InterMoor successfully completes life-of-field service operations in Gomez field

Gomez field is located in Mississippi Canyon Block 711.

InterMoor
06/03/2014 14:17
Visualizações: 2217 (0) (0) (0) (0)

 

InterMoor, an Acteon company, has successfully completed decommissioning operations of the Innovator platform in Gomez field, Mississippi Canyon Block 711, Gulf of Mexico. 
The scope of work, conducted in water depths of 910 m, involved disconnecting 10 risers/umbilicals; disconnecting 12 mooring lines and then towing the Innovator to Ingleside, Texas. InterMoor developed special procedures for disconnection and towing, procured rigging and tow equipment for all vessels including the Anchor Handling Vessel (AHV), FPU and tug vessels, and provided essential personnel for the AHV and FPU throughout all phases of operations.
InterMoor’s involvement with the Innovator platform dates prior to 2006 when it was a mobile offshore drilling unit (MODU) known as the Rowan Midland. At that time, the MODU was being converted by ATP to a production platform, and InterMoor provided the mooring design, project management, procurement, installation and hook-up of the mooring system. The 12-leg mooring system consisted of suction embedded plate anchors (SEPLA), stud link chain, subsea connectors and polyester mooring ropes. This was leading-edge technology at the time, as it was only the third permanent polyester mooring system installed in the Gulf of Mexico and the first permanent SEPLA mooring.
InterMoor’s next assignment on the Innovator was in 2011, providing mooring line inspection, change-out of all rig wires, and upgrading five of the mooring legs due to new Metocean regulations and possible life extension. InterMoor performed the upgraded mooring analyses, provided regulatory interface and procured the upgrade mooring components.
The success of the decommissioning programme was a result of InterMoor’s detailed understanding of the Innovator platform’s mooring system, which was gained during the operations in 2006 and 2011. Tom Fulton, InterMoor president, said, “The successful decommissioning of the Innovator proves InterMoor’s technical and operational capabilities for complete floating platform decommissioning in deep water. At a time when many operators are looking at life-of-field solutions, we are proud to have played a role at crucial times throughout the development and decommissioning of this offshore asset.”

InterMoor, an Acteon company, has successfully completed decommissioning operations of the Innovator platform in Gomez field, Mississippi Canyon Block 711, Gulf of Mexico. 


The scope of work, conducted in water depths of 910 m, involved disconnecting 10 risers/umbilicals; disconnecting 12 mooring lines and then towing the Innovator to Ingleside, Texas. InterMoor developed special procedures for disconnection and towing, procured rigging and tow equipment for all vessels including the Anchor Handling Vessel (AHV), FPU and tug vessels, and provided essential personnel for the AHV and FPU throughout all phases of operations.


InterMoor’s involvement with the Innovator platform dates prior to 2006 when it was a mobile offshore drilling unit (MODU) known as the Rowan Midland. At that time, the MODU was being converted by ATP to a production platform, and InterMoor provided the mooring design, project management, procurement, installation and hook-up of the mooring system. The 12-leg mooring system consisted of suction embedded plate anchors (SEPLA), stud link chain, subsea connectors and polyester mooring ropes. This was leading-edge technology at the time, as it was only the third permanent polyester mooring system installed in the Gulf of Mexico and the first permanent SEPLA mooring.


InterMoor’s next assignment on the Innovator was in 2011, providing mooring line inspection, change-out of all rig wires, and upgrading five of the mooring legs due to new Metocean regulations and possible life extension. InterMoor performed the upgraded mooring analyses, provided regulatory interface and procured the upgrade mooring components.


The success of the decommissioning programme was a result of InterMoor’s detailed understanding of the Innovator platform’s mooring system, which was gained during the operations in 2006 and 2011. Tom Fulton, InterMoor president, said, “The successful decommissioning of the Innovator proves InterMoor’s technical and operational capabilities for complete floating platform decommissioning in deep water. At a time when many operators are looking at life-of-field solutions, we are proud to have played a role at crucial times throughout the development and decommissioning of this offshore asset.”

 

Most Read Today
see see
Fenasucro
Future Fuel consolidates Brazilian pioneering role and b...
20/05/26
Partnership
Radix partners with Repsol Sinopec Brasil and PUCRS to c...
20/05/26
Communication
The behind-the-scenes story of communication and adverti...
20/05/26
Result
Total oil production under production-sharing regime hit...
20/05/26
BOGE2026
Global geopolitics’ impact on the local oil sector to be...
19/05/26
International Women's Day
IBP celebrates International Women at Sea Day and reinfo...
19/05/26
Pre-Salt
Mero Field in the Santos Basin Pre-Salt Receives Unprece...
14/05/26
Results
Petrobras reports net profit of R$ 32.7 billion in the f...
14/05/26
Partnership
Halliburton and Shape Digital establish strategic collab...
06/05/26
ROG.e 2026
ROG.e 2026 will bring together CEOs from TotalEnergies, ...
06/05/26
International
At OTC Houston 2026, Firjan SENAI SESI expands its reach...
06/05/26
International
At OTC Houston 2026, Firjan SENAI holds international ed...
04/05/26
Recognition
BRAVA Energia receives top global industry award for Atl...
04/05/26
International
Brazil reaffirms technological leadership at OTC Houston...
04/05/26
Pre-Salt
PPSA closes 2025 with a net profit of R$ 30.1 million
04/05/26
Results
With 5.531 million boe/d, Brazil continues with record o...
04/05/26
International
Brazil reaffirms technological leadership at OTC Houston...
02/05/26
Environment
Brazil appears among world's largest methane emitters in...
30/04/26
PPSA
Federal Government receives R$ 917.32 million from Tupi ...
07/04/26
Study
Brazil increases dependence on thermal power, but lack o...
07/04/26
Permanent Offer
Permanent Production Sharing Offer (OPP): ANP publishes ...
07/04/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.