North Sea

Statoil selects concept for the Johan Sverdrup field

The field will be developed in multiple phases.

Statoil
13/02/2014 11:27
Visualizações: 2791 (0) (0) (0) (0)

 

Statoil and the partners in the Johan Sverdrup field have decided on a concept for the first development phase. The partners have agreed on a field centre consisting of four installations and power from shore. The partners have decided on power from shore for the Johan Sverdrup field in the first phase, which will reduce total CO2 emissions from the Utsira High area by 60-70%. 
“This is historic. We have not made a concept selection for a field this size since the 1980s,” says Arne Sigve Nylund, executive vice president for development and production in Norway.
The field will be developed in multiple phases. The design capacity of the first phase is 315,000 barrels of oil equivalents per day field capacity (Statoil share 40%) with an expected production between 315,000 and 380,000 boe/d in the early phase. Pre-drilling of wells will contribute to a rapid production ramp-up. 
“The ambition is a recovery rate of 70% for the full field,” says Øivind Reinertsen, senior vice president of the Johan Sverdrup field. 
Investments in the first phase are estimated at between NOK 100-120 billion. These include the field centre, wells, export solutions for oil and gas, and power supply. The estimates also include contingencies and provisions for market adjustments. In addition, the first phase will facilitate measures for improved oil recovery. The partners are working continuously to lower the investment level for the first phase.
The field centre in the first phase comprises a process platform, drilling platform, riser platform and living quarter, and has been designed so as to facilitate future development. The installations have steel jackets that are linked by bridges. The water depth is approximately 120 metres in the area. 
Power from shore 
Johan Sverdrup phase 1 will be supplied with power from shore with a transformer on Kårstø delivering direct current to the riser platform, ensuring an estimated 80 MW.
As part of the plan for development and operations, scheduled to be delivered in early 2015, alternative power solutions for the future phases will be described. One of the alternatives will be power from shore to the whole Utsira High area based on updated power requirements.
“This alternative, if selected, has the potential to capture more than 90% of the total CO2 emissions from this area,” says Reinertsen.
The export solution for oil and gas from Johan Sverdrup is based on transport to shore through dedicated pipelines. The oil will be transported to the Mongstad terminal in Hordaland county. The gas will be transported via Statpipe to Kårstø in Rogaland county for processing and transport onward.
“Johan Sverdrup is the result of 40 years of development and activities on the Norwegian shelf. This is the opportunity to advance history several steps,” summarises Nylund.

Statoil and the partners in the Johan Sverdrup field have decided on a concept for the first development phase. The partners have agreed on a field centre consisting of four installations and power from shore. The partners have decided on power from shore for the Johan Sverdrup field in the first phase, which will reduce total CO2 emissions from the Utsira High area by 60-70%. 

“This is historic. We have not made a concept selection for a field this size since the 1980s,” says Arne Sigve Nylund, executive vice president for development and production in Norway.

The field will be developed in multiple phases. The design capacity of the first phase is 315,000 barrels of oil equivalents per day field capacity (Statoil share 40%) with an expected production between 315,000 and 380,000 boe/d in the early phase. Pre-drilling of wells will contribute to a rapid production ramp-up. 

“The ambition is a recovery rate of 70% for the full field,” says Øivind Reinertsen, senior vice president of the Johan Sverdrup field. 

Investments in the first phase are estimated at between NOK 100-120 billion. These include the field centre, wells, export solutions for oil and gas, and power supply. The estimates also include contingencies and provisions for market adjustments. In addition, the first phase will facilitate measures for improved oil recovery. The partners are working continuously to lower the investment level for the first phase.

The field centre in the first phase comprises a process platform, drilling platform, riser platform and living quarter, and has been designed so as to facilitate future development. The installations have steel jackets that are linked by bridges. The water depth is approximately 120 metres in the area. 

Power from shore 

Johan Sverdrup phase 1 will be supplied with power from shore with a transformer on Kårstø delivering direct current to the riser platform, ensuring an estimated 80 MW.

As part of the plan for development and operations, scheduled to be delivered in early 2015, alternative power solutions for the future phases will be described. One of the alternatives will be power from shore to the whole Utsira High area based on updated power requirements.

“This alternative, if selected, has the potential to capture more than 90% of the total CO2 emissions from this area,” says Reinertsen.


The export solution for oil and gas from Johan Sverdrup is based on transport to shore through dedicated pipelines. The oil will be transported to the Mongstad terminal in Hordaland county. The gas will be transported via Statpipe to Kårstø in Rogaland county for processing and transport onward.

“Johan Sverdrup is the result of 40 years of development and activities on the Norwegian shelf. This is the opportunity to advance history several steps,” summarises Nylund.

 

Most Read Today
see see
International
5th Congress of the Federation of Portuguese-Speaking La...
05/11/26
FIRJAN
Public-private partnership seen as vital to petrochemica...
05/11/26
Drilling
Norbe VIII, operated by Foresea, is ready to operate in ...
05/11/26
Refineries
TEM Boaventura Consortium completes lift of first reacto...
04/11/26
FIRJAN
Greater natural gas availability strengthens Rio de Jane...
03/11/26
Result
Oil and natural gas production hits a new record in Sept...
03/11/26
Pre-Salt
P-78 Platform (Búzios 6) reaches peak production of 180,...
03/11/26
Auction
Neoenergia wins Lots 1 and 7 in ANEEL Transmission Auction
30/10/26
WPC Energy
WPC Energy welcomes the Republic of Chad into membership
28/10/26
International
PortXL presents its 2026 cohort of 11 maritime startups ...
30/09/26
ADIPEC
ADIPEC 2026 set to welcome record Asian participation as...
29/09/26
ANP
Royalties: amounts referring to July production were dis...
29/09/26
25th WPC
Riyadh Takes Center Stage as Global Energy Heavyweights ...
28/09/26
ROG.e 2026
Petrobras president advocates active exploration and exp...
25/09/26
ROG.e 2026
Nikki Martin, president and CEO of EnerGeo Alliance, spo...
25/09/26
ROG.e 2026
Oil States Highlights Integration Between Engineering, M...
25/09/26
ROG.e 2026
Port of Açu and OceanPact sign agreement for expansion o...
25/09/26
ROG.e 2026
Lumina’s Role and the Impact of ROG.e 2026 on the Energy...
25/09/26
ROG.e 2026
Leaders Identify Brazil as a Pillar of Energy Security a...
24/09/26
ROG.e 2026
Firjan SENAI and Sebrae Rio Connect Small Businesses wit...
24/09/26
ROG.e 2026
PPSA Study Identifies Best Practices to Support Investme...
24/09/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.