Natural Gas

Arup Completes Detailed Engineering Design of Malampaya Depletion Compression Platform

Arup
19/02/2014 18:38
Arup Completes Detailed Engineering Design of Malampaya  Depletion Compression Platform Imagem: Arup Visualizações: 2609 (0) (0) (0) (0)

 

Arup, a multidisciplinary engineering and consulting firm with a reputation for delivering innovative and sustainable designs, announced today that it completed the substructure detailed design of the Malampaya Depletion Compression Platform, a new offshore natural gas platform to be installed in the West Philippine Sea off the coast of Palawan, Philippines. Shell Philippines Exploration B.V. (SPEX), selected Fluor Daniel Pacific, Inc. (Fluor) to design and provide procurement support for the Malampaya Phase 3 Project, which includes the Malampaya Depletion Compression Platform. Fluor appointed Arup as a subcontractor to complete the Substructure Detailed Design and also provide procurement support on substructure related matters.
            
With construction completion scheduled for 2014, this new facility supports extension of the life of the Philippines only indigenous producing natural gas source, which provides 40 to 45 percent of the power generation needs for the island of Luzon (www.malampaya.com). 
 
Arup first became involved in the Malampaya gas field in 1998 when they were commissioned to conduct feasibility studies and Front End Engineering Design (FEED). This led to Engineer Procure and Construction (EPC) phases for the initial development that included the Arup concrete gravity substructure (CGS) solution. In 2010 Arup was engaged by SPEX to develop the second fixed platform substructure. Studies were performed for floating stability, vessel sea-tow response, installation ballasting sequence and post-installation wave and seismic performance. The substructure design proposed by Arup was an adaption of the firm’s award-winning Arup Concept Elevating (ACE) platform. This specific gravity-based solution reduces foundation technical and construction risk for the client.
 
 
 
“Arup’s experience implementing similar self-installing platform designs allowed for the rapid development of an efficient design,” said Martyn Turner, SPEX engineering manager. “The firm’s ability to mobilize an established local engineering team from its Manila office reduced the in-country engineering execution risk and allowed us to come in ahead of schedule and within budget.” 
 
For this extension project, Arup configured the length and width of the platform deck to provide sufficient buoyancy for float-out from the fabricator’s facility and for its tow to the site, and the structural sizing was refined to optimize efficiency and minimize cost. 
 
Located 43 meters deep on a prepared seabed, the platform had to be configured to support 4,900 tonnes of facilities with enough stability to withstand extreme storm conditions and seismic events. Due to high seismic activity in the Philippines, detailed analyses were conducted, including a seismic hazard assessment, site response studies and liquefaction assessments. 
 
In addition to designing the substructure, Arup developed the concept for the 43 meter bridge link connecting the platform to the existing CGS platform Arup delivered in 2000. 

Arup, a multidisciplinary engineering and consulting firm with a reputation for delivering innovative and sustainable designs, announced today that it completed the substructure detailed design of the Malampaya Depletion Compression Platform, a new offshore natural gas platform to be installed in the West Philippine Sea off the coast of Palawan, Philippines. Shell Philippines Exploration B.V. (SPEX), selected Fluor Daniel Pacific, Inc. (Fluor) to design and provide procurement support for the Malampaya Phase 3 Project, which includes the Malampaya Depletion Compression Platform. Fluor appointed Arup as a subcontractor to complete the Substructure Detailed Design and also provide procurement support on substructure related matters.

 

With construction completion scheduled for 2014, this new facility supports extension of the life of the Philippines only indigenous producing natural gas source, which provides 40 to 45 percent of the power generation needs for the island of Luzon (www.malampaya.com).  


Arup first became involved in the Malampaya gas field in 1998 when they were commissioned to conduct feasibility studies and Front End Engineering Design (FEED). This led to Engineer Procure and Construction (EPC) phases for the initial development that included the Arup concrete gravity substructure (CGS) solution. In 2010 Arup was engaged by SPEX to develop the second fixed platform substructure. Studies were performed for floating stability, vessel sea-tow response, installation ballasting sequence and post-installation wave and seismic performance. The substructure design proposed by Arup was an adaption of the firm’s award-winning Arup Concept Elevating (ACE) platform. This specific gravity-based solution reduces foundation technical and construction risk for the client.  

 

 “Arup’s experience implementing similar self-installing platform designs allowed for the rapid development of an efficient design,” said Martyn Turner, SPEX engineering manager. “The firm’s ability to mobilize an established local engineering team from its Manila office reduced the in-country engineering execution risk and allowed us to come in ahead of schedule and within budget.”  


For this extension project, Arup configured the length and width of the platform deck to provide sufficient buoyancy for float-out from the fabricator’s facility and for its tow to the site, and the structural sizing was refined to optimize efficiency and minimize cost. 


Located 43 meters deep on a prepared seabed, the platform had to be configured to support 4,900 tonnes of facilities with enough stability to withstand extreme storm conditions and seismic events. Due to high seismic activity in the Philippines, detailed analyses were conducted, including a seismic hazard assessment, site response studies and liquefaction assessments. In addition to designing the substructure, Arup developed the concept for the 43 meter bridge link connecting the platform to the existing CGS platform Arup delivered in 2000. 

 

Most Read Today
see see
Partnership
Halliburton and Shape Digital establish strategic collab...
06/05/26
ROG.e
ROG.e 2026 will bring together CEOs from TotalEnergies, ...
06/05/26
International
At OTC Houston 2026, Firjan SENAI SESI expands its reach...
06/05/26
International
At OTC Houston 2026, Firjan SENAI holds international ed...
04/05/26
Recognition
BRAVA Energia receives top global industry award for Atl...
04/05/26
International
Brazil reaffirms technological leadership at OTC Houston...
04/05/26
Pre-Salt
PPSA closes 2025 with a net profit of R$ 30.1 million
04/05/26
Results
With 5.531 million boe/d, Brazil continues with record o...
04/05/26
International
Brazil reaffirms technological leadership at OTC Houston...
02/05/26
Environment
Brazil appears among world's largest methane emitters in...
30/04/26
PPSA
Federal Government receives R$ 917.32 million from Tupi ...
07/04/26
Study
Brazil increases dependence on thermal power, but lack o...
07/04/26
Permanent Offer
Permanent Production Sharing Offer (OPP): ANP publishes ...
07/04/26
Taxation
Infis Consultoria promotes the 4th Oil & Gas Taxation Se...
07/04/26
Green Hydrogen
Study at RCGI maps regions with the greatest potential f...
07/04/26
iBEM26
Goldwind advances in Bahia with factory in Camaçari and ...
27/03/26
iBEM26
Bahia showcases its bioenergy potential and reinforces i...
27/03/26
iBEM26
ESG practices in the renewable energy sector are highlig...
26/03/26
iBEM26
ABPIP highlights the role of independent producers in en...
26/03/26
iBEM26
Jerônimo Rodrigues highlights Bahia’s potential in the e...
26/03/26
Campos Basin
New oil discovery in the pre-salt of the Campos Basin
26/03/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.