Campos Basin

PetroRio starts production of the fifth well of Tubarão Martelo in BC

T&B Petroleum/Press Release
19/08/2020 20:30
PetroRio starts production of the fifth well of Tubarão Martelo in BC Imagem: FPSO OSX-3 Visualizações: 1524 (0) (0) (0) (0)

Petro Rio informs the positive result of the first phase of the campaign to revitalize the Tubarão Martelo Field.

 

The first phase of the revitalization campaign included the workover (submersible pump exchange) of the TBMT-2HP well and the connection of a fifth producer well (TBMT-4HP) to the FPSO OSX-3, owned by PetroRio.

 

In June 2020, Dommo Energia, then operator of the Tubarão Martelo Field, released the positive result of the workover carried out at the TBMT-2HP well, which increased the Field's production to approximately 7,000 barrels per day.

 

After this first stage, the TBMT-4HP well was connected, which started production with an initial flow of approximately 3,000 barrels of oil per day, thus increasing the production of the Tubarão Martelo field to 10,000 barrels per day, that is, , an increase of 40%.

 

The revitalization of mature fields is a fundamental part of PetroRio's strategy and has an important role in the continuous reduction of the lifting cost per barrel of the Company, in the continuous increase in the recovery factor of the fields operated and in the continuous increase in the economic life of the assets.

 

Tubarão Martelo with Polvo Tieback 

PetroRio intends to perform the tieback of the Polvo and Tubarão Martelo fields in 2021 and estimates a Capex of around US $ 45 million, much of which will be spent during the first half. In addition, the Company plans to take the opportunity to connect the TBMT-10H well, the sixth production well in Tubarão Martelo, which may require additional Capex of US $ 20 to US $ 25 million.

 

Finally, PetroRio thanks the teams of both companies for their efforts and work during this important period.

Most Read Today
see see
Pre-Salt
MODEC FPSOs Boost Oil and Gas Production, According to A...
29/05/25
Celebration
ANP’s BDEP Turns 25
29/05/25
Bahia Oil & Gas Energy 2025
Bahia Oil and Gas 2025 opens with strategic discussions ...
29/05/25
Sergipe Oil & Gas 2025
June 3rd Marks the Launch of Sergipe Oil & Gas 2025
29/05/25
Bahia Oil & Gas Energy 2025
Tiger Rentank marks its presence on the first day of Bah...
29/05/25
Partnership
ANP partners with the Navy to begin work on the extensio...
27/05/25
Bahia Oil & Gas Energy 2025
Authorities confirm participation in Brazil's second lar...
27/05/25
Pre-Salt
Libra Consortium announces first oil from Mero-4 FPSO in...
27/05/25
Permanent Offer
5th Cycle of the Permanent Concession Offer: Bidding Seq...
27/05/25
OTC Houston 2025
Brazilian Companies Generate US$316 Million in Deals Dur...
22/05/25
Bahia Oil & Gas Energy 2025
The Largest Oil and Gas Event in Northern and Northeaste...
22/05/25
Pre-Salt
ANP Authorizes Start of Operations for Platform in the M...
22/05/25
ANP
Amounts related to March production from concession and ...
22/05/25
Bahia Oil & Gas Energy 2025
Tenaris highlights field-proven solutions for onshore pr...
22/05/25
Results
Oil Production Under Production-Sharing Regime Surpasses...
21/05/25
Equatorial Margin
Petrobras Obtains Authorization from Ibama for Deepwater...
21/05/25
International Event
4 Weeks to Go: North America’s Largest CCUS Event Approaches
20/05/25
Bahia Oil & Gas Energy 2025
BOGE25 to Offer Business Opportunities for Oil and Gas C...
16/05/25
Petrobras
The Búzios and Atapu fields received nearly the entire U...
13/05/25
Petrobras
Petrobras informs about shareholder remuneration
13/05/25
Pre-Salt
Petrobras informs about new oil discovery in the Santos ...
09/05/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.