Liquified Natural Gas

Novatek, Total Approve USD 27 Billion LNG Project

Yamal LNG plant will have capacity of 16.5 million tons per year.

Novatek
19/12/2013 18:58
Visualizações: 248 (0) (0) (0) (0)

 

Novatek of Russia said on Wednesday that the Board of Directors of Yamal LNG approved a final investment decision (FID) for the LNG export project, consisting of the development of the South-Tambeyskoye gas condensate field and the construction of a natural gas liquefaction plant on the Yamal Peninsula. All of the relevant corporate approvals had been issued earlier by NOVATEK and Total, shareholders of Yamal LNG.
The Yamal LNG plant will consist of three liquefaction trains with overall capacity of 16.5 million tons per annum. Start of commissioning works at the first liquefaction train is scheduled for 2016 with the planned commercial launch of the first LNG train in 2017. The project also requires the construction of transport infrastructure including a sea-port facility and an international airport located at Sabetta (north-east of the Yamal Peninsula). Up to 16 ice-class LNG carriers of special ARC-7 design will be used to effect year-round transportation of LNG to international markets.
As part of the project implementation, main tenders have been completed and key contracts have been signed. The EPC contract has been awarded to the joint venture of Technip and JGC. Overall capital expenditures of the project are now estimated at $26.9 billion, of which $2.6 billion have already been financed by the shareholders.
As of today, the orders for long-lead items (including cryogenic heat exchangers, gas turbines, and the compressors for the liquefaction trains) have been placed; eight production wells have been drilled, more than 3,100 construction workers are already on site. Preparation of the construction site for the LNG plant has been completed, the piling of the foundation for the LNG tanks has begun, the construction of the sea-port and airport has reached an advanced stage, and more than 70% of the expected LNG production output has already been contracted.
Chairman of the Management Board of Novatek, Leonid V. Mikhelson commented “The Yamal LNG project is a transformative project for NOVATEK and a key element in the overall strategy to develop the natural gas resources on the Yamal Peninsula and increase the output of LNG from Russia. In a relatively condensed period of time we have accomplished quite a lot of work with the project establishing a very good base to move forward with confidence to implement our plans”.
Yves-Louis Darricarrère, President Upstream at Total stated “The successful sanction of Yamal LNG strengthens Total’s global portfolio to sustain post-2017 production over the next decades and further increases our presence in a high potential region of Russia in terms of gas resources. Yamal LNG has made tremendous progress in recent months and Total will join forces with Novatek by harnessing all of its expertise and effort to deliver this top-tier LNG project within schedule”.

Novatek of Russia said on Wednesday that the Board of Directors of Yamal LNG approved a final investment decision (FID) for the LNG export project, consisting of the development of the South-Tambeyskoye gas condensate field and the construction of a natural gas liquefaction plant on the Yamal Peninsula. All of the relevant corporate approvals had been issued earlier by NOVATEK and Total, shareholders of Yamal LNG.


The Yamal LNG plant will consist of three liquefaction trains with overall capacity of 16.5 million tons per annum. Start of commissioning works at the first liquefaction train is scheduled for 2016 with the planned commercial launch of the first LNG train in 2017. The project also requires the construction of transport infrastructure including a sea-port facility and an international airport located at Sabetta (north-east of the Yamal Peninsula). Up to 16 ice-class LNG carriers of special ARC-7 design will be used to effect year-round transportation of LNG to international markets.


As part of the project implementation, main tenders have been completed and key contracts have been signed. The EPC contract has been awarded to the joint venture of Technip and JGC. Overall capital expenditures of the project are now estimated at $26.9 billion, of which $2.6 billion have already been financed by the shareholders.


As of today, the orders for long-lead items (including cryogenic heat exchangers, gas turbines, and the compressors for the liquefaction trains) have been placed; eight production wells have been drilled, more than 3,100 construction workers are already on site. Preparation of the construction site for the LNG plant has been completed, the piling of the foundation for the LNG tanks has begun, the construction of the sea-port and airport has reached an advanced stage, and more than 70% of the expected LNG production output has already been contracted.


Chairman of the Management Board of Novatek, Leonid V. Mikhelson commented “The Yamal LNG project is a transformative project for NOVATEK and a key element in the overall strategy to develop the natural gas resources on the Yamal Peninsula and increase the output of LNG from Russia. In a relatively condensed period of time we have accomplished quite a lot of work with the project establishing a very good base to move forward with confidence to implement our plans”.


Yves-Louis Darricarrère, President Upstream at Total stated “The successful sanction of Yamal LNG strengthens Total’s global portfolio to sustain post-2017 production over the next decades and further increases our presence in a high potential region of Russia in terms of gas resources. Yamal LNG has made tremendous progress in recent months and Total will join forces with Novatek by harnessing all of its expertise and effort to deliver this top-tier LNG project within schedule”.

 

Most Read Today
see see
ROG.e 2026
M&O and Belga Marine to Showcase Global Energy and Offsh...
17/09/26
26th WPC
WPC ENERGY announces the theme, date and location for it...
16/09/26
New Contracts
Petrobras awards Strohm a contract to supply thermoplast...
15/09/26
ROG.e 2026
Equinor Celebrates 25 Years in Brazil and Showcases Its ...
15/09/26
ROG.e 2026
Sindicom to Host Lubricants Arena at ROG.e 2026
15/09/26
ROG.e 2026
ROG.e 2026 Expected to Generate R$ 593 Million for Rio d...
14/09/26
ABPIP
Independent Producers Propose Nine Measures for the Next...
14/09/26
Products and Services
RiverTough Bearings and Seals
05/09/26
International Company News
OES Group Returns to Private Ownership Following Managem...
31/08/26
Pre-Salt
Petrobras platforms P-80 and P-82, which will operate in...
31/08/26
Royalties
Values related to June production were distributed to st...
27/08/26
People
bp appoints Felipe Arbelaez head of country for Brazil
27/08/26
ROG.e 2026
ROG.e 2026 brings global leaders together to discuss the...
26/08/26
Pre-Salt
Búzios field sets monthly and daily natural gas export r...
26/08/26
Navalshore
Firjan SENAI presents the Supplier Opportunities Network...
17/08/26
Equatorial Margin
Morpho Well: Petrobras discovers hydrocarbons in ultra-d...
15/08/26
Power Generation
Campo Grande hosts four days of debates on bioenergy and...
12/08/26
International
KPMG: fossil fuel consumption falls, despite oil's signi...
12/08/26
Fenasucro
Fenasucro & Agrocana opening highlights Brazil's leaders...
12/08/26
Event
IBP and BIP bring together leaders to discuss technology...
11/08/26
Event
Asset Management gains prominence in corporate strategy;...
11/08/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2