ABB has won a $103 million contract from Brazilian mining company Vale to install electrical and automation systems at a modern iron ore mine in the Carajás mountains of northern Brazil as part of a major capacity expansion.

 

This order follows a previous $140 million contract won by ABB to complete the first phase of the S11D project, supplying and installing automation and electrical equipment for the process plant that separates the ore from the spoil material.

 

With this order, ABB will supply a 230 kilovolt in-feed substation to connect the mine to the electricity grid as well as 42 secondary substations. These secondary substations will be contained in ABB’s e-houses, prefabricated, walk-in, modular, outdoor enclosures designed to house a range of electrical and automation equipment. ABB will also supply the motors driving the mine’s conveyor belts.

 

Vale is developing a sustainable mine of the future in the Amazon. The S11D will still represent an industry vanguard in 20 to 30 years. To achieve this, ABB has developed highly customized solutions and has the capability to successfully deploy these solutions on massive scale.

 

“I’m proud that ABB and Vale’s close relationship over more than 10 years has culminated in this pioneering project that sets a new standard in productivity, sustainability and safety,” said Veli-Matti Reinikkala, head of ABB’s Process Automation division. “Cross-divisional collaboration on this project is enabling tight power and automation integration, a key differentiator for ABB.”

 

ABB’s first contract for S11D, announced in September 2012, required the installation and successful commissioning of the primary transmission substation, the first of its kind in Brazil.

 

With this next phase, ABB has now been asked to extend the electrification system to the excavators, stackers, reclaimers and conveyor-belt system at the mine itself.

 

Truckless transportation will use conveyor belts to move rock and ore around the site with lower carbon emissions, reduced operating costs and greater safety than the truck-based system it is replacing. This is the first time such a solution will have been used on a large scale at an iron ore mine.

 

If the S11D mine were to be operated using conventional means, it would need around 100 off-highway trucks that consume 77 percent more diesel per year.

 

The S11D Carajás ore deposit is expected to reach a peak production capacity of 90 million tons annually.

Most Read Today
see see
ADIPEC 2025
From energy to intelligence to impact: ADIPEC 2025 sets ...
07/11/25
ADIPEC 2025
ADIPEC 2025 Day 3: Energy, finance and technology leader...
07/11/25
Results
Petrobras reaches net income of R$ 32.7 billion in the t...
07/11/25
Cop30
IBP Advocates Global Criteria for a Just Energy Transition
07/11/25
Offshore
Decommissioning Takes Center Stage
07/11/25
Natural Gas
ANP Approves Action Plan on Gas Pipeline Transportation ...
07/11/25
ADIPEC 2025
AI is no longer a side project: Technology leaders at AD...
05/11/25
Environment
ANP Holds Workshop on Methane Emissions in Partnership w...
05/11/25
International Event
International Energy Event Opens Registration for Activities
05/11/25
RD&I
Norway and Brazil Launch New Joint Research Funding Call...
05/11/25
Partnership
DeepOcean and Jana Marine enter Saudi Arabia subsea part...
04/11/25
ADIPEC 2025
ADIPEC 2025: Industry calls for policy pragmatism, embra...
04/11/25
ADIPEC 2025
Johnson Matthey: Leadership and Innovation Driving the G...
31/10/25
OTC Brasil 2025
OTC Brazil connects the Equatorial Margin’s potential to...
30/10/25
OTC Brasil 2025
New Version of ANP’s Greenhouse Gas Emissions Dynamic Da...
30/10/25
OTC Brasil 2025
Port of Açu and IKM Advance Partnership to Create Brazil...
30/10/25
OTC Brasil 2025
Port of Açu and SISTAC Sign Agreement to Provide Decommi...
29/10/25
Royalties
Royalties from August Production Distributed to States a...
29/10/25
OTC Brasil 2025
iUP Innovation Connections Links Innovation Strategy to ...
29/10/25
ANP
Permanent Production Sharing Offer: Registered Companies...
29/10/25
OTC Brasil 2025
Firjan Showcases Technology and Innovation Solutions for...
29/10/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.