Post-Salt

Petrobras reduces cost of post-salt well construction

Petrobras Agency
14/07/2020 15:16
Petrobras reduces cost of post-salt well construction Imagem: Petrobras Agency Visualizações: 325 (0) (0) (0) (0)

Petrobras informs that in early July, it completed, in half the time, the construction of the 7 GLF 49H ESS offshore well, in the Golfinho field, in the Espírito Santo Basin, 100 km from Vitória. This was the first post-salt well built with the application of the True One Trip Ultra Slender (TOTUS) concept, which consists of simplifying and reducing the time spent in the drilling and completion stages, based on optimizations and innovations inserted in the design and planning phases.

 

The pioneering use of TOTUS allowed the completion of this first well in only 44 days compared to the historical average of the field of 96 days, resulting in a cost reduction of approximately 50%, equivalent to US$ 30 million. Petrobras can apply this new concept in its new wells, in several mature fields in the post-salt, in the period from 2021 to 2025, with potential for cost reduction between US$ 20 - 35 million per well.

 

The TOTUS concept, developed and patented by Petrobras, is part of the company's effort to find technological solutions that aim to reduce costs in its activities in a safe and efficient way. The concept consists of drilling the well in only 3 phases (Ultra Slender) and the completion installed in a single maneuver (True One Trip), different from traditional configurations (4 or 5 drilling phases and 2 or more maneuvers to install the completion).

 

TOTUS can be used in certain mature fields of the post-salt where the geological and reservoir characteristics favor its application.

Most Read Today
see see
Royalties
Royalties: amounts related to January production for con...
26/03/26
iBEM26
iBEM 2026 begins in Salvador with debates on energy secu...
25/03/26
iBEM26
iBEM 2026 brings together specialists and discusses the ...
25/03/26
Petrobras
Museum of Petroleum and New Energies will operate in the...
19/03/26
Macaé Energy
Macaé Energy: debates focus on the strategic role of nat...
18/03/26
Macaé Energy
Macaé Energy 2026 strengthens the municipality’s positio...
17/03/26
Macaé Energy
With record-breaking attendance, the Macaé Energy trade ...
17/03/26
Offshore Technology & Subsea Engineering
Trendsetter Vulcan Offshore Customizes Tethered BOP Tech...
17/03/26
Macaé Energy
FIRJAN: Technical Conference is a Highlight of Macaé Ene...
16/03/26
Permanent Offer
Inclusion of 15 New Blocks in Permanent Offer (OPP) Bid ...
14/03/26
Rio de Janeiro
Rio City Hall Signs Agreement to Transfer Automóvel Club...
13/03/26
Result
Porto do Açu Sets Historic Record in Cargo Handling
13/03/26
Environment
Following COP30, IBP Organizes Meeting to Debate Brazil'...
13/03/26
Jet Fuel
Resolution Approved to Revise Aviation Kerosene Quality ...
13/03/26
Biofuels
ANP to Participate in Research Project on Increasing Bio...
13/03/26
Results
Petrobras Paid R$ 277.6 Billion in Taxes and Government ...
13/03/26
North Sea
Two new discoveries in the North Sea
11/03/26
Macaé Energy
At Macaé Energy 2026, FIRJAN Promotes Special Edition of...
09/03/26
iBEM26
Innovation, ESG, and Sustainability
06/03/26
iBEM26
Artificial Intelligence drives increased demand for elec...
02/03/26
FIRJAN
Despite Tariff Hikes, Oil Drives Rio's Trade Flow Up 9% ...
27/02/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.