Wind Energy

Dudgeon Offshore wind farm contracts to Siemens plc

Statoil ia a as operator.

Statoil
14/01/2014 12:14
Visualizações: 2531 (0) (0) (0) (0)

 

As operator, Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project.
The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and three separate rotor blades (154-metre rotor diameter).
The engineering work will commence in January 2014 and contributes to design development of the project's design work for foundations and electrical infrastructure. The first batch of turbines shall be ready for load out and installation January 2017.
The service contract will cover operations and maintenance of the WTGs through the first two years after installation is completed, followed by three years where Siemens plc provides Dudgeon with technicians and other agreed services.  The estimated value for both contracts is GBP 516 million.
Statoil renewable energy senior vice president Siri Espedal Kindem states that this is a significant milestone for the Dudgeon offshore wind project and its owners.
"The new turbine contract will secure planned progress in the Dudgeon project towards full operation during 2017. Technology development is fundamental to optimising offshore wind industry costs and solutions, and the use of new large turbines such as these is a main contributor to reducing offshore wind costs."
The Dudgeon Offshore Wind Farm is Statoil's second full-scale commercial offshore wind project, and a key project in Norfolk.
Once in operation, the wind farm will provide renewable energy to approximately 400,000 households in the UK market.
"This WTG contract is important for further developing the Dudgeon project towards concept selection and a final investment decision in 2014. We have gained valuable experience to build on from Sheringham Shoal from both the installation and operational phases," says Statoil offshore wind project vice president Halfdan Brustad.
"In Dudgeon we seek to optimise solutions even further to bring down electricity costs, and we will have a strong cooperation with Siemens in operation and maintenance to ensure high regularity."


As operator, Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project.


The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and three separate rotor blades (154-metre rotor diameter).


The engineering work will commence in January 2014 and contributes to design development of the project's design work for foundations and electrical infrastructure. The first batch of turbines shall be ready for load out and installation January 2017.


The service contract will cover operations and maintenance of the WTGs through the first two years after installation is completed, followed by three years where Siemens plc provides Dudgeon with technicians and other agreed services.  The estimated value for both contracts is GBP 516 million.


Statoil renewable energy senior vice president Siri Espedal Kindem states that this is a significant milestone for the Dudgeon offshore wind project and its owners.


"The new turbine contract will secure planned progress in the Dudgeon project towards full operation during 2017. Technology development is fundamental to optimising offshore wind industry costs and solutions, and the use of new large turbines such as these is a main contributor to reducing offshore wind costs."


The Dudgeon Offshore Wind Farm is Statoil's second full-scale commercial offshore wind project, and a key project in Norfolk.


Once in operation, the wind farm will provide renewable energy to approximately 400,000 households in the UK market.


"This WTG contract is important for further developing the Dudgeon project towards concept selection and a final investment decision in 2014. We have gained valuable experience to build on from Sheringham Shoal from both the installation and operational phases," says Statoil offshore wind project vice president Halfdan Brustad.


"In Dudgeon we seek to optimise solutions even further to bring down electricity costs, and we will have a strong cooperation with Siemens in operation and maintenance to ensure high regularity."

Most Read Today
see see
ADIPEC 2025
From energy to intelligence to impact: ADIPEC 2025 sets ...
07/11/25
ADIPEC 2025
ADIPEC 2025 Day 3: Energy, finance and technology leader...
07/11/25
Results
Petrobras reaches net income of R$ 32.7 billion in the t...
07/11/25
Cop30
IBP Advocates Global Criteria for a Just Energy Transition
07/11/25
Offshore
Decommissioning Takes Center Stage
07/11/25
Natural Gas
ANP Approves Action Plan on Gas Pipeline Transportation ...
07/11/25
ADIPEC 2025
AI is no longer a side project: Technology leaders at AD...
05/11/25
Environment
ANP Holds Workshop on Methane Emissions in Partnership w...
05/11/25
International Event
International Energy Event Opens Registration for Activities
05/11/25
RD&I
Norway and Brazil Launch New Joint Research Funding Call...
05/11/25
Partnership
DeepOcean and Jana Marine enter Saudi Arabia subsea part...
04/11/25
ADIPEC 2025
ADIPEC 2025: Industry calls for policy pragmatism, embra...
04/11/25
ADIPEC 2025
Johnson Matthey: Leadership and Innovation Driving the G...
31/10/25
OTC Brasil 2025
OTC Brazil connects the Equatorial Margin’s potential to...
30/10/25
OTC Brasil 2025
New Version of ANP’s Greenhouse Gas Emissions Dynamic Da...
30/10/25
OTC Brasil 2025
Port of Açu and IKM Advance Partnership to Create Brazil...
30/10/25
OTC Brasil 2025
Port of Açu and SISTAC Sign Agreement to Provide Decommi...
29/10/25
Royalties
Royalties from August Production Distributed to States a...
29/10/25
OTC Brasil 2025
iUP Innovation Connections Links Innovation Strategy to ...
29/10/25
ANP
Permanent Production Sharing Offer: Registered Companies...
29/10/25
OTC Brasil 2025
Firjan Showcases Technology and Innovation Solutions for...
29/10/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.