Petrobras on scheduled stoppage of Mexilhão and Route 1

Petrobras Agency
07/06/2021 20:28
Petrobras on scheduled stoppage of Mexilhão and Route 1 Imagem: Petrobras Agency Visualizações: 1307 (0) (0) (0) (0)

Petrobras informs that it will start on August 15th the scheduled stoppage for 30 days of the Mexilhão platform and Route 1 pipeline, which outflows natural gas produced in Mexilhão and in other pre-salt and post-salt platforms in the Santos Basin.

 

The intervention on Mexilhão platform and Route 1 gas pipeline was planned several months in advance, considering its complexity and the need for contracting goods and services and coordinating the availability of resources required for its execution. The scheduled stoppage was communicated to the National Petroleum Agency in October 2020, in the Annual Production Programs (PAP) and specific meetings with the MME/CMGN - Natural Gas Monitoring Committee of the Ministry of Mines and Energy and ONS in March 2021.

 

The stoppage will enable preventive maintenance and improvements at the facilities, ensuring continuity and safety in natural gas flow and supply operations.

 

The highlights of the stoppage are:

 

  • Inspection of NR-13 equipment (Regulatory Standard on safety inspection and operation of pressure vessels, boilers and piping) and SPIE (In-house Equipment Inspection Service), which must comply with the maximum deadlines designated by the standard.
  • Compliance with Critical Inspection Recommendations with maturities from August 2021. These interventions are in equipment necessary for the gas production and delivery process and require the interruption of the systems to which they are associated, requiring the shutdown of platform operations to safe execution of planned services.
  • An important part of the activities refers to internal components of the equipment in operation and without access for inspection or testing, thus the postponement of the intervention can lead to operational risks or unscheduled stoppages, further impairing the gas flow to UTGCA - Caraguatatuba Gas Treatment Unit.

 

Therefore, the scheduled stoppage cannot be postponed, as it aims at operational safety and compliance with regulatory deadlines.

 

The company notified customers of the stoppage, under the contractually established terms, and continues to take actions to mitigate impacts on gas supply during the stoppage. The solutions involve:

 

  • Expansion of the capacity of the Guanabara Bay Regasification Terminal from 20 million to 30 million m³/day;
  • Repositioning of regasification vessel from the Pecém LNG Regasification Terminal to the Bahia Terminal (TRBA), with the capacity to offer an additional 14 million m³/day;
  • Positioning in the LNG supply ships and cargo market;
  • Negotiation of a new interruptible contract for a temporary increase in imports from Bolivia.

 

As an additional measure, Petrobras will reconcile the maintenance of Mexilhão platform and Route 1 gas pipeline with the scheduled stoppages of its own and third-party thermoelectric plants, thus reducing the demand for natural gas from these thermoelectric plants during the stoppage period and increasing their generation availability in the remaining dry period. The thermoelectric stoppage schedule was articulated in advance with the National Electric System Operator (ONS), seeking the least possible impact on the sector. The reduction in the supply of electricity generated by thermal plants will be of approximately 3 thousand megawatts during the stoppage period, compared with a total natural gas thermal generation capacity in the country of about 15 thousand megawatts and a total installed generation capacity, considering all sources, of about 170 thousand megawatts (system capacity data from the ONS website).

Most Read Today
see see
Business
SBM Offshore signs US$400 million Sale and Leaseback agr...
09/04/25
Vitória Petroshow 2025
Vitória PetroShow 2025 reinforces Espírito Santo’s leade...
08/04/25
Vitória Petroshow 2025
Exploration of New Blocks Could Triple Reserves and Doub...
08/04/25
Event
Espírito Santo Unveils New Yearbook Highlighting the Fut...
08/04/25
Vitória Petroshow 2025
Entrepreneurship and Energy Sector Leaders Invite You to...
07/04/25
Vitória Petroshow 2025
Márcio Felix Highlights the Strategic Importance of Vitó...
07/04/25
Vitória Petroshow 2025
Vitória Petroshow highlights Espírito Santo as a nationa...
07/04/25
OTC Houston 2025
OTC Recognizes 2025 Spotlight on New Technology® Award W...
04/04/25
Agreement
Petrobras and Braskem Sign Agreement for Carbon Capture ...
04/04/25
Energy Transition
Oil and Gas Sector Reinforces Its Commitment to Energy T...
04/04/25
Onshore
Oil and gas production in onshore fields is expected to ...
03/04/25
ANP
Proven oil reserves in Brazil increased by 5.92% in 2024.
03/04/25
E&P
Investments in exploration could reach up to US$ 2.3 bil...
03/04/25
International
Sebrae Rio: Registrations for the Technical Mission to O...
02/04/25
Company News
Global Reach Inspires OMMICA to Significant Sales Increase
31/03/25
Local Content
The National Agency of Petroleum, Natural Gas, and Biofu...
28/03/25
Pernambuco
RNEST Increases Processing Capacity with Completion of T...
28/03/25
Equatorial Margin
Petrobras Contributes to the Expansion of Brazil’s Conti...
28/03/25
iBEM25
Engineering Students Adapt Vehicle for Renewable Energy ...
28/03/25
iBEM25
Closing of iBEM 25: A Milestone in Latin America's Energ...
28/03/25
iBEM25
iBEM 25: Conference Addresses Challenges of Recycling Ma...
27/03/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.