McDermott discusses its work on Papa Terra TLP

First production occurred in November 2013.

McDermott
06/02/2014 16:16
Visualizações: 3039 (0) (0) (0) (0)

 

McDermott discusses its work on Papa Terra TLP
McDermott International Inc., is highlighting its recent work on the Papa Terra TLP at the Topsides, Platforms and Hulls Conference & Exhibition being held at the Moody Gardens Hotel & Convention Center in Galveston, Texas.
McDermott says the project involved the first use of dry-tree floating technology offshore Brazil and the first TLP installation offshore South America. The company also says that project drew upon the proprietary technology, engineering, and construction resources of McDermott, Keppel, and FloaTEC, the joint venture company between McDermott and Keppel.
The facilities developed included the tension leg wellhead platform (TLWP), hull, topsides, tendons, and risers. Work was allocated as follows: 
Topsides engineering was by McDermott while the hull engineering was by FloaTEC. Partial procurement services were provided by the cross-company project team.
Fabrication of the piles and tendons was by McDermott’s Morgan City multi-joint welding facility. Major installation components, such as tendon buoyancy modules, were provided by McDermott Wuchuan fabrication yard in Qingdao and at McDermott's Morgan City facility. Risers, well systems, and tendon components were supplied by FloaTEC. The TLWP hull and topsides are being constructed by Keppel.
McDermott performed float-over project management and TLWP installation offshore, as well as installation of the anchor piles and tendons; with the cross-company project team responsible for commissioning.
FloaTEC will perform operations and maintenance of the TLWP for the initial three-year period of operations.
Papa Terra is a heavy crude oil field in block BC-20 of the Campos basin 110 km (68 mi) offshore Brazil in 1,190 m (3,903 ft) water depth. Petrobras is operator with 62.5% interest while Chevron holds the remaining 37.5%.
The partners made the final investment decision in January 2010 and will invest $5.2 billion on field development. First production occurred in November 2013.

McDermott International Inc., is highlighting its recent work on the Papa Terra TLP at the Topsides, Platforms and Hulls Conference & Exhibition being held at the Moody Gardens Hotel & Convention Center in Galveston, Texas.

 

McDermott says the project involved the first use of dry-tree floating technology offshore Brazil and the first TLP installation offshore South America. The company also says that project drew upon the proprietary technology, engineering, and construction resources of McDermott, Keppel, and FloaTEC, the joint venture company between McDermott and Keppel.

 

The facilities developed included the tension leg wellhead platform (TLWP), hull, topsides, tendons, and risers. Work was allocated as follows: 

 

Topsides engineering was by McDermott while the hull engineering was by FloaTEC. Partial procurement services were provided by the cross-company project team.

 

Fabrication of the piles and tendons was by McDermott’s Morgan City multi-joint welding facility. Major installation components, such as tendon buoyancy modules, were provided by McDermott Wuchuan fabrication yard in Qingdao and at McDermott's Morgan City facility. Risers, well systems, and tendon components were supplied by FloaTEC. The TLWP hull and topsides are being constructed by Keppel.

 


McDermott performed float-over project management and TLWP installation offshore, as well as installation of the anchor piles and tendons; with the cross-company project team responsible for commissioning.
FloaTEC will perform operations and maintenance of the TLWP for the initial three-year period of operations.

 

Papa Terra is a heavy crude oil field in block BC-20 of the Campos basin 110 km (68 mi) offshore Brazil in 1,190 m (3,903 ft) water depth. Petrobras is operator with 62.5% interest while Chevron holds the remaining 37.5%.

 

The partners made the final investment decision in January 2010 and will invest $5.2 billion on field development. First production occurred in November 2013.

Most Read Today
see see
International
PortXL presents its 2026 cohort of 11 maritime startups ...
30/09/26
ADIPEC
ADIPEC 2026 set to welcome record Asian participation as...
29/09/26
ANP
Royalties: amounts referring to July production were dis...
29/09/26
25th WPC
Riyadh Takes Center Stage as Global Energy Heavyweights ...
28/09/26
ROG.e 2026
Petrobras president advocates active exploration and exp...
25/09/26
ROG.e 2026
Nikki Martin, president and CEO of EnerGeo Alliance, spo...
25/09/26
ROG.e 2026
Oil States Highlights Integration Between Engineering, M...
25/09/26
ROG.e 2026
Port of Açu and OceanPact sign agreement for expansion o...
25/09/26
ROG.e 2026
Lumina’s Role and the Impact of ROG.e 2026 on the Energy...
25/09/26
ROG.e 2026
Leaders Identify Brazil as a Pillar of Energy Security a...
24/09/26
ROG.e 2026
Firjan SENAI and Sebrae Rio Connect Small Businesses wit...
24/09/26
ROG.e 2026
PPSA Study Identifies Best Practices to Support Investme...
24/09/26
ROG.e 2026
ROG.e 2026 Reinforces the DE&I Agenda in the Energy Sect...
24/09/26
ROG.e 2026
IBP Launches Publication on Energy Companies’ Socio-envi...
23/09/26
ROG.e 2026
Industry Giants and Independent Producers Accelerate Pro...
22/09/26
ROG.e 2026
Firjan Attends ROG.e 2026 Opening Ceremony and Signs Tec...
22/09/26
ROG.e 2026
ROG.e 2026 Opening Ceremony Highlights Just Energy Trans...
21/09/26
ROG.e 2026
Global Leaders Position Brazil as a Hub of Stability, At...
21/09/26
ROG.e 2026
Exclusive Interview: Pelagus targets Brazil to strengthe...
21/09/26
ROG.e 2026
At ROG.e, Firjan SENAI Holds the 30th Edition of the Sup...
21/09/26
ROG.e 2026
ROG.e 2026 kicks off next Monday (21) with global energy...
19/09/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.