ENSCO 104 continues work at Blackwood-2 well in permit NT/P68

MEO Australia Limited disclosed that at 06:00 Darwin time Friday.

MEO Australia
06/12/2013 11:38
Visualizações: 229 (0) (0) (0) (0)

 

MEO Australia Limited disclosed that at 06:00 Darwin time Friday Dec. 6, the jackup Ensco 104 (400' ILC)  was preparing to commence the wireline logging program having drilled the Blackwood-2 well in Permit NT/P68 offshore Australia's Northern Territory to total depth at 11,236 feet (3,425 meters) measured depth below rotary table (MDRT).
Operational progress since the previous report is summarized in the table below.
PROGRESS SUMMARY
Progress since last report:
Drilled 8.5 inch (216 millimeters) hole from 10,334 feet (3,150 meters) MDRT to 10,538 feet (3,226 meters) MDRT
Cut core from 10,538 feet (3,226 meters) to 10,771 feet (3,283 meters) MDRT (recovered 196 feet or 60 meters)
Drilled 8.5 inch (216 millimeters) hole from 10,771 feet (3,283 meters) MDRT to 11,236 feet (3,425 meters) MDRT (Total Depth)
Prepared to commence wireline logging program
Present Operation (at 06:00 Darwin time, Dec. 6):
Preparing to conduct wireline logging program
Outlook:
Production test (if warranted)
Plug and abandon well
BACKGROUND
The Blackwood-2 appraisal well is located approximately 4.9 miles (8 kilometers) from the Blackwood-1 discovery well. Further information regarding the NT/P68 Exploration Permit is available on the MEO website.
The drilling of Blackwood-2 is an obligation under the NT/P68 Farm-in Agreement (FIA) dated May 17, 2011 between Eni Australia Limited (Eni) and MEO. Under the FIA and subsequent amendment, MEO’s 50 percent participating interest share of the costs of the well will be carried.

MEO Australia Limited disclosed that at 06:00 Darwin time Friday Dec. 6, the jackup Ensco 104 (400' ILC)  was preparing to commence the wireline logging program having drilled the Blackwood-2 well in Permit NT/P68 offshore Australia's Northern Territory to total depth at 11,236 feet (3,425 meters) measured depth below rotary table (MDRT).

 

Operational progress since the previous report is summarized in the table below.

 

Progress Sumary

 

Progress since last report:

 

Drilled 8.5 inch (216 millimeters) hole from 10,334 feet (3,150 meters) MDRT to 10,538 feet (3,226 meters) MDRTCut core from 10,538 feet (3,226 meters) to 10,771 feet (3,283 meters) MDRT (recovered 196 feet or 60 meters)Drilled 8.5 inch (216 millimeters) hole from 10,771 feet (3,283 meters) MDRT to 11,236 feet (3,425 meters) MDRT (Total Depth)Prepared to commence wireline logging program Present.

 

Operation (at 06:00 Darwin time, Dec. 6):

 

Preparing to conduct wireline logging program

 

Outlook:

 

Production test (if warranted)Plug and abandon wellBACKGROUNDThe Blackwood-2 appraisal well is located approximately 4.9 miles (8 kilometers) from the Blackwood-1 discovery well. Further information regarding the NT/P68 Exploration Permit is available on the MEO website.

 

The drilling of Blackwood-2 is an obligation under the NT/P68 Farm-in Agreement (FIA) dated May 17, 2011 between Eni Australia Limited (Eni) and MEO. Under the FIA and subsequent amendment, MEO’s 50 percent participating interest share of the costs of the well will be carried.

Most Read Today
see see
Royalties
Royalties: amounts referring to May production distribut...
23/07/26
Fuels
Fuel and lubricants sector registers 1.8% drop in June, ...
22/07/26
IBP
Studies point to redundancy of the export tax and extra ...
22/07/26
PPSA
7th Spot Auction: PPSA markets cargoes from Atapu and Ba...
20/07/26
Results
Union oil production reaches 244 thousand barrels per da...
17/07/26
State of Ceará
Natural gas arrives in Cariri (CE) and strengthens econo...
16/07/26
Terminals
Vast announces contract extension with PETRONAS Brasil u...
15/07/26
International
War, oil and the dollar: how global fluctuations impact ...
13/07/26
ANP
Third-party access to natural gas flow pipelines and pro...
10/07/26
Agreement
ANP and Petrobras sign agreement to bring 335 offshore w...
07/07/26
Logistics
Vast Infraestrutura and Petrobras strengthen partnership...
07/07/26
IBP Positioning
Change of the instrument does not fix the illegalities o...
07/07/26
Energy Summit
Energy Summit 2026: Embrapii technologies strengthen Bra...
22/06/26
Energy Summit
Biodiesel and renewable fuels move to the center of the ...
22/06/26
Natural Gas
ANP extends public consultation on the calculation of th...
22/06/26
Rio de Janeiro
Firjan’s Oil Yearbook in Rio highlights that positive pr...
22/06/26
Biomethane
With a market five times larger since 2020, the biometha...
22/06/26
Petrobras
Petrobras approves investment in bio-jet fuel and renewa...
22/06/26
BOGE2026
Smart Control Gains Prominence at Bahia Oil & Gas Energy...
09/06/26
BOGE2026
Bahia Oil & Gas Energy Concludes Historic Edition and Se...
06/06/26
Branded Content
Boaventura Energy Complex drives Brazil’s energy future ...
06/06/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2