Campos Basin

Platform P-20 resumes production

Platform is part of Marlim field production system.

Petrobras Agency
08/04/2014 14:04
Platform P-20 resumes production Imagem: Petrobras Agency Visualizações: 2017 (0) (0) (0) (0)

 

Petrobras reports that platform P-20, deployed in Marlim field, Campos Basin, restarted production on Monday, April 7, at 10:30 am. The platform was temporarily shut down due to damage caused by a fire in its chemicals system on December 26 of last year. With authorization from the competent agencies, Petrobras has taken all necessary steps to normalize operations on the P-20, in line with the most rigorous health, safety and environmental standards.
Specialized teams from various disciplines worked hard and tirelessly for around 100 days to complete the repair work. Overall, 79 professionals onshore (25 working exclusively on the operation) as well as 220 onboard were involved.
P-20 has a potential output capacity of 20,000 barrels of oil per day and is one of the platforms in the Campos Basin’s Marlim Field production system.

Petrobras reports that platform P-20, deployed in Marlim field, Campos Basin, restarted production on Monday, April 7, at 10:30 am. The platform was temporarily shut down due to damage caused by a fire in its chemicals system on December 26 of last year. With authorization from the competent agencies, Petrobras has taken all necessary steps to normalize operations on the P-20, in line with the most rigorous health, safety and environmental standards.

Specialized teams from various disciplines worked hard and tirelessly for around 100 days to complete the repair work. Overall, 79 professionals onshore (25 working exclusively on the operation) as well as 220 onboard were involved.

P-20 has a potential output capacity of 20,000 barrels of oil per day and is one of the platforms in the Campos Basin’s Marlim Field production system.

Most Read Today
see see
Agreement
Wärtsilä Lifecycle agreement renewed to maintain safe, r...
22/10/25
Petrobras
Petrobras receives operating license for deepwater explo...
20/10/25
Equatorial Margin
License Grant for Drilling in the Equatorial Margin Is P...
20/10/25
Equatorial Margin
ABESPetro Statement on the Licensing of the Equatorial M...
20/10/25
Energy Transition
BNDES, Petrobras, and Finep select Valetec to manage the...
20/10/25
Pre-Salt
Petrobras and PPSA sign equalization agreement for Jubar...
20/10/25
WPC Energy Youth Forum
Kuwait to Host 8th WPC Energy Youth Forum in October 2025
20/10/25
Exports
Petrobras signs contract to sell six million barrels of ...
20/10/25
Petrobras
Petrobras puts the Harpia supercomputer into operation
10/10/25
PPSA
PPSA Publishes Notice for the Non-Contracted Areas Auction
10/10/25
ROG.e
IBP Launches the New ROG.e: The World’s Largest Energy F...
10/10/25
Pre-Salt
CNPE Sets Minimum Value of BRL 10.2 Billion for the Unio...
08/10/25
Natural Gas
Petrobras Carries Out First Natural Gas Import from Arge...
08/10/25
Agreement
Seagems renews Wärtsilä Lifecycle Agreement to support t...
07/10/25
Pre-Salt
Petrobras begins contracting for the construction of FPS...
03/10/25
International Company News
Alkhorayef Petroleum Company acquires GRC Technologies, ...
01/10/25
Pre-Salt
FPSO P-78 arrives at the Búzios Field
01/10/25
RD&I
Brazil Has the Capacity to Develop Its Own Technology fo...
01/10/25
Equatorial Margin
Ibama Approves Pre-Operational Assessment (APO) Conducte...
26/09/25
Sustainable Aviation
Embraer Advances SAF Studies Following Acquisition of Bi...
26/09/25
International Company News
ExxonMobil Guyana Expands Capacity With Seventh Offshore...
24/09/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.