Consortium approves working and investment plan for Libra in 2014

Capital for these activities is US$ 400 million.

Petrobras
24/01/2014 11:24
Consortium approves working and investment plan for Libra in 2014 Imagem: TB Petroleum Visualizações: 1975 (0) (0) (0) (0)

 

Petrobras announces that the consortium formed by Petrobras (40%), Shell (20%), Total (20%), CNOOC (10%) and CNPC (10%), along with Pré-Sal Petróleo S.A. (PPSA), has approved, on the Operational Committee meeting held on January 21st, the working and investment plan for Libra in 2014.  
The main activities included in the working plan are: seismic reprocessing in the whole area of the block; drilling of two wells starting on the 2nd half of 2014 with estimated conclusion on the 1st half of 2015; and studies for a new seismic acquisition using high-end technologies and for an extended well test forecasted for the end of 2016. The approved capital expenditure for these activities in 2014 is within a range of US$ 400 million and US$ 500 million.
The production share contract of Libra states that the exploration phase of the block will have duration of four years from the contract signature date, which happened on December 2nd, 2013. The minimum exploratory program, to be carried out during this period, includes 3D seismic acquisition for the whole block, two exploratory wells and one extended well test.
The Libra block is located in ultra deep waters of Santos Basin pre-salt and is considered a prospect of high potential. The total extension of the area is 1,547.76 km2 and was discovered by well 2-ANP-0002ARJS, drilled in 2010.

Petrobras announces that the consortium formed by Petrobras (40%), Shell (20%), Total (20%), CNOOC (10%) and CNPC (10%), along with Pré-Sal Petróleo S.A. (PPSA), has approved, on the Operational Committee meeting held on January 21st, the working and investment plan for Libra in 2014.  


The main activities included in the working plan are: seismic reprocessing in the whole area of the block; drilling of two wells starting on the 2nd half of 2014 with estimated conclusion on the 1st half of 2015; and studies for a new seismic acquisition using high-end technologies and for an extended well test forecasted for the end of 2016. The approved capital expenditure for these activities in 2014 is within a range of US$ 400 million and US$ 500 million.


The production share contract of Libra states that the exploration phase of the block will have duration of four years from the contract signature date, which happened on December 2nd, 2013. The minimum exploratory program, to be carried out during this period, includes 3D seismic acquisition for the whole block, two exploratory wells and one extended well test.


The Libra block is located in ultra deep waters of Santos Basin pre-salt and is considered a prospect of high potential. The total extension of the area is 1,547.76 km2 and was discovered by well 2-ANP-0002ARJS, drilled in 2010.

Most Read Today
see see
Rio Pipeline & Logistics 2025
Tanacas celebrates 25 years with the launch of the Smart...
11/09/25
Rio Pipeline & Logistics 2025
Offshore Projects to Strengthen Energy Security in Brazi...
11/09/25
Rio Pipeline & Logistics 2025
IBP Booth Hosts Inspiring Debate on Women in Midstream a...
11/09/25
Rio Pipeline & Logistics 2025
Rio Pipeline 2025 Exhibition Showcases Innovations in En...
11/09/25
Production
Brazil’s Federal Government Oil and Natural Gas Producti...
11/09/25
Rio Pipeline & Logistics 2025
Brazil and Argentina Close to Agreement on Natural Gas T...
11/09/25
Rio Pipeline & Logistics 2025
ITP Brasil showcases high-performance engineering soluti...
10/09/25
Rio Pipeline & Logistics 2025
Overview of investments in pipeline and logistics infras...
10/09/25
Rio Pipeline & Logistics 2025
Young talents present innovative solutions at the Young ...
10/09/25
Rio Pipeline & Logistics 2025
Ministry of Ports and Airports aims to expand the role o...
10/09/25
Auction
PPSA makes available access to the Hybrid Data Package f...
10/09/25
Rio Pipeline & Logistics 2025
Rio Pipeline & Logistics 2025 Opens with Stronger Integr...
09/09/25
Rio Pipeline & Logistics 2025
At Transpetro, Social Responsibility Initiatives Support...
09/09/25
Rio Pipeline & Logistics 2025
DNV participates in Rio Pipeline & Logistics 2025
09/09/25
Rio Pipeline & Logistics 2025
Construtora Elevação Brings Innovation, Efficiency, and ...
09/09/25
ANP
A\Sense wins ANP technology challenge with advanced opti...
09/09/25
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.