PetroRio starts production of the fifth well of Tubarão Martelo in BC

T&B Petroleum/Press Release
19/08/2020 20:30
PetroRio starts production of the fifth well of Tubarão Martelo in BC Imagem: FPSO OSX-3 Visualizações: 2599 (0) (0) (0) (0)

Petro Rio informs the positive result of the first phase of the campaign to revitalize the Tubarão Martelo Field.

 

The first phase of the revitalization campaign included the workover (submersible pump exchange) of the TBMT-2HP well and the connection of a fifth producer well (TBMT-4HP) to the FPSO OSX-3, owned by PetroRio.

 

In June 2020, Dommo Energia, then operator of the Tubarão Martelo Field, released the positive result of the workover carried out at the TBMT-2HP well, which increased the Field's production to approximately 7,000 barrels per day.

 

After this first stage, the TBMT-4HP well was connected, which started production with an initial flow of approximately 3,000 barrels of oil per day, thus increasing the production of the Tubarão Martelo field to 10,000 barrels per day, that is, , an increase of 40%.

 

The revitalization of mature fields is a fundamental part of PetroRio's strategy and has an important role in the continuous reduction of the lifting cost per barrel of the Company, in the continuous increase in the recovery factor of the fields operated and in the continuous increase in the economic life of the assets.

 

Tubarão Martelo with Polvo Tieback 

PetroRio intends to perform the tieback of the Polvo and Tubarão Martelo fields in 2021 and estimates a Capex of around US $ 45 million, much of which will be spent during the first half. In addition, the Company plans to take the opportunity to connect the TBMT-10H well, the sixth production well in Tubarão Martelo, which may require additional Capex of US $ 20 to US $ 25 million.

 

Finally, PetroRio thanks the teams of both companies for their efforts and work during this important period.

Most Read Today
see see
Agreement
Wärtsilä Lifecycle agreement renewed to maintain safe, r...
22/10/25
Petrobras
Petrobras receives operating license for deepwater explo...
20/10/25
Equatorial Margin
License Grant for Drilling in the Equatorial Margin Is P...
20/10/25
Equatorial Margin
ABESPetro Statement on the Licensing of the Equatorial M...
20/10/25
Energy Transition
BNDES, Petrobras, and Finep select Valetec to manage the...
20/10/25
Pre-Salt
Petrobras and PPSA sign equalization agreement for Jubar...
20/10/25
WPC Energy Youth Forum
Kuwait to Host 8th WPC Energy Youth Forum in October 2025
20/10/25
Exports
Petrobras signs contract to sell six million barrels of ...
20/10/25
Petrobras
Petrobras puts the Harpia supercomputer into operation
10/10/25
PPSA
PPSA Publishes Notice for the Non-Contracted Areas Auction
10/10/25
ROG.e
IBP Launches the New ROG.e: The World’s Largest Energy F...
10/10/25
Pre-Salt
CNPE Sets Minimum Value of BRL 10.2 Billion for the Unio...
08/10/25
Natural Gas
Petrobras Carries Out First Natural Gas Import from Arge...
08/10/25
Agreement
Seagems renews Wärtsilä Lifecycle Agreement to support t...
07/10/25
Pre-Salt
Petrobras begins contracting for the construction of FPS...
03/10/25
International Company News
Alkhorayef Petroleum Company acquires GRC Technologies, ...
01/10/25
Pre-Salt
FPSO P-78 arrives at the Búzios Field
01/10/25
RD&I
Brazil Has the Capacity to Develop Its Own Technology fo...
01/10/25
Equatorial Margin
Ibama Approves Pre-Operational Assessment (APO) Conducte...
26/09/25
Sustainable Aviation
Embraer Advances SAF Studies Following Acquisition of Bi...
26/09/25
International Company News
ExxonMobil Guyana Expands Capacity With Seventh Offshore...
24/09/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.