Gulf of Mexico

InterMoor successfully completes life-of-field service operations in Gomez field

Gomez field is located in Mississippi Canyon Block 711.

InterMoor
06/03/2014 14:17
Visualizações: 1727 (0) (0) (0) (0)

 

InterMoor, an Acteon company, has successfully completed decommissioning operations of the Innovator platform in Gomez field, Mississippi Canyon Block 711, Gulf of Mexico. 
The scope of work, conducted in water depths of 910 m, involved disconnecting 10 risers/umbilicals; disconnecting 12 mooring lines and then towing the Innovator to Ingleside, Texas. InterMoor developed special procedures for disconnection and towing, procured rigging and tow equipment for all vessels including the Anchor Handling Vessel (AHV), FPU and tug vessels, and provided essential personnel for the AHV and FPU throughout all phases of operations.
InterMoor’s involvement with the Innovator platform dates prior to 2006 when it was a mobile offshore drilling unit (MODU) known as the Rowan Midland. At that time, the MODU was being converted by ATP to a production platform, and InterMoor provided the mooring design, project management, procurement, installation and hook-up of the mooring system. The 12-leg mooring system consisted of suction embedded plate anchors (SEPLA), stud link chain, subsea connectors and polyester mooring ropes. This was leading-edge technology at the time, as it was only the third permanent polyester mooring system installed in the Gulf of Mexico and the first permanent SEPLA mooring.
InterMoor’s next assignment on the Innovator was in 2011, providing mooring line inspection, change-out of all rig wires, and upgrading five of the mooring legs due to new Metocean regulations and possible life extension. InterMoor performed the upgraded mooring analyses, provided regulatory interface and procured the upgrade mooring components.
The success of the decommissioning programme was a result of InterMoor’s detailed understanding of the Innovator platform’s mooring system, which was gained during the operations in 2006 and 2011. Tom Fulton, InterMoor president, said, “The successful decommissioning of the Innovator proves InterMoor’s technical and operational capabilities for complete floating platform decommissioning in deep water. At a time when many operators are looking at life-of-field solutions, we are proud to have played a role at crucial times throughout the development and decommissioning of this offshore asset.”

InterMoor, an Acteon company, has successfully completed decommissioning operations of the Innovator platform in Gomez field, Mississippi Canyon Block 711, Gulf of Mexico. 


The scope of work, conducted in water depths of 910 m, involved disconnecting 10 risers/umbilicals; disconnecting 12 mooring lines and then towing the Innovator to Ingleside, Texas. InterMoor developed special procedures for disconnection and towing, procured rigging and tow equipment for all vessels including the Anchor Handling Vessel (AHV), FPU and tug vessels, and provided essential personnel for the AHV and FPU throughout all phases of operations.


InterMoor’s involvement with the Innovator platform dates prior to 2006 when it was a mobile offshore drilling unit (MODU) known as the Rowan Midland. At that time, the MODU was being converted by ATP to a production platform, and InterMoor provided the mooring design, project management, procurement, installation and hook-up of the mooring system. The 12-leg mooring system consisted of suction embedded plate anchors (SEPLA), stud link chain, subsea connectors and polyester mooring ropes. This was leading-edge technology at the time, as it was only the third permanent polyester mooring system installed in the Gulf of Mexico and the first permanent SEPLA mooring.


InterMoor’s next assignment on the Innovator was in 2011, providing mooring line inspection, change-out of all rig wires, and upgrading five of the mooring legs due to new Metocean regulations and possible life extension. InterMoor performed the upgraded mooring analyses, provided regulatory interface and procured the upgrade mooring components.


The success of the decommissioning programme was a result of InterMoor’s detailed understanding of the Innovator platform’s mooring system, which was gained during the operations in 2006 and 2011. Tom Fulton, InterMoor president, said, “The successful decommissioning of the Innovator proves InterMoor’s technical and operational capabilities for complete floating platform decommissioning in deep water. At a time when many operators are looking at life-of-field solutions, we are proud to have played a role at crucial times throughout the development and decommissioning of this offshore asset.”

 

Most Read Today
see see
OTC Brasil 2025
O&G exploration is key to social development and a just ...
28/10/25
OTC Brasil 2025
Experts warn regulatory instability threatens US$100 bil...
28/10/25
International Company News
Sercel Awarded Major Contract by ONGC to Supply Sercel 5...
28/10/25
Record
Petrobras announces production record of FPSO Almirante ...
28/10/25
OTC Brasil 2025
Event brings together global offshore industry leaders a...
28/10/25
OTC Brasil 2025
Petrobras participates in OTC Brasil 2025, in Rio de Janeiro
28/10/25
Petrobras
Petrobras produced 3.14 million barrels of oil equivalen...
27/10/25
FIRJAN
By 2035+, Rio de Janeiro State’s Energy Potential Could ...
23/10/25
Pre-Salt
PPSA to auction in December the first share of governmen...
23/10/25
Auction
Petrobras wins auction and leases RDJ07 terminal at the ...
23/10/25
Permanent Offer
Equinor acquires two new blocks in the Campos Basin duri...
23/10/25
OTC Brasil 2025
OTC Brasil 2025 Kicks Off in One Week with a Packed Prog...
22/10/25
Agreement
Wärtsilä Lifecycle agreement renewed to maintain safe, r...
22/10/25
Petrobras
Petrobras receives operating license for deepwater explo...
20/10/25
Equatorial Margin
License Grant for Drilling in the Equatorial Margin Is P...
20/10/25
Equatorial Margin
ABESPetro Statement on the Licensing of the Equatorial M...
20/10/25
Energy Transition
BNDES, Petrobras, and Finep select Valetec to manage the...
20/10/25
Pre-Salt
Petrobras and PPSA sign equalization agreement for Jubar...
20/10/25
WPC Energy Youth Forum
Kuwait to Host 8th WPC Energy Youth Forum in October 2025
20/10/25
Exports
Petrobras signs contract to sell six million barrels of ...
20/10/25
Petrobras
Petrobras puts the Harpia supercomputer into operation
10/10/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.