Alstom completes Brazil’s first M-Upgrades on GT11N2 gas turbines at Enel´s Fortaleza power plant

Alstom
28/09/2015 16:39
Alstom completes Brazil’s first M-Upgrades on GT11N2 gas turbines at Enel´s Fortaleza power plant Imagem: Alstom Visualizações: 879 (0) (0) (0) (0)

Alstom has completed the implementation of the first M-upgrades on two GT11N2 gas turbines installed in Central Geradora Termelétrica Fortaleza (CGTF), a combined-cycle power plant owned by Enel located in the northeast of Brazil. The upgrades were successfully implemented within the 30 days window of a regular major scheduled outage, part of a contract award to Alstom in 2013 for maintenance of gas turbines, including support on site and remote support for all types of inspections until 2023.

 

The M-upgrade is a product developed by Alstom that enhances power output, efficiency and availability of the gas turbine in a flexible way through extended intervals between outages. In the case of CGTF, the product increased the capacity by more than 8MW for each gas turbine.

 

“This is an important milestone for us since it is not only about the conclusion of another successful outage in Fortaleza, but also the first time that a company does this type of upgrade in Brazil. The completion of this task reinforces that our technology and technical support will ensure high availability of the plant with a safe and reliable operation”, commented Michael Rechsteiner, Senior Vice President of Alstom Thermal Services.

 

Alstom has a long contribution to the Brazilian market for power generation. In addition to CGTF (Enel) plant, Alstom has supplied similar equipment and services for other gas fired power plants such as UTE Leonel Brizola, UTE Fernando Gasparian and Celso Furtado (Petrobras) and for CSA Siderúrgica do Atlântico (ThyssenKrupp).

Most Read Today
see see
OTC Houston 2025
Brazilian Companies Generate US$316 Million in Deals Dur...
22/05/25
Bahia Oil & Gas Energy 2025
The Largest Oil and Gas Event in Northern and Northeaste...
22/05/25
Pre-Salt
ANP Authorizes Start of Operations for Platform in the M...
22/05/25
ANP
Amounts related to March production from concession and ...
22/05/25
Bahia Oil & Gas Energy 2025
Tenaris highlights field-proven solutions for onshore pr...
22/05/25
Results
Oil Production Under Production-Sharing Regime Surpasses...
21/05/25
Equatorial Margin
Petrobras Obtains Authorization from Ibama for Deepwater...
21/05/25
International Event
4 Weeks to Go: North America’s Largest CCUS Event Approaches
20/05/25
Bahia Oil & Gas Energy 2025
BOGE25 to Offer Business Opportunities for Oil and Gas C...
16/05/25
Petrobras
The Búzios and Atapu fields received nearly the entire U...
13/05/25
Petrobras
Petrobras informs about shareholder remuneration
13/05/25
Pre-Salt
Petrobras informs about new oil discovery in the Santos ...
09/05/25
OTC Houston 2025
ABEMI reinforces strategic presence at OTC 2025
09/05/25
OTC Houston 2025
Oil States stands out at OTC Houston 2025 with award-win...
09/05/25
Natural Gas
Petrobras and Portobello establish unprecedented partner...
09/05/25
OTC Houston 2025
Offshore Technology Conference 2025: Waves of Innovation...
09/05/25
OTC Houston 2025
At OTC Houston 2025, Firjan takes part in MoU signing be...
09/05/25
Santos Basin
Karoon completes acquisition of FPSO Cidade de Itajaí
08/05/25
OTC Houston 2025
Brazilian company gains recognition at OTC with pioneeri...
08/05/25
OTC Houston 2025
Technology from Brazilian company Vidya is being used in...
08/05/25
OTC Houston 2025
Tenenge and Enseada are present at OTC 2025 in Houston
08/05/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.