Petrobras on scheduled stoppage of Mexilhão and Route 1

Petrobras Agency
16/08/2021 12:22
Petrobras on scheduled stoppage of Mexilhão and Route 1 Imagem: Petrobras Agency Visualizações: 2329 (0) (0) (0) (0)

Petrobras informs that the scheduled stoppage of 30 days for maintenance of the Mexilhão platform and the Route 1 gas pipeline, which transports the natural gas produced in Mexilhão and other platforms in the pre-salt and post-salt areas of the Santos Basin, will be postponed by 14 days, to August 29, 2021.


The postponement was due to an unscheduled emergency stoppage to repair equipment in the processing plant which receives the natural gas coming from the Route 2 pipeline, which also transports the natural gas produced in the Santos Basin and Campos Basin. The operation is essential to ensure the full operation of Route 2, which will guarantee market supply during the stoppage of the Route 1 pipeline.


As this is merely an adjustment to the schedule, the assumptions of supply and physical availability of the gas molecule are preserved, thus ensuring the market supply, observing the conditions agreed in the contracts.


The new schedule brought a development that is favorable to the market and the Brazilian electricity sector, since it results in a reduction of the period in which there would be the imposition of contractual restrictions on the programming of gas to customers and, consequently, an eventual increase of cost in the case of withdrawals of gas above the programmed and restricted volumes. According to the contracts, Petrobras' scheduled maintenance can last a maximum of 30 days. With the change, Petrobras will apply the restriction, if necessary, for only 16 days, between August 29th and September 13th. Thus, during the period between August 15th and 29th, normal contract conditions will be maintained. The activities of the Mexilhão stoppage and of the Route 1 gas pipeline are expected to take place until September 28th.


The new schedule will also allow for an increase in natural gas power generation if compared to the previous scenario, due to the availability of gas for plants that would have scheduled shutdowns concurrently with the stoppage of Route 1 or that would operate with alternative fuels. Thus, the stoppage of UTE Cubatão, owned by Petrobras, was rescheduled, in addition to the confirmation of availability for the consumption of natural gas for power generation for another 14 days (between August 15th and 29th) at the Araucária, Linhares, Santa Cruz, William Arjona, and Norte Fluminense plants.

 

Map of the gas flow routes (Routes 1, 2 and 3)


The adjustment in the start date of the scheduled stoppage ensures compliance with the maximum deadlines designated in standards and recommendations for inspections to be carried out as preventive maintenance and improvements in the facilities, not changing the original scope considered and ensuring continuity and safety in the operations of natural gas flow and supply.


Petrobras continues to make every effort to maximize the availability of gas to the market during the scheduled stoppage, always observing the safety of its operations and respect for the environment. Among the implemented solutions are:


• Expansion of the capacity of the Guanabara Bay Regasification Terminal from 20 million to 30 million m³/day;

• Repositioning of regasification vessel from the Pecém LNG Regasification Terminal to the Bahia Terminal (TRBA), with the capacity to offer an additional 14 million m³/day;

• Positioning in the LNG supply ships and cargo market.

Most Read Today
see see
Recognition
ABS Consulting Earns Third Elev8 GovCon Honor for Excell...
22/11/25
Award
Aed Energy Wins at the 2025 Energy Storage Awards
22/11/25
Mossoró Oil & Gas Energy 2025
PetroSupply Meeting to Boost Business at Mossoró Oil & G...
21/11/25
Results
Union’s Oil Production Reached 174 Thousand Barrels per ...
21/11/25
International Company News
TGS Extends Agreement with the Government of the Federal...
21/11/25
Company News
Belga Marine and Global Maritime Announce Strategic Part...
21/11/25
Niterói
Tomorrow Blue Economy sets Niterói in motion in the coun...
13/11/25
Cop30
ANP Participates in the Event and Advances Measures for ...
13/11/25
FIRJAN
Enaex 2025 Discusses Reindustrialization, Brazil’s Compe...
13/11/25
Mossoró Oil & Gas Energy 2025
Mossoró Oil & Gas Energy to Feature Strategic Debates in...
13/11/25
Company News
Norsul becomes the first company in Latin America to ado...
11/11/25
ADIPEC 2025
From energy to intelligence to impact: ADIPEC 2025 sets ...
07/11/25
ADIPEC 2025
ADIPEC 2025 Day 3: Energy, finance and technology leader...
07/11/25
Results
Petrobras reaches net income of R$ 32.7 billion in the t...
07/11/25
Cop30
IBP Advocates Global Criteria for a Just Energy Transition
07/11/25
Offshore
Decommissioning Takes Center Stage
07/11/25
Natural Gas
ANP Approves Action Plan on Gas Pipeline Transportation ...
07/11/25
ADIPEC 2025
AI is no longer a side project: Technology leaders at AD...
05/11/25
Environment
ANP Holds Workshop on Methane Emissions in Partnership w...
05/11/25
International Event
International Energy Event Opens Registration for Activities
05/11/25
RD&I
Norway and Brazil Launch New Joint Research Funding Call...
05/11/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.