Petrobras on scheduled stoppage of Mexilhão and Route 1

Petrobras Agency
16/08/2021 12:22
Petrobras on scheduled stoppage of Mexilhão and Route 1 Imagem: Petrobras Agency Visualizações: 1835 (0) (0) (0) (0)

Petrobras informs that the scheduled stoppage of 30 days for maintenance of the Mexilhão platform and the Route 1 gas pipeline, which transports the natural gas produced in Mexilhão and other platforms in the pre-salt and post-salt areas of the Santos Basin, will be postponed by 14 days, to August 29, 2021.


The postponement was due to an unscheduled emergency stoppage to repair equipment in the processing plant which receives the natural gas coming from the Route 2 pipeline, which also transports the natural gas produced in the Santos Basin and Campos Basin. The operation is essential to ensure the full operation of Route 2, which will guarantee market supply during the stoppage of the Route 1 pipeline.


As this is merely an adjustment to the schedule, the assumptions of supply and physical availability of the gas molecule are preserved, thus ensuring the market supply, observing the conditions agreed in the contracts.


The new schedule brought a development that is favorable to the market and the Brazilian electricity sector, since it results in a reduction of the period in which there would be the imposition of contractual restrictions on the programming of gas to customers and, consequently, an eventual increase of cost in the case of withdrawals of gas above the programmed and restricted volumes. According to the contracts, Petrobras' scheduled maintenance can last a maximum of 30 days. With the change, Petrobras will apply the restriction, if necessary, for only 16 days, between August 29th and September 13th. Thus, during the period between August 15th and 29th, normal contract conditions will be maintained. The activities of the Mexilhão stoppage and of the Route 1 gas pipeline are expected to take place until September 28th.


The new schedule will also allow for an increase in natural gas power generation if compared to the previous scenario, due to the availability of gas for plants that would have scheduled shutdowns concurrently with the stoppage of Route 1 or that would operate with alternative fuels. Thus, the stoppage of UTE Cubatão, owned by Petrobras, was rescheduled, in addition to the confirmation of availability for the consumption of natural gas for power generation for another 14 days (between August 15th and 29th) at the Araucária, Linhares, Santa Cruz, William Arjona, and Norte Fluminense plants.

 

Map of the gas flow routes (Routes 1, 2 and 3)


The adjustment in the start date of the scheduled stoppage ensures compliance with the maximum deadlines designated in standards and recommendations for inspections to be carried out as preventive maintenance and improvements in the facilities, not changing the original scope considered and ensuring continuity and safety in the operations of natural gas flow and supply.


Petrobras continues to make every effort to maximize the availability of gas to the market during the scheduled stoppage, always observing the safety of its operations and respect for the environment. Among the implemented solutions are:


• Expansion of the capacity of the Guanabara Bay Regasification Terminal from 20 million to 30 million m³/day;

• Repositioning of regasification vessel from the Pecém LNG Regasification Terminal to the Bahia Terminal (TRBA), with the capacity to offer an additional 14 million m³/day;

• Positioning in the LNG supply ships and cargo market.

Most Read Today
see see
Biomethane
Presidente Prudente (SP) Begins R$12 Million Biomethane ...
10/07/25
E&P
Hitachi Energy to evaluate electrification of offshore p...
10/07/25
Digitalization
TGS and Equinor Collaborate to Drive Digital Transformat...
10/07/25
People
Julia Cruz Appointed as New Secretary of Green Economy, ...
03/07/25
Sustainability
ABB among TIME’s World’s Most Sustainable Companies
03/07/25
Biofuels
Brazil Can Lead the Decarbonization of International Tra...
03/07/25
Pre-Salt
Oil States signs contracts to supply rigid jumpers for S...
03/07/25
Electric Energy
SMEs: Seven Tips for Joining the Free Energy Market
03/07/25
Energy Transition
CCEE Highlights Leadership in Energy Transition at EVEX ...
03/07/25
Award
WPC Energy Announces Vicki Hollub as Recipient of the Pr...
01/07/25
ANP
Final Results of the PRH-ANP 2025 Announced
01/07/25
Wind Energy
New Provisional Measure Will Not Be Enough to Counter Ha...
30/06/25
International
Oil discovery in the Johan Castberg area in the Barents Sea
30/06/25
Fuels
Gasoline Drops Just 0.78% in June Despite Petrobras' 5.6...
30/06/25
Event
Brazil Advances Energy Transition with E30 and B15, Rein...
30/06/25
People
Patricia Pradal Appointed as New President of Chevron So...
30/06/25
Results
ANP Releases Consolidated Data for the Regulated Sector ...
30/06/25
Ethanol
Ethanol Prices Rise in the Last Week of June
30/06/25
People
Fulkrum appoints Louisa Poole as Chief Financial Officer
26/06/25
International Company News
Johan Castberg producing at full capacity
25/06/25
Decarbonization
EPE to Launch Analysis on Decarbonization of Brazilian E...
13/06/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2