Petrobras on scheduled stoppage of Mexilhão and Route 1

Petrobras Agency
16/08/2021 12:22
Petrobras on scheduled stoppage of Mexilhão and Route 1 Imagem: Petrobras Agency Visualizações: 3558 (0) (0) (0) (0)

Petrobras informs that the scheduled stoppage of 30 days for maintenance of the Mexilhão platform and the Route 1 gas pipeline, which transports the natural gas produced in Mexilhão and other platforms in the pre-salt and post-salt areas of the Santos Basin, will be postponed by 14 days, to August 29, 2021.


The postponement was due to an unscheduled emergency stoppage to repair equipment in the processing plant which receives the natural gas coming from the Route 2 pipeline, which also transports the natural gas produced in the Santos Basin and Campos Basin. The operation is essential to ensure the full operation of Route 2, which will guarantee market supply during the stoppage of the Route 1 pipeline.


As this is merely an adjustment to the schedule, the assumptions of supply and physical availability of the gas molecule are preserved, thus ensuring the market supply, observing the conditions agreed in the contracts.


The new schedule brought a development that is favorable to the market and the Brazilian electricity sector, since it results in a reduction of the period in which there would be the imposition of contractual restrictions on the programming of gas to customers and, consequently, an eventual increase of cost in the case of withdrawals of gas above the programmed and restricted volumes. According to the contracts, Petrobras' scheduled maintenance can last a maximum of 30 days. With the change, Petrobras will apply the restriction, if necessary, for only 16 days, between August 29th and September 13th. Thus, during the period between August 15th and 29th, normal contract conditions will be maintained. The activities of the Mexilhão stoppage and of the Route 1 gas pipeline are expected to take place until September 28th.


The new schedule will also allow for an increase in natural gas power generation if compared to the previous scenario, due to the availability of gas for plants that would have scheduled shutdowns concurrently with the stoppage of Route 1 or that would operate with alternative fuels. Thus, the stoppage of UTE Cubatão, owned by Petrobras, was rescheduled, in addition to the confirmation of availability for the consumption of natural gas for power generation for another 14 days (between August 15th and 29th) at the Araucária, Linhares, Santa Cruz, William Arjona, and Norte Fluminense plants.

 

Map of the gas flow routes (Routes 1, 2 and 3)


The adjustment in the start date of the scheduled stoppage ensures compliance with the maximum deadlines designated in standards and recommendations for inspections to be carried out as preventive maintenance and improvements in the facilities, not changing the original scope considered and ensuring continuity and safety in the operations of natural gas flow and supply.


Petrobras continues to make every effort to maximize the availability of gas to the market during the scheduled stoppage, always observing the safety of its operations and respect for the environment. Among the implemented solutions are:


• Expansion of the capacity of the Guanabara Bay Regasification Terminal from 20 million to 30 million m³/day;

• Repositioning of regasification vessel from the Pecém LNG Regasification Terminal to the Bahia Terminal (TRBA), with the capacity to offer an additional 14 million m³/day;

• Positioning in the LNG supply ships and cargo market.

Most Read Today
see see
BOGE2026
Lumina Group Makes Its Presence Felt at Bahia Oil & Gas ...
29/05/26
BOGE2026
Bahia Brings Together Industry, Innovation, and Business...
28/05/26
Royalties
Amounts related to March production for concession and t...
28/05/26
BOGE2026
Oil & Gas Expansion Boosts Demand for Industrial Waste T...
28/05/26
BOGE2026
BRAVA Energia Marks Presence at Bahia Oil & Gas Energy 2...
27/05/26
IBP
Brazil Can Expand Its Prominence as a Global Energy Supp...
27/05/26
Investments
Petrobras and Transpetro announce R$ 2.8 billion in inve...
27/05/26
International Company News
Jumbo orders a new class of versatile heavy lift vessels
27/05/26
BOGE2026
The Largest Oil and Gas Event in the North and Northeast...
25/05/26
BOGE2026
With production on the rise, independent players lead di...
25/05/26
ANP
ANP Workshop Debates Boosting Oil and Gas Exploration in...
25/05/26
BOGE2026
ANP participates in Bahia Oil & Gas Energy 2026, in Salvador
25/05/26
Fenasucro
Future Fuel consolidates Brazilian pioneering role and b...
20/05/26
Partnership
Radix partners with Repsol Sinopec Brasil and PUCRS to c...
20/05/26
Communication
The behind-the-scenes story of communication and adverti...
20/05/26
Result
Total oil production under production-sharing regime hit...
20/05/26
BOGE2026
Global geopolitics’ impact on the local oil sector to be...
19/05/26
International Women's Day
IBP celebrates International Women at Sea Day and reinfo...
19/05/26
Pre-Salt
Mero Field in the Santos Basin Pre-Salt Receives Unprece...
14/05/26
Results
Petrobras reports net profit of R$ 32.7 billion in the f...
14/05/26
Partnership
Halliburton and Shape Digital establish strategic collab...
06/05/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.