Offshore

ExxonMobil Installs Topsides of Tapis R Platform

Platform is in Malaysia.

ExxonMobil
02/05/2014 17:08
Visualizações: 1955 (0) (0) (0) (0)

 

ExxonMobil Exploration and Production Malaysia successfully installed the topsides of Tapis R offshore platform at the Tapis field offshore Terengganu, Malaysia, local news agency Bernama reported Wedensday. Tapis R -- one of the largest offshore platform in Southeast Asia -- is a key component of the $3.1 billion (MYR 10 billion) Tapis Enhanced Oil Recovery (EOR) project in which ExxonMobil and joint-venture partner Petronas Carigali Sdn Bhd invest in new oil and gas assets to help ensure reliable and sustainable energy supplies for Malaysia. 
"The Tapis EOR project will enhance production from the Tapis field which has been producing since 1978 ... The EOR process will use alternating water and gas injection to improve oil recovery from this mature field over the long-term," ExxonMobil Exploration and Production Malaysia Inc President and Chairman of ExxonMobil subsidiaries in Malaysia See Kok Yew said, as quoted by Bernama. The Tapis R topsides was constructed as one large integrated deck, including gas compression and water injection facilities, production-processing equipment, utility systems and living quarters for 145 people. 
The topsides, designed and constructed locally, was fabricated by Malaysia Marine & Heavy Engineering under a $434 million (MYR 1.4 billion) contract awarded by ExxonMobil in November 2011. The contract also included construction of the Tapis Q riser platform, which was installed in October 2012, and the installation of access bridges linking the new Tapis R and Tapis Q platforms with the existing Tapis B platform. About 31 miles (50 kilometers) of new pipeline were also installed to distribute gas and water injection from Tapis R and to receive full-well stream production from the existing Tapis platforms, while a main oil pipeline was installed to export production from Tapis R. 
Hook-up and commissioning is expected to continue in the next few months at the Tapis R platform to prepare for water-alternating-gas injection activities to start in the third quarter of this year. 

ExxonMobil Exploration and Production Malaysia successfully installed the topsides of Tapis R offshore platform at the Tapis field offshore Terengganu, Malaysia, local news agency Bernama reported Wedensday. Tapis R -- one of the largest offshore platform in Southeast Asia -- is a key component of the $3.1 billion (MYR 10 billion) Tapis Enhanced Oil Recovery (EOR) project in which ExxonMobil and joint-venture partner Petronas Carigali Sdn Bhd invest in new oil and gas assets to help ensure reliable and sustainable energy supplies for Malaysia. 

"The Tapis EOR project will enhance production from the Tapis field which has been producing since 1978 ... The EOR process will use alternating water and gas injection to improve oil recovery from this mature field over the long-term," ExxonMobil Exploration and Production Malaysia Inc President and Chairman of ExxonMobil subsidiaries in Malaysia See Kok Yew said, as quoted by Bernama. The Tapis R topsides was constructed as one large integrated deck, including gas compression and water injection facilities, production-processing equipment, utility systems and living quarters for 145 people. 

The topsides, designed and constructed locally, was fabricated by Malaysia Marine & Heavy Engineering under a $434 million (MYR 1.4 billion) contract awarded by ExxonMobil in November 2011. The contract also included construction of the Tapis Q riser platform, which was installed in October 2012, and the installation of access bridges linking the new Tapis R and Tapis Q platforms with the existing Tapis B platform. About 31 miles (50 kilometers) of new pipeline were also installed to distribute gas and water injection from Tapis R and to receive full-well stream production from the existing Tapis platforms, while a main oil pipeline was installed to export production from Tapis R. 
Hook-up and commissioning is expected to continue in the next few months at the Tapis R platform to prepare for water-alternating-gas injection activities to start in the third quarter of this year. 

 

Most Read Today
see see
Sergipe Oil & Gas 2025
Sergipe’s Oil and Gas Potential Highlighted at SOG25 Opening
23/07/25
Sergipe Oil & Gas 2025
Sergas Participates in Sergipe Oil & Gas 2025 with Focus...
23/07/25
Sergipe Oil & Gas 2025
Fourth Edition of Sergipe Oil & Gas Highlights State’s R...
23/07/25
RD&I
ANP Holds Workshop on Private Equity Investment Fund (FIP)
23/07/25
Campos Basin
Petrobras announces Approval of the Production Individua...
23/07/25
ADIPEC 2025
ADIPEC 2025 Technical Conferences achieve record submiss...
22/07/25
People
BCCK names Andres Martinez as business development manager
21/07/25
Fenasucro
Brazil Holds Global Leadership in Renewable Cogeneration...
21/07/25
Results
Revap Achieves Historic Records in H1 with S10 Diesel an...
21/07/25
Solar Energy
Transpetro Inaugurates Solar Plant to Supply the Belém T...
21/07/25
Company News
Strohm completes successful field trials for Petrobras
16/07/25
Natural Gas
Gasmig: 39 Years of Energy, Innovation, and Commitment t...
16/07/25
Sustainability
Foresea earns Social Seal and reports significant result...
11/07/25
Results
Oil and Gas Sector Leads Dividend Distribution in 2024 w...
10/07/25
Natural Gas
Comgás Receives 41 Proposals in Public Call for Natural ...
10/07/25
People
Lucas Mota de Lima Appointed Executive Manager of ABPIP
10/07/25
Biomethane
Presidente Prudente (SP) Begins R$12 Million Biomethane ...
10/07/25
E&P
Hitachi Energy to evaluate electrification of offshore p...
10/07/25
Digitalization
TGS and Equinor Collaborate to Drive Digital Transformat...
10/07/25
People
Julia Cruz Appointed as New Secretary of Green Economy, ...
03/07/25
Sustainability
ABB among TIME’s World’s Most Sustainable Companies
03/07/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.