Dudgeon Offshore wind farm contracts to Siemens plc

Statoil ia a as operator.

Statoil
14/01/2014 12:14
Visualizações: 1672 (0) (0) (0) (0)

 

As operator, Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project.
The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and three separate rotor blades (154-metre rotor diameter).
The engineering work will commence in January 2014 and contributes to design development of the project's design work for foundations and electrical infrastructure. The first batch of turbines shall be ready for load out and installation January 2017.
The service contract will cover operations and maintenance of the WTGs through the first two years after installation is completed, followed by three years where Siemens plc provides Dudgeon with technicians and other agreed services.  The estimated value for both contracts is GBP 516 million.
Statoil renewable energy senior vice president Siri Espedal Kindem states that this is a significant milestone for the Dudgeon offshore wind project and its owners.
"The new turbine contract will secure planned progress in the Dudgeon project towards full operation during 2017. Technology development is fundamental to optimising offshore wind industry costs and solutions, and the use of new large turbines such as these is a main contributor to reducing offshore wind costs."
The Dudgeon Offshore Wind Farm is Statoil's second full-scale commercial offshore wind project, and a key project in Norfolk.
Once in operation, the wind farm will provide renewable energy to approximately 400,000 households in the UK market.
"This WTG contract is important for further developing the Dudgeon project towards concept selection and a final investment decision in 2014. We have gained valuable experience to build on from Sheringham Shoal from both the installation and operational phases," says Statoil offshore wind project vice president Halfdan Brustad.
"In Dudgeon we seek to optimise solutions even further to bring down electricity costs, and we will have a strong cooperation with Siemens in operation and maintenance to ensure high regularity."


As operator, Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project.


The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and three separate rotor blades (154-metre rotor diameter).


The engineering work will commence in January 2014 and contributes to design development of the project's design work for foundations and electrical infrastructure. The first batch of turbines shall be ready for load out and installation January 2017.


The service contract will cover operations and maintenance of the WTGs through the first two years after installation is completed, followed by three years where Siemens plc provides Dudgeon with technicians and other agreed services.  The estimated value for both contracts is GBP 516 million.


Statoil renewable energy senior vice president Siri Espedal Kindem states that this is a significant milestone for the Dudgeon offshore wind project and its owners.


"The new turbine contract will secure planned progress in the Dudgeon project towards full operation during 2017. Technology development is fundamental to optimising offshore wind industry costs and solutions, and the use of new large turbines such as these is a main contributor to reducing offshore wind costs."


The Dudgeon Offshore Wind Farm is Statoil's second full-scale commercial offshore wind project, and a key project in Norfolk.


Once in operation, the wind farm will provide renewable energy to approximately 400,000 households in the UK market.


"This WTG contract is important for further developing the Dudgeon project towards concept selection and a final investment decision in 2014. We have gained valuable experience to build on from Sheringham Shoal from both the installation and operational phases," says Statoil offshore wind project vice president Halfdan Brustad.


"In Dudgeon we seek to optimise solutions even further to bring down electricity costs, and we will have a strong cooperation with Siemens in operation and maintenance to ensure high regularity."

Most Read Today
see see
Sergipe Oil & Gas 2025
Sergas Highlights Progress and Expansion of Natural Gas ...
25/07/25
Permanent Offer
ANP Approves Studies for the Calcita Project, Potentiall...
25/07/25
Sergipe Oil & Gas 2025
Natural Gas Market Takes Center Stage on Second Day of S...
25/07/25
People
New Interim Director to Take Office on 7/25 at ANP’s Dir...
24/07/25
Sergipe Oil & Gas 2025
Sebrae Participates in the Opening of Sergipe Oil & Gas 2025
24/07/25
Royalties
Royalties: May Production Revenues for Concession and Tr...
24/07/25
Sergipe Oil & Gas 2025
Sergipe Reinforces National Leadership in the Energy Sec...
24/07/25
Sergipe Oil & Gas 2025
Sergipe’s Oil and Gas Potential Highlighted at SOG25 Opening
23/07/25
Sergipe Oil & Gas 2025
Sergas Participates in Sergipe Oil & Gas 2025 with Focus...
23/07/25
Sergipe Oil & Gas 2025
Fourth Edition of Sergipe Oil & Gas Highlights State’s R...
23/07/25
RD&I
ANP Holds Workshop on Private Equity Investment Fund (FIP)
23/07/25
Campos Basin
Petrobras announces Approval of the Production Individua...
23/07/25
ADIPEC 2025
ADIPEC 2025 Technical Conferences achieve record submiss...
22/07/25
People
BCCK names Andres Martinez as business development manager
21/07/25
Fenasucro
Brazil Holds Global Leadership in Renewable Cogeneration...
21/07/25
Results
Revap Achieves Historic Records in H1 with S10 Diesel an...
21/07/25
Solar Energy
Transpetro Inaugurates Solar Plant to Supply the Belém T...
21/07/25
Company News
Strohm completes successful field trials for Petrobras
16/07/25
Natural Gas
Gasmig: 39 Years of Energy, Innovation, and Commitment t...
16/07/25
Sustainability
Foresea earns Social Seal and reports significant result...
11/07/25
Results
Oil and Gas Sector Leads Dividend Distribution in 2024 w...
10/07/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2