Results

Petrobras reaches 2024 annual production target

Petrobras Agency
28/01/2025 21:30
Petrobras reaches 2024 annual production target Imagem: Petrobras Agency Visualizações: 3575 (0) (0) (0) (0)

Petrobras informs that, in 2024, it achieved all the production targets set in its Strategic Plan 2024-2028+, within a range of ±4%. The total production of oil and natural gas reached 2.7 million barrels of oil equivalent per day (boed). The commercial production of oil and natural gas reached 2.4 million boed, and the oil production was 2.2 million barrels per day (bpd).

The company set new annual records for total own and operated production in the pre-salt, with 2.2 million boed and 3.2 million boed, respectively. The production volume in the pre-salt represents 81% of the company's total  production.

Also noteworthy is the start-up of two new platforms in 2024: FPSO Maria Quitéria, located in the Jubarte field, in the pre-salt of the Campos Basin, which was originally scheduled to start operating in 2025; and FPSO Marechal Duque de Caxias, in the Mero field, in the pre-salt of the Santos Basin. During the year, the maximum oil production capacity of the FPSO Sepetiba platform, in the Mero field, was reached after eight months of operation. The ramp-up of these platforms partially offset the losses resulting from maintenance stoppages and the decline of mature fields, as well as the impact on production due to unscheduled stoppages determined by the ANP and the effects of the Ibama strike. Despite these external factors, the company managed to close 2024 within plan.

Another highlight of the year was the start of commercial operation of the Natural Gas Processing Unit (UPGN), located at the Boaventura Energy Complex (Itaboraí/RJ), in November, with the capacity to process 10.5 million m3/day of gas, through its first module.

These results were achieved thanks to the integrated efforts of the entire company, reinforcing Petrobras' commitment to investors and Brazilian Society.

Most Read Today
see see
PPSA
Federal Government receives R$ 917.32 million from Tupi ...
07/04/26
Study
Brazil increases dependence on thermal power, but lack o...
07/04/26
Permanent Offer
Permanent Production Sharing Offer (OPP): ANP publishes ...
07/04/26
Taxation
Infis Consultoria promotes the 4th Oil & Gas Taxation Se...
07/04/26
Green Hydrogen
Study at RCGI maps regions with the greatest potential f...
07/04/26
iBEM26
Goldwind advances in Bahia with factory in Camaçari and ...
27/03/26
iBEM26
Bahia showcases its bioenergy potential and reinforces i...
27/03/26
iBEM26
ESG practices in the renewable energy sector are highlig...
26/03/26
iBEM26
ABPIP highlights the role of independent producers in en...
26/03/26
iBEM26
Jerônimo Rodrigues highlights Bahia’s potential in the e...
26/03/26
Campos Basin
New oil discovery in the pre-salt of the Campos Basin
26/03/26
Royalties
Royalties: amounts related to January production for con...
26/03/26
iBEM26
iBEM 2026 begins in Salvador with debates on energy secu...
25/03/26
iBEM26
iBEM 2026 brings together specialists and discusses the ...
25/03/26
Petrobras
Museum of Petroleum and New Energies will operate in the...
19/03/26
Macaé Energy
Macaé Energy: debates focus on the strategic role of nat...
18/03/26
Macaé Energy
Macaé Energy 2026 strengthens the municipality’s positio...
17/03/26
Macaé Energy
With record-breaking attendance, the Macaé Energy trade ...
17/03/26
Offshore Technology & Subsea Engineering
Trendsetter Vulcan Offshore Customizes Tethered BOP Tech...
17/03/26
Macaé Energy
FIRJAN: Technical Conference is a Highlight of Macaé Ene...
16/03/26
Permanent Offer
Inclusion of 15 New Blocks in Permanent Offer (OPP) Bid ...
14/03/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.