the central processing platform, the living quarters module platform, and the riser block.


A transport/installation barge with a 400-ton capacity crane fixed the bearing blocks to the seafloor via piles of more than 2 m (6.5 ft) dia. and wall thickness of up to 80 mm (3.1-in.), driven to a depth of 60 m (197 ft). The piles are designed to withstand extreme ice and wave loads.


Additionally, 77 km (48 mi) of subsea oil pipeline and 61 km (38 mi) of subsea gas pipeline have been installed, along with 40 km (25 mi) of inter-field oil pipelines and 40 km of inter-field gas lines, connecting V.Filanovsky with the producing Yu.Korchagin field.


In 2014, topside sections will be mounted on the bearing blocks, and construction will start of onshore gas pipelines to the Stavrolen petrochemical enterprise in Budennovsk, and an oil pipeline to oil intake facilities close to the Komsomolskaya oil pumping station owned by the Caspian Pipeline Consortium.


Development drilling should also start next year, with first oil slated for the end of 2015.

 

Most Read
see see
International
5th Congress of the Federation of Portuguese-Speaking La...
05/11/26
FIRJAN
Public-private partnership seen as vital to petrochemica...
05/11/26
Drilling
Norbe VIII, operated by Foresea, is ready to operate in ...
05/11/26
Refineries
TEM Boaventura Consortium completes lift of first reacto...
04/11/26
FIRJAN
Greater natural gas availability strengthens Rio de Jane...
03/11/26
Result
Oil and natural gas production hits a new record in Sept...
03/11/26
Pre-Salt
P-78 Platform (Búzios 6) reaches peak production of 180,...
03/11/26
Auction
Neoenergia wins Lots 1 and 7 in ANEEL Transmission Auction
30/10/26
WPC Energy
WPC Energy welcomes the Republic of Chad into membership
28/10/26
International
PortXL presents its 2026 cohort of 11 maritime startups ...
30/09/26
ADIPEC
ADIPEC 2026 set to welcome record Asian participation as...
29/09/26
ANP
Royalties: amounts referring to July production were dis...
29/09/26
25th WPC
Riyadh Takes Center Stage as Global Energy Heavyweights ...
28/09/26
ROG.e 2026
Petrobras president advocates active exploration and exp...
25/09/26
ROG.e 2026
Nikki Martin, president and CEO of EnerGeo Alliance, spo...
25/09/26
ROG.e 2026
Oil States Highlights Integration Between Engineering, M...
25/09/26
ROG.e 2026
Port of Açu and OceanPact sign agreement for expansion o...
25/09/26
ROG.e 2026
Lumina’s Role and the Impact of ROG.e 2026 on the Energy...
25/09/26
ROG.e 2026
Leaders Identify Brazil as a Pillar of Energy Security a...
24/09/26
ROG.e 2026
Firjan SENAI and Sebrae Rio Connect Small Businesses wit...
24/09/26
ROG.e 2026
PPSA Study Identifies Best Practices to Support Investme...
24/09/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.