Liquified Natural Gas

Novatek, Total Approve USD 27 Billion LNG Project

Yamal LNG plant will have capacity of 16.5 million tons per year.

Novatek
19/12/2013 18:58
Visualizações: 247 (0) (0) (0) (0)

 

Novatek of Russia said on Wednesday that the Board of Directors of Yamal LNG approved a final investment decision (FID) for the LNG export project, consisting of the development of the South-Tambeyskoye gas condensate field and the construction of a natural gas liquefaction plant on the Yamal Peninsula. All of the relevant corporate approvals had been issued earlier by NOVATEK and Total, shareholders of Yamal LNG.
The Yamal LNG plant will consist of three liquefaction trains with overall capacity of 16.5 million tons per annum. Start of commissioning works at the first liquefaction train is scheduled for 2016 with the planned commercial launch of the first LNG train in 2017. The project also requires the construction of transport infrastructure including a sea-port facility and an international airport located at Sabetta (north-east of the Yamal Peninsula). Up to 16 ice-class LNG carriers of special ARC-7 design will be used to effect year-round transportation of LNG to international markets.
As part of the project implementation, main tenders have been completed and key contracts have been signed. The EPC contract has been awarded to the joint venture of Technip and JGC. Overall capital expenditures of the project are now estimated at $26.9 billion, of which $2.6 billion have already been financed by the shareholders.
As of today, the orders for long-lead items (including cryogenic heat exchangers, gas turbines, and the compressors for the liquefaction trains) have been placed; eight production wells have been drilled, more than 3,100 construction workers are already on site. Preparation of the construction site for the LNG plant has been completed, the piling of the foundation for the LNG tanks has begun, the construction of the sea-port and airport has reached an advanced stage, and more than 70% of the expected LNG production output has already been contracted.
Chairman of the Management Board of Novatek, Leonid V. Mikhelson commented “The Yamal LNG project is a transformative project for NOVATEK and a key element in the overall strategy to develop the natural gas resources on the Yamal Peninsula and increase the output of LNG from Russia. In a relatively condensed period of time we have accomplished quite a lot of work with the project establishing a very good base to move forward with confidence to implement our plans”.
Yves-Louis Darricarrère, President Upstream at Total stated “The successful sanction of Yamal LNG strengthens Total’s global portfolio to sustain post-2017 production over the next decades and further increases our presence in a high potential region of Russia in terms of gas resources. Yamal LNG has made tremendous progress in recent months and Total will join forces with Novatek by harnessing all of its expertise and effort to deliver this top-tier LNG project within schedule”.

Novatek of Russia said on Wednesday that the Board of Directors of Yamal LNG approved a final investment decision (FID) for the LNG export project, consisting of the development of the South-Tambeyskoye gas condensate field and the construction of a natural gas liquefaction plant on the Yamal Peninsula. All of the relevant corporate approvals had been issued earlier by NOVATEK and Total, shareholders of Yamal LNG.


The Yamal LNG plant will consist of three liquefaction trains with overall capacity of 16.5 million tons per annum. Start of commissioning works at the first liquefaction train is scheduled for 2016 with the planned commercial launch of the first LNG train in 2017. The project also requires the construction of transport infrastructure including a sea-port facility and an international airport located at Sabetta (north-east of the Yamal Peninsula). Up to 16 ice-class LNG carriers of special ARC-7 design will be used to effect year-round transportation of LNG to international markets.


As part of the project implementation, main tenders have been completed and key contracts have been signed. The EPC contract has been awarded to the joint venture of Technip and JGC. Overall capital expenditures of the project are now estimated at $26.9 billion, of which $2.6 billion have already been financed by the shareholders.


As of today, the orders for long-lead items (including cryogenic heat exchangers, gas turbines, and the compressors for the liquefaction trains) have been placed; eight production wells have been drilled, more than 3,100 construction workers are already on site. Preparation of the construction site for the LNG plant has been completed, the piling of the foundation for the LNG tanks has begun, the construction of the sea-port and airport has reached an advanced stage, and more than 70% of the expected LNG production output has already been contracted.


Chairman of the Management Board of Novatek, Leonid V. Mikhelson commented “The Yamal LNG project is a transformative project for NOVATEK and a key element in the overall strategy to develop the natural gas resources on the Yamal Peninsula and increase the output of LNG from Russia. In a relatively condensed period of time we have accomplished quite a lot of work with the project establishing a very good base to move forward with confidence to implement our plans”.


Yves-Louis Darricarrère, President Upstream at Total stated “The successful sanction of Yamal LNG strengthens Total’s global portfolio to sustain post-2017 production over the next decades and further increases our presence in a high potential region of Russia in terms of gas resources. Yamal LNG has made tremendous progress in recent months and Total will join forces with Novatek by harnessing all of its expertise and effort to deliver this top-tier LNG project within schedule”.

 

Most Read Today
see see
ROG.e 2026
Petrobras president advocates active exploration and exp...
25/09/26
ROG.e 2026
Nikki Martin, president and CEO of EnerGeo Alliance, spo...
25/09/26
ROG.e 2026
Oil States Highlights Integration Between Engineering, M...
25/09/26
ROG.e 2026
Port of Açu and OceanPact sign agreement for expansion o...
25/09/26
ROG.e 2026
Lumina’s Role and the Impact of ROG.e 2026 on the Energy...
25/09/26
ROG.e 2026
Leaders Identify Brazil as a Pillar of Energy Security a...
24/09/26
ROG.e 2026
Firjan SENAI and Sebrae Rio Connect Small Businesses wit...
24/09/26
ROG.e 2026
PPSA Study Identifies Best Practices to Support Investme...
24/09/26
ROG.e 2026
ROG.e 2026 Reinforces the DE&I Agenda in the Energy Sect...
24/09/26
ROG.e 2026
IBP Launches Publication on Energy Companies’ Socio-envi...
23/09/26
ROG.e 2026
Industry Giants and Independent Producers Accelerate Pro...
22/09/26
ROG.e 2026
Firjan Attends ROG.e 2026 Opening Ceremony and Signs Tec...
22/09/26
ROG.e 2026
ROG.e 2026 Opening Ceremony Highlights Just Energy Trans...
21/09/26
ROG.e 2026
Global Leaders Position Brazil as a Hub of Stability, At...
21/09/26
ROG.e 2026
Exclusive Interview: Pelagus targets Brazil to strengthe...
21/09/26
ROG.e 2026
At ROG.e, Firjan SENAI Holds the 30th Edition of the Sup...
21/09/26
ROG.e 2026
ROG.e 2026 kicks off next Monday (21) with global energy...
19/09/26
ROG.e 2026
Camorim invests R$ 250 million in 2026 to expand fleet a...
18/09/26
ROG.e 2026
Firjan SENAI SESI Presents New Technologies at ROG.e Dev...
18/09/26
ADIPEC 2026
ADIPEC 2026 to mobilise investment in resilient, intelli...
18/09/26
Acquisition
CoreMarine takes a decisive step to expand its offshore ...
17/09/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2