Petrobras on scheduled stoppage of Mexilhão and Route 1

Petrobras Agency
16/08/2021 12:22
Petrobras on scheduled stoppage of Mexilhão and Route 1 Imagem: Petrobras Agency Visualizações: 2331 (0) (0) (0) (0)

Petrobras informs that the scheduled stoppage of 30 days for maintenance of the Mexilhão platform and the Route 1 gas pipeline, which transports the natural gas produced in Mexilhão and other platforms in the pre-salt and post-salt areas of the Santos Basin, will be postponed by 14 days, to August 29, 2021.


The postponement was due to an unscheduled emergency stoppage to repair equipment in the processing plant which receives the natural gas coming from the Route 2 pipeline, which also transports the natural gas produced in the Santos Basin and Campos Basin. The operation is essential to ensure the full operation of Route 2, which will guarantee market supply during the stoppage of the Route 1 pipeline.


As this is merely an adjustment to the schedule, the assumptions of supply and physical availability of the gas molecule are preserved, thus ensuring the market supply, observing the conditions agreed in the contracts.


The new schedule brought a development that is favorable to the market and the Brazilian electricity sector, since it results in a reduction of the period in which there would be the imposition of contractual restrictions on the programming of gas to customers and, consequently, an eventual increase of cost in the case of withdrawals of gas above the programmed and restricted volumes. According to the contracts, Petrobras' scheduled maintenance can last a maximum of 30 days. With the change, Petrobras will apply the restriction, if necessary, for only 16 days, between August 29th and September 13th. Thus, during the period between August 15th and 29th, normal contract conditions will be maintained. The activities of the Mexilhão stoppage and of the Route 1 gas pipeline are expected to take place until September 28th.


The new schedule will also allow for an increase in natural gas power generation if compared to the previous scenario, due to the availability of gas for plants that would have scheduled shutdowns concurrently with the stoppage of Route 1 or that would operate with alternative fuels. Thus, the stoppage of UTE Cubatão, owned by Petrobras, was rescheduled, in addition to the confirmation of availability for the consumption of natural gas for power generation for another 14 days (between August 15th and 29th) at the Araucária, Linhares, Santa Cruz, William Arjona, and Norte Fluminense plants.

 

Map of the gas flow routes (Routes 1, 2 and 3)


The adjustment in the start date of the scheduled stoppage ensures compliance with the maximum deadlines designated in standards and recommendations for inspections to be carried out as preventive maintenance and improvements in the facilities, not changing the original scope considered and ensuring continuity and safety in the operations of natural gas flow and supply.


Petrobras continues to make every effort to maximize the availability of gas to the market during the scheduled stoppage, always observing the safety of its operations and respect for the environment. Among the implemented solutions are:


• Expansion of the capacity of the Guanabara Bay Regasification Terminal from 20 million to 30 million m³/day;

• Repositioning of regasification vessel from the Pecém LNG Regasification Terminal to the Bahia Terminal (TRBA), with the capacity to offer an additional 14 million m³/day;

• Positioning in the LNG supply ships and cargo market.

Most Read Today
see see
Permanent Offer
Equinor acquires two new blocks in the Campos Basin duri...
23/10/25
OTC Brasil 2025
OTC Brasil 2025 Kicks Off in One Week with a Packed Prog...
22/10/25
Agreement
Wärtsilä Lifecycle agreement renewed to maintain safe, r...
22/10/25
Petrobras
Petrobras receives operating license for deepwater explo...
20/10/25
Equatorial Margin
License Grant for Drilling in the Equatorial Margin Is P...
20/10/25
Equatorial Margin
ABESPetro Statement on the Licensing of the Equatorial M...
20/10/25
Energy Transition
BNDES, Petrobras, and Finep select Valetec to manage the...
20/10/25
Pre-Salt
Petrobras and PPSA sign equalization agreement for Jubar...
20/10/25
WPC Energy Youth Forum
Kuwait to Host 8th WPC Energy Youth Forum in October 2025
20/10/25
Exports
Petrobras signs contract to sell six million barrels of ...
20/10/25
Petrobras
Petrobras puts the Harpia supercomputer into operation
10/10/25
PPSA
PPSA Publishes Notice for the Non-Contracted Areas Auction
10/10/25
ROG.e
IBP Launches the New ROG.e: The World’s Largest Energy F...
10/10/25
Pre-Salt
CNPE Sets Minimum Value of BRL 10.2 Billion for the Unio...
08/10/25
Natural Gas
Petrobras Carries Out First Natural Gas Import from Arge...
08/10/25
Agreement
Seagems renews Wärtsilä Lifecycle Agreement to support t...
07/10/25
Pre-Salt
Petrobras begins contracting for the construction of FPS...
03/10/25
International Company News
Alkhorayef Petroleum Company acquires GRC Technologies, ...
01/10/25
Pre-Salt
FPSO P-78 arrives at the Búzios Field
01/10/25
RD&I
Brazil Has the Capacity to Develop Its Own Technology fo...
01/10/25
Equatorial Margin
Ibama Approves Pre-Operational Assessment (APO) Conducte...
26/09/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.