Natural Gas

GE signs $ 100 million contract to expand natural gas plant in Maranhão

Agreement with Techint Engenharia e Construção and Eneva forecasts the change in the configuration of UTE Parnaíba I from single-cycle to combined-cycle and potential jump in power generation efficiency of approximately 20%.

T&B Petroleum/Press Office
23/07/2019 22:17
Visualizações: 2252 (0) (0) (0) (0)

GE Power, a business that provides innovative products and services to the power generation industry, has signed an estimated $ 100 million ($ 400 million) contract with construction company Techint to supply equipment for the Parnaíba V plant, in Maranhão.

 

“The agreement foresees the closure of the Parnaíba I Plant cycle, with the change of configuration from the single-cycle plant to the combined-cycle plant, constituting the Parnaíba V Plant, which will add 385MW to Eneva's thermoelectric generation capacity inland. from Maranhão. This is an energy efficiency project, as increasing capacity will not consume any additional gas molecules, ”says Rafael Coitinho, Eneva's engineering manager.

 

According to Daniel Meniuk, GE Power's Latin America leader, the closing cycle will improve the efficiency of the Parnaíba I plant by up to 58%. "The new configuration of the plant may also allow emissions reduction compared to the current model, thanks to the potential increase in efficiency in power generation," he says.

 

For the change in plant configuration, GE will supply a model STF-D600 steam turbine, four heat recovery boilers, a condenser and valves. Equipment delivery is scheduled for the first quarter of 2021 and installation is expected to be completed by September 2022.

 

“The project is extremely important for the country, as it increases plant efficiency by up to 20 percentage points. More thermoelectric plants are expected to be contracted in the coming years, following the growth of renewables, and natural gas represents the reliable source of energy to provide safety and stability to the grid, in parallel with intermittent sources, ”says Daniel Meniuk.

 

The expansion of UTE Parnaíba I strengthens GE's position in Brazil's largest private independent power project, with nearly 2 GW of installed natural gas generation capacity operating with seven GE class F gas turbines.

 

Eneva's Parnaíba Complex is one of the largest natural gas thermal power generation parks in the country, being the first reservoir-to-wire (R2W) venture. With 1.4 GW of installed capacity, the generation of the Complex represents 11% of Brazil's gas thermal generation capacity.

 

 

Most Read Today
see see
OTC Brasil 2025
Experts warn regulatory instability threatens US$100 bil...
28/10/25
International Company News
Sercel Awarded Major Contract by ONGC to Supply Sercel 5...
28/10/25
Record
Petrobras announces production record of FPSO Almirante ...
28/10/25
OTC Brasil 2025
Event brings together global offshore industry leaders a...
28/10/25
OTC Brasil 2025
Petrobras participates in OTC Brasil 2025, in Rio de Janeiro
28/10/25
Petrobras
Petrobras produced 3.14 million barrels of oil equivalen...
27/10/25
FIRJAN
By 2035+, Rio de Janeiro State’s Energy Potential Could ...
23/10/25
Pre-Salt
PPSA to auction in December the first share of governmen...
23/10/25
Auction
Petrobras wins auction and leases RDJ07 terminal at the ...
23/10/25
Permanent Offer
Equinor acquires two new blocks in the Campos Basin duri...
23/10/25
OTC Brasil 2025
OTC Brasil 2025 Kicks Off in One Week with a Packed Prog...
22/10/25
Agreement
Wärtsilä Lifecycle agreement renewed to maintain safe, r...
22/10/25
Petrobras
Petrobras receives operating license for deepwater explo...
20/10/25
Equatorial Margin
License Grant for Drilling in the Equatorial Margin Is P...
20/10/25
Equatorial Margin
ABESPetro Statement on the Licensing of the Equatorial M...
20/10/25
Energy Transition
BNDES, Petrobras, and Finep select Valetec to manage the...
20/10/25
Pre-Salt
Petrobras and PPSA sign equalization agreement for Jubar...
20/10/25
WPC Energy Youth Forum
Kuwait to Host 8th WPC Energy Youth Forum in October 2025
20/10/25
Exports
Petrobras signs contract to sell six million barrels of ...
20/10/25
Petrobras
Petrobras puts the Harpia supercomputer into operation
10/10/25
PPSA
PPSA Publishes Notice for the Non-Contracted Areas Auction
10/10/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.