Investment of $35.8 billion is planned for E&P activities.

Chevron
12/12/2013 16:52
Visualizações: 985 (0) (0) (0) (0)

 

Chevron reports a $39.8 billion capital and exploratory investment program for 2014. Investment of $35.8 billion is planned for exploration and production activities. Notable major capital investments include developments in Australia, Nigeria, the Gulf of Mexico, the Permian Basin, Kazakhstan, Angola, and the Republic of the Congo.
Planned capital spending is also directed toward improving crude oil and natural gas recovery and reducing natural field declines from existing producing assets throughout the world. About 30% of the Upstream capital program is allocated to development wells and other projects associated with current producing assets. The 2014 base program includes an increase in activity across several producing regions of North America as well as in Thailand and Indonesia.
In Australia, the Gorgon project has been under construction for four years and is almost 75% complete. The current estimate for the cost of the foundation project is $54 billion (AU$55 billion), with plant startup and first gas planned for mid-2015.
“Gorgon project economics are attractive,” said vice chairman George Kirkland. 
“We continue to make steady progress against key project milestones and are applying lessons learned to our Wheatstone development which is almost 25% complete. Approximately 75% of our combined LNG offtake from the two projects is committed under firm, long-term sales and purchase agreements. These LNG developments are two of our most important future legacy assets, representing approximately 400,000 barrels a day of net production at full capacity.”
In the Gulf of Mexico, projects under development include Jack/St. Malo, Big Foot, and Tubular Bells. The Jack/St. Malo hull is moored on location and is on schedule for a 2014 startup. The Big Foot project is forecasting a 3Q 2014 tow to location and a 2Q 2015 startup.
Global exploration funding is expected to be $3.2 billion in 2014. This planned spending includes initial appraisal of new acreage acquired over the past two years, including Australia, the Kurdistan region of Iraq, and Morocco. The program also supports continued exploration and appraisal activity in Western Australia, the Gulf of Mexico, West Africa, and in shale gas regions around the world.

Chevron reports a $39.8 billion capital and exploratory investment program for 2014. Investment of $35.8 billion is planned for exploration and production activities. Notable major capital investments include developments in Australia, Nigeria, the Gulf of Mexico, the Permian Basin, Kazakhstan, Angola, and the Republic of the Congo.


Planned capital spending is also directed toward improving crude oil and natural gas recovery and reducing natural field declines from existing producing assets throughout the world. About 30% of the Upstream capital program is allocated to development wells and other projects associated with current producing assets. The 2014 base program includes an increase in activity across several producing regions of North America as well as in Thailand and Indonesia.


In Australia, the Gorgon project has been under construction for four years and is almost 75% complete. The current estimate for the cost of the foundation project is $54 billion (AU$55 billion), with plant startup and first gas planned for mid-2015.“Gorgon project economics are attractive,” said vice chairman George Kirkland. 


“We continue to make steady progress against key project milestones and are applying lessons learned to our Wheatstone development which is almost 25% complete. Approximately 75% of our combined LNG offtake from the two projects is committed under firm, long-term sales and purchase agreements. These LNG developments are two of our most important future legacy assets, representing approximately 400,000 barrels a day of net production at full capacity.”


In the Gulf of Mexico, projects under development include Jack/St. Malo, Big Foot, and Tubular Bells. The Jack/St. Malo hull is moored on location and is on schedule for a 2014 startup. The Big Foot project is forecasting a 3Q 2014 tow to location and a 2Q 2015 startup.


Global exploration funding is expected to be $3.2 billion in 2014. This planned spending includes initial appraisal of new acreage acquired over the past two years, including Australia, the Kurdistan region of Iraq, and Morocco. The program also supports continued exploration and appraisal activity in Western Australia, the Gulf of Mexico, West Africa, and in shale gas regions around the world.

 

Most Read Today
see see
Navalshore
Firjan SENAI presents the Supplier Opportunities Network...
17/08/26
Equatorial Margin
Morpho Well: Petrobras discovers hydrocarbons in ultra-d...
15/08/26
Power Generation
Campo Grande hosts four days of debates on bioenergy and...
12/08/26
International
KPMG: fossil fuel consumption falls, despite oil's signi...
12/08/26
Fenasucro
Fenasucro & Agrocana opening highlights Brazil's leaders...
12/08/26
Event
IBP and BIP bring together leaders to discuss technology...
11/08/26
Event
Asset Management gains prominence in corporate strategy;...
11/08/26
Macaé
Foresea takes part in WSOP 2026 and reinforces that safe...
11/08/26
Sergipe-Alagoas Basin
Siemens Energy advances offshore expansion in Brazil wit...
10/08/26
Campos Basin
Raia Project Reaches New Milestones in One of Brazil’s M...
06/08/26
Permanent Offer
ANP Takes Part in Ceremony Marking the Signing of Contra...
05/08/26
SOG 2026
ABPIP Strengthens Territorial Development Agenda in Serg...
04/08/26
SOG 2026
SOG26 Surpasses the Previous Edition and Reinforces Serg...
03/08/26
People
Shell Brasil Begins a New Leadership Cycle with João San...
03/08/26
Results
ANP Releases Consolidated Data on Oil and Gas Production...
03/08/26
SOG 2026
Banco do Nordeste Has R$ 504 Million for the Energy Sect...
03/08/26
PPSA
TotalEnergies and ExxonMobil Win Atapu and Bacalhau Cargoes
31/07/26
SOG 2026
Sebrae Sergipe Strengthens Small Businesses and Expands ...
31/07/26
PPSA
PPSA Expects to Hold the First Auction of the Union’s Na...
30/07/26
SOG 2026
Sergipe Oil & Gas 2026 Begins with a Focus on Investment...
30/07/26
SOG 2026
Petrobras Director Opens Sergipe Oil & Gas with Analysis...
30/07/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.