Ithaca Expects Steady Production in 2014

In 2013 Ithaca averaged around 13,000 boe/d.

Ithaca Energy
15/01/2014 13:06
Visualizações: 126 (0) (0) (0) (0)

 

Ithaca Energy reported Wednesday that it expects its 2014 production to be roughly the same rate at that achieved in 2013. In 2013 Ithaca averaged around 13,000 barrels of oil equivalent per day, while guidance from the company for 2014 is between 11,000 and 13,000 boepd – with 95 percent of this amount being composed of oil.
Ithaca said that it expects first hydrocarbons to be produced from its Greater Stella Area hub at the end of 2014, which should result in net initial annualized production for the company of approximately 16,000 boepd.
Ithaca said that it expects its capital spending in 2014 to be approximately $295 million
Around $185 million of 2014 spending relates to Ithaca’s Greater Stella Area development, $100 million relates to investments in the company’s existing producing asset portfolio and $10 million relates to its Norwegian portfolio.
Ithaca expects a number of production enhancement activities to be completed in the Causeway Area during 2014, while its joint venture at the Don Southwest field is planning to drill a new infill production well during the year. At Athena a workover will be performed on the P4 well during the second half of the year, while extension works are to be undertaken at the Cook field.
Meanwhile, Ithaca said that operations are ongoing at the Handcross prospect in the West of Shetlands sector of the UK Continental Shelf. 
In terms of developing its business further, Ithaca said that it will continue to seek opportunities to enhance the value of its existing UK portfolio. The firm said its growth strategy remains focused on securing appraisal, development and production opportunities.

Ithaca Energy reported today that it expects its 2014 production to be roughly the same rate at that achieved in 2013. In 2013 Ithaca averaged around 13,000 barrels of oil equivalent per day, while guidance from the company for 2014 is between 11,000 and 13,000 boepd – with 95 percent of this amount being composed of oil. Company said that it expects first hydrocarbons to be produced from its Greater Stella Area hub at the end of 2014, which should result in net initial annualized production for the company of approximately 16,000 boepd. Ithaca said that it expects its capital spending in 2014 to be approximately $295 million.


Around $185 million of 2014 spending relates to Ithaca’s Greater Stella Area development, $100 million relates to investments in the company’s existing producing asset portfolio and $10 million relates to its Norwegian portfolio.


Ithaca expects a number of production enhancement activities to be completed in the Causeway Area during 2014, while its joint venture at the Don Southwest field is planning to drill a new infill production well during the year. At Athena a workover will be performed on the P4 well during the second half of the year, while extension works are to be undertaken at the Cook field. Meanwhile, Ithaca said that operations are ongoing at the Handcross prospect in the West of Shetlands sector of the UK Continental Shelf. 


In terms of developing its business further, Ithaca said that it will continue to seek opportunities to enhance the value of its existing UK portfolio. The firm said its growth strategy remains focused on securing appraisal, development and production opportunities.

 

Most Read Today
see see
International
Petrobras announces participation in exploratory block i...
15/09/25
REVAP
Revap Maintenance Shutdown Involves R$ 1 Billion Investment
15/09/25
Rio Pipeline & Logistics 2025
Tanacas celebrates 25 years with the launch of the Smart...
11/09/25
Rio Pipeline & Logistics 2025
Offshore Projects to Strengthen Energy Security in Brazi...
11/09/25
Rio Pipeline & Logistics 2025
IBP Booth Hosts Inspiring Debate on Women in Midstream a...
11/09/25
Rio Pipeline & Logistics 2025
Rio Pipeline 2025 Exhibition Showcases Innovations in En...
11/09/25
Production
Brazil’s Federal Government Oil and Natural Gas Producti...
11/09/25
Rio Pipeline & Logistics 2025
Brazil and Argentina Close to Agreement on Natural Gas T...
11/09/25
Rio Pipeline & Logistics 2025
ITP Brasil showcases high-performance engineering soluti...
10/09/25
Rio Pipeline & Logistics 2025
Overview of investments in pipeline and logistics infras...
10/09/25
Rio Pipeline & Logistics 2025
Young talents present innovative solutions at the Young ...
10/09/25
Rio Pipeline & Logistics 2025
Ministry of Ports and Airports aims to expand the role o...
10/09/25
Auction
PPSA makes available access to the Hybrid Data Package f...
10/09/25
Rio Pipeline & Logistics 2025
Rio Pipeline & Logistics 2025 Opens with Stronger Integr...
09/09/25
Rio Pipeline & Logistics 2025
At Transpetro, Social Responsibility Initiatives Support...
09/09/25
Rio Pipeline & Logistics 2025
DNV participates in Rio Pipeline & Logistics 2025
09/09/25
Rio Pipeline & Logistics 2025
Construtora Elevação Brings Innovation, Efficiency, and ...
09/09/25
ANP
A\Sense wins ANP technology challenge with advanced opti...
09/09/25
Rio Pipeline & Logistics 2025
Rio Pipeline & Logistics 2025 kicks off today, September 9
09/09/25
Minas Gerais
With R$ 314 million investment, pioneering macaúba biofu...
03/09/25
Recognition
Supergasbras earns Gold Seal in the Brazilian GHG Protoc...
03/09/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2