Chevron states capital, exploratory budget for next year

Investment of $35.8 billion is planned for E&P activities.

Chevron
12/12/2013 16:52
Visualizações: 1110 (0) (0) (0) (0)

 

Chevron reports a $39.8 billion capital and exploratory investment program for 2014. Investment of $35.8 billion is planned for exploration and production activities. Notable major capital investments include developments in Australia, Nigeria, the Gulf of Mexico, the Permian Basin, Kazakhstan, Angola, and the Republic of the Congo.
Planned capital spending is also directed toward improving crude oil and natural gas recovery and reducing natural field declines from existing producing assets throughout the world. About 30% of the Upstream capital program is allocated to development wells and other projects associated with current producing assets. The 2014 base program includes an increase in activity across several producing regions of North America as well as in Thailand and Indonesia.
In Australia, the Gorgon project has been under construction for four years and is almost 75% complete. The current estimate for the cost of the foundation project is $54 billion (AU$55 billion), with plant startup and first gas planned for mid-2015.
“Gorgon project economics are attractive,” said vice chairman George Kirkland. 
“We continue to make steady progress against key project milestones and are applying lessons learned to our Wheatstone development which is almost 25% complete. Approximately 75% of our combined LNG offtake from the two projects is committed under firm, long-term sales and purchase agreements. These LNG developments are two of our most important future legacy assets, representing approximately 400,000 barrels a day of net production at full capacity.”
In the Gulf of Mexico, projects under development include Jack/St. Malo, Big Foot, and Tubular Bells. The Jack/St. Malo hull is moored on location and is on schedule for a 2014 startup. The Big Foot project is forecasting a 3Q 2014 tow to location and a 2Q 2015 startup.
Global exploration funding is expected to be $3.2 billion in 2014. This planned spending includes initial appraisal of new acreage acquired over the past two years, including Australia, the Kurdistan region of Iraq, and Morocco. The program also supports continued exploration and appraisal activity in Western Australia, the Gulf of Mexico, West Africa, and in shale gas regions around the world.

Chevron reports a $39.8 billion capital and exploratory investment program for 2014. Investment of $35.8 billion is planned for exploration and production activities. Notable major capital investments include developments in Australia, Nigeria, the Gulf of Mexico, the Permian Basin, Kazakhstan, Angola, and the Republic of the Congo.


Planned capital spending is also directed toward improving crude oil and natural gas recovery and reducing natural field declines from existing producing assets throughout the world. About 30% of the Upstream capital program is allocated to development wells and other projects associated with current producing assets. The 2014 base program includes an increase in activity across several producing regions of North America as well as in Thailand and Indonesia.


In Australia, the Gorgon project has been under construction for four years and is almost 75% complete. The current estimate for the cost of the foundation project is $54 billion (AU$55 billion), with plant startup and first gas planned for mid-2015.“Gorgon project economics are attractive,” said vice chairman George Kirkland. 


“We continue to make steady progress against key project milestones and are applying lessons learned to our Wheatstone development which is almost 25% complete. Approximately 75% of our combined LNG offtake from the two projects is committed under firm, long-term sales and purchase agreements. These LNG developments are two of our most important future legacy assets, representing approximately 400,000 barrels a day of net production at full capacity.”


In the Gulf of Mexico, projects under development include Jack/St. Malo, Big Foot, and Tubular Bells. The Jack/St. Malo hull is moored on location and is on schedule for a 2014 startup. The Big Foot project is forecasting a 3Q 2014 tow to location and a 2Q 2015 startup.


Global exploration funding is expected to be $3.2 billion in 2014. This planned spending includes initial appraisal of new acreage acquired over the past two years, including Australia, the Kurdistan region of Iraq, and Morocco. The program also supports continued exploration and appraisal activity in Western Australia, the Gulf of Mexico, West Africa, and in shale gas regions around the world.

 

Most Read
see see
ROG.e 2026
ROG.e 2026 Reinforces the DE&I Agenda in the Energy Sect...
24/09/26
ROG.e 2026
IBP Launches Publication on Energy Companies’ Socio-envi...
23/09/26
ROG.e 2026
Industry Giants and Independent Producers Accelerate Pro...
22/09/26
ROG.e 2026
Firjan Attends ROG.e 2026 Opening Ceremony and Signs Tec...
22/09/26
ROG.e 2026
ROG.e 2026 Opening Ceremony Highlights Just Energy Trans...
21/09/26
ROG.e 2026
Global Leaders Position Brazil as a Hub of Stability, At...
21/09/26
ROG.e 2026
Exclusive Interview: Pelagus targets Brazil to strengthe...
21/09/26
ROG.e 2026
At ROG.e, Firjan SENAI Holds the 30th Edition of the Sup...
21/09/26
ROG.e 2026
ROG.e 2026 kicks off next Monday (21) with global energy...
19/09/26
ROG.e 2026
Camorim invests R$ 250 million in 2026 to expand fleet a...
18/09/26
ROG.e 2026
Firjan SENAI SESI Presents New Technologies at ROG.e Dev...
18/09/26
ADIPEC 2026
ADIPEC 2026 to mobilise investment in resilient, intelli...
18/09/26
Acquisition
CoreMarine takes a decisive step to expand its offshore ...
17/09/26
ROG.e 2026
M&O and Belga Marine to Showcase Global Energy and Offsh...
17/09/26
26th WPC
WPC ENERGY announces the theme, date and location for it...
16/09/26
New Contracts
Petrobras awards Strohm a contract to supply thermoplast...
15/09/26
ROG.e 2026
Equinor Celebrates 25 Years in Brazil and Showcases Its ...
15/09/26
ROG.e 2026
Sindicom to Host Lubricants Arena at ROG.e 2026
15/09/26
ROG.e 2026
ROG.e 2026 Expected to Generate R$ 593 Million for Rio d...
14/09/26
ABPIP
Independent Producers Propose Nine Measures for the Next...
14/09/26
Products and Services
RiverTough Bearings and Seals
05/09/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.