Auction

With a forecast of R$ 21.7 billion in investments, the bidding documents for the second transmission auction of 2023 are being sent to the Federal Court of Accounts (TCU).

Lot 1, estimated at R$ 18.1 billion, will be subdivided into four sub-lots to increase competition, alongside the full lot.

T&B Petroleum/Press Office
02/08/2023 17:15
With a forecast of R$ 21.7 billion in investments, the bidding documents for the second transmission auction of 2023 are being sent to the Federal Court of Accounts (TCU). Imagem: Divulgation Visualizações: 3608 (0) (0) (0) (0)

Transmission Auction No. 2/2023 will be both one of the smallest and the largest event of its kind ever held by the National Electric Energy Agency (ANEEL). It will be one of the smallest in terms of the number of lots - only three - and the largest in terms of the estimated investment value: R$ 21.7 billion. The Collegiate Board of the Agency approved the auction notice draft on Tuesday (01/08) for the construction and maintenance of over 3,000 kilometers of transmission lines and substations, with a capacity of 9,840 megawatts (MW) in conversion capacity. The draft will be sent to the Federal Court of Accounts for review in the coming days. The auction is scheduled for December 15th at the B3 headquarters in São Paulo.

The three lots in question involve the construction of 11 projects in five states - Goiás, Maranhão, Minas Gerais, São Paulo, and Tocantins. With construction periods ranging from 60 to 72 months, they are expected to generate 36.9 thousand jobs.

One of the offered lots, Lot 1, has an estimated investment of R$ 18.1 billion. It includes the delivery of approximately 1,468 km of direct current transmission lines, crossing three states (Maranhão, Tocantins, and Goiás). Due to its complexity, Lot 1 has the longest completion period ever granted by the Agency: 72 months. This period is justified by the size of the project and the capacity of the market to meet construction demands.

After receiving 120 contributions from 21 entities during the Public Consultation No. 008/2023, ANEEL decided to subdivide Lot 1 into four sub-lots to increase competitiveness. The bidding in this case will follow the following dynamics:

  1. Interested bidders in the complete Lot 1 or any of the sub-lots must submit five envelopes to the auctioneer, with or without a valid bid for the lot and the four sub-lots. For this, they will previously register in this block, by providing a single proposal guarantee;
  2. The auctioneer will conduct two rounds: in the first, the choice will be made whether the grant will be for one contract (complete Lot 1) or 4 contracts (sub-lots), based on a comparison of the proposals presented in the envelopes. In this phase, regardless of the difference between the proposal composed of the sum of the lowest bids for the sub-lots and the best offer for the complete Lot 1, only the solution with the lowest overall value will advance;
  3. In the second round, there will be a live bid phase if there are proposals at most 5% above the lowest proposal, for the complete Lot or for each sub-lot individually, as decided in the previous stage.

A technical clarification workshop on the main points of the event is scheduled for October. After the review by the Federal Court of Accounts, the ANEEL Board foresees the publication of the notice and the bidding announcement in November.

Most Read Today
see see
Rio de Janeiro
Rio City Hall Signs Agreement to Transfer Automóvel Club...
13/03/26
Result
Porto do Açu Sets Historic Record in Cargo Handling
13/03/26
Environment
Following COP30, IBP Organizes Meeting to Debate Brazil'...
13/03/26
Jet Fuel
Resolution Approved to Revise Aviation Kerosene Quality ...
13/03/26
Biofuels
ANP to Participate in Research Project on Increasing Bio...
13/03/26
Results
Petrobras Paid R$ 277.6 Billion in Taxes and Government ...
13/03/26
FIRJAN
Despite Tariff Hikes, Oil Drives Rio's Trade Flow Up 9% ...
27/02/26
Royalties
December Production Royalty Payments Distributed to Stat...
26/02/26
Award
BRAVA Energia Wins Top Honor at OTC Houston for Atlanta ...
26/02/26
Strategic Agenda
ABPIP Presents 2026 Strategic Agenda to Chairman of the ...
26/02/26
People
TVO Enhances Project Management Expertise
26/02/26
Memorandum of Understanding
Wärtsilä and Abu Dhabi Maritime Academy explore collabor...
12/02/26
Pre-Salt
Petrobras platform P-79 arrives at the Búzios field
12/02/26
Results
Petrobras’ oil and gas production rises 11% and reaches ...
12/02/26
Permanent Offer
Comprehensive and Unprecedented Joint Statement Speeds U...
12/02/26
PPSA
MME and MMA Clear Strategic Pre-Salt Areas, Enabling the...
12/02/26
Biomethane
Biomethane in Focus with Debate on Credit, Regulation, a...
12/02/26
People
Mario Ferreira is the New Commercial Manager at Wiz Corp...
11/02/26
Visas Agreement
Brazil implements electronic VISIT Visa for Chinese citizens
22/01/26
Biofuels
Sifaeg Highlights New Investment Cycle and the Consolida...
21/01/26
Drilling
Foresea’s Norbe IX Drillship Undergoes Scheduled Mainten...
21/01/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.