Petrobras on scheduled stoppage of Mexilhão and Route 1

Petrobras Agency
07/06/2021 20:28
Petrobras on scheduled stoppage of Mexilhão and Route 1 Imagem: Petrobras Agency Visualizações: 1777 (0) (0) (0) (0)

Petrobras informs that it will start on August 15th the scheduled stoppage for 30 days of the Mexilhão platform and Route 1 pipeline, which outflows natural gas produced in Mexilhão and in other pre-salt and post-salt platforms in the Santos Basin.

 

The intervention on Mexilhão platform and Route 1 gas pipeline was planned several months in advance, considering its complexity and the need for contracting goods and services and coordinating the availability of resources required for its execution. The scheduled stoppage was communicated to the National Petroleum Agency in October 2020, in the Annual Production Programs (PAP) and specific meetings with the MME/CMGN - Natural Gas Monitoring Committee of the Ministry of Mines and Energy and ONS in March 2021.

 

The stoppage will enable preventive maintenance and improvements at the facilities, ensuring continuity and safety in natural gas flow and supply operations.

 

The highlights of the stoppage are:

 

  • Inspection of NR-13 equipment (Regulatory Standard on safety inspection and operation of pressure vessels, boilers and piping) and SPIE (In-house Equipment Inspection Service), which must comply with the maximum deadlines designated by the standard.
  • Compliance with Critical Inspection Recommendations with maturities from August 2021. These interventions are in equipment necessary for the gas production and delivery process and require the interruption of the systems to which they are associated, requiring the shutdown of platform operations to safe execution of planned services.
  • An important part of the activities refers to internal components of the equipment in operation and without access for inspection or testing, thus the postponement of the intervention can lead to operational risks or unscheduled stoppages, further impairing the gas flow to UTGCA - Caraguatatuba Gas Treatment Unit.

 

Therefore, the scheduled stoppage cannot be postponed, as it aims at operational safety and compliance with regulatory deadlines.

 

The company notified customers of the stoppage, under the contractually established terms, and continues to take actions to mitigate impacts on gas supply during the stoppage. The solutions involve:

 

  • Expansion of the capacity of the Guanabara Bay Regasification Terminal from 20 million to 30 million m³/day;
  • Repositioning of regasification vessel from the Pecém LNG Regasification Terminal to the Bahia Terminal (TRBA), with the capacity to offer an additional 14 million m³/day;
  • Positioning in the LNG supply ships and cargo market;
  • Negotiation of a new interruptible contract for a temporary increase in imports from Bolivia.

 

As an additional measure, Petrobras will reconcile the maintenance of Mexilhão platform and Route 1 gas pipeline with the scheduled stoppages of its own and third-party thermoelectric plants, thus reducing the demand for natural gas from these thermoelectric plants during the stoppage period and increasing their generation availability in the remaining dry period. The thermoelectric stoppage schedule was articulated in advance with the National Electric System Operator (ONS), seeking the least possible impact on the sector. The reduction in the supply of electricity generated by thermal plants will be of approximately 3 thousand megawatts during the stoppage period, compared with a total natural gas thermal generation capacity in the country of about 15 thousand megawatts and a total installed generation capacity, considering all sources, of about 170 thousand megawatts (system capacity data from the ONS website).

Most Read Today
see see
Minas Gerais
With R$ 314 million investment, pioneering macaúba biofu...
03/09/25
Recognition
Supergasbras earns Gold Seal in the Brazilian GHG Protoc...
03/09/25
FIRJAN
Brazilian industry records four consecutive months witho...
03/09/25
Copel
EPE President presents future outlook for the power sector
03/09/25
FIRJAN
Together with CNI, Firjan launches business mission in t...
03/09/25
Gulf of America
C-Innovation completes successful decommissioning projec...
28/08/25
Equatorial Margin
Rig chartered by Petrobras arrives in Amapá to take part...
19/08/25
FIRJAN
Rio gains Firjan SENAI Metalworking Reference Center
19/08/25
RD&I
CEPETRO develops for Petrobras a tool that integrates mu...
19/08/25
Pre-Salt
Búzios Field surpasses the record level of 900 thousand ...
19/08/25
Logistics
PetroReconcavo and Dislub build an unprecedented oil out...
19/08/25
IBP
NAVE Program advances with 21 energy sector startups
19/08/25
International Event
The 3rd Annual World ReAM Show Returns to Dubai, Bridgin...
13/08/25
Sustainability
ATPI Expands Global Sustainability Portfolio with Brazil...
06/08/25
Results
ANP releases consolidated 2024 data in English for the r...
29/07/25
Sergipe Oil & Gas 2025
SOG25 Surpasses Expectations in Its 4th Edition and Sets...
28/07/25
Sergipe
Government of Sergipe and Petrobras Strengthen Partnersh...
28/07/25
Sergipe Oil & Gas 2025
Sergipe Oil & Gas 2025 Highlights the Competitiveness of...
25/07/25
Sergipe Oil & Gas 2025
Márcio Félix, President of ABPIP, Sees a Promising Futur...
25/07/25
Sergipe Oil & Gas 2025
Sergas Highlights Progress and Expansion of Natural Gas ...
25/07/25
Permanent Offer
ANP Approves Studies for the Calcita Project, Potentiall...
25/07/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2