Pre-Salt

Petrobras on FPSO Mero 4

Petrobras Agency
01/12/2021 18:06
Petrobras on FPSO Mero 4 Imagem: Divulgation Visualizações: 3995 (0) (0) (0) (0)

Petrobras informs that it signed on November 29th contracts with the company SBM Offshore for the chartering and provision of services of the FPSO Alexandre de Gusmão, the fourth definitive system to be installed in the Mero field, located in the pre-salt of the Santos Basin. The contracts follow the same parameters of the letter of intent signed in August of this year. The unit is expected to start production in 2025.

 

The FPSO, which stands for floating production, storage, and oil transfer unit, will be installed approximately 160 kilometers from Arraial do Cabo, in Rio de Janeiro, and will be capable of processing 180 thousand barrels of oil and 12 million cubic meters of gas per day. The contracts will last for 22 years and 6 months from the unit's final acceptance.

 

The project foresees the interconnection of 15 wells to the FPSO, 8 of which are oil producers, 6 water and gas injectors, 1 convertible well from producer to gas injector, through a subsea infrastructure composed of rigid production and injection pipelines and flexible service pipelines. To date, the project has had 4 wells drilled and 2 completed.

 

The contracts reinforce Petrobras' performance in partnership in the E&P area with a focus on deep and ultradeep waters. The company continues to operate efficiently and competitively, maximizing the potential of its assets and promoting more return for the company and the society.

 

About Mero Field 

The Mero field is the third largest in the pre-salt and is located in the Libra area, operated by Petrobras (40%) in partnership with Shell Brasil Petróleo Ltda. (20%), TotalEnergies EP Brasil Ltda. (20%), CNODC Brasil Petróleo e Gás Ltda. (10%), CNOOC Petroleum Brasil Ltda. (10%) and Pré-Sal Petróleo S.A. (PPSA), which is the manager of this contract.

 

Production of the first definitive Mero system (Mero 1) is scheduled to start in 2022, through FPSO Guanabara, followed by Mero 2 (FPSO Sepetiba), in 2023, and Mero 3 (FPSO Marechal Duque de Caxias), in 2024.

Most Read Today
see see
Navalshore
Firjan SENAI presents the Supplier Opportunities Network...
17/08/26
Equatorial Margin
Morpho Well: Petrobras discovers hydrocarbons in ultra-d...
15/08/26
Power Generation
Campo Grande hosts four days of debates on bioenergy and...
12/08/26
International
KPMG: fossil fuel consumption falls, despite oil's signi...
12/08/26
Fenasucro
Fenasucro & Agrocana opening highlights Brazil's leaders...
12/08/26
Event
IBP and BIP bring together leaders to discuss technology...
11/08/26
Event
Asset Management gains prominence in corporate strategy;...
11/08/26
Macaé
Foresea takes part in WSOP 2026 and reinforces that safe...
11/08/26
Sergipe-Alagoas Basin
Siemens Energy advances offshore expansion in Brazil wit...
10/08/26
Campos Basin
Raia Project Reaches New Milestones in One of Brazil’s M...
06/08/26
Permanent Offer
ANP Takes Part in Ceremony Marking the Signing of Contra...
05/08/26
SOG 2026
ABPIP Strengthens Territorial Development Agenda in Serg...
04/08/26
SOG 2026
SOG26 Surpasses the Previous Edition and Reinforces Serg...
03/08/26
People
Shell Brasil Begins a New Leadership Cycle with João San...
03/08/26
Results
ANP Releases Consolidated Data on Oil and Gas Production...
03/08/26
SOG 2026
Banco do Nordeste Has R$ 504 Million for the Energy Sect...
03/08/26
PPSA
TotalEnergies and ExxonMobil Win Atapu and Bacalhau Cargoes
31/07/26
SOG 2026
Sebrae Sergipe Strengthens Small Businesses and Expands ...
31/07/26
PPSA
PPSA Expects to Hold the First Auction of the Union’s Na...
30/07/26
SOG 2026
Sergipe Oil & Gas 2026 Begins with a Focus on Investment...
30/07/26
SOG 2026
Petrobras Director Opens Sergipe Oil & Gas with Analysis...
30/07/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.