Santos Basin

Petrobras on the start of P-71 production

T&B Petroleum/Petrobras Agency
26/12/2022 16:35
Petrobras on the start of P-71 production Imagem: Petrobras Agency Visualizações: 1902 (0) (0) (0) (0)

Petrobras informs that it put into operation, last Wednesday (Dec,21), the P-71 platform vessel, installed in the Itapu field, in the Santos Basin pre-salt area, 200 km off the coast of Rio de Janeiro. The start of production has been anticipated, as it was originally scheduled for 2023.

From Petrobras' own platform portfolio, the P-71 is an FPSO (floating unit for the production, storage, and transfer of oil and gas) type with capacity to process up to 150,000 barrels of oil and 6 million m³ of gas per day, in addition to storing up to 1.6 million barrels of oil.

“We were able to anticipate the production of the P-71 platform, which was originally scheduled for 2023. We will also be able to anticipate the ramp-up (production evolution), which is excellent news not only for Petrobras but also for the country, which will receive the royalties from this production earlier," says Petrobras' Chief Production Development Officer, João Henrique Rittershaussen.

Positioned in a water depth of 2,010 meters, the P-71 will be the only one to produce in the Itapu field, fully operated by Petrobras under the Transfer of Rights and Production Sharing regimes. The company expects the unit to reach its maximum production capacity in 2023.

The P-71 is the sixth and last of the series of replicant platforms operated by Petrobras. These units are characterized by a standardized engineering design, high production capacity, and advanced technologies for operation and reduction of greenhouse gas emissions. One of the unit's low-carbon technologies is the so-called FGRU (Flare Gas Recovery Unity) system, which contributes to a greater utilization of the produced gas and reduction of emissions.

Most Read Today
see see
Company News
Bunker One centralizes multinational activities in Latin...
25/03/25
Fuels
Fuel and Lubricants Sector Drops 1.9% in February, Accor...
25/03/25
Pre-Salt
Petrobras reports results of exploratory well in Santos ...
19/03/25
Logistics
Transpetro to Double Platform Offloading Capacity by 2028
19/03/25
Brasilia
Launch of the Institute of Petroleum, Gas, and Energy in...
19/03/25
International Company News
Fulkrum Successfully Completes Vendor Surveillance for S...
14/03/25
E&P
Operational Safety: ANP Launches Dynamic Incident Panel ...
10/03/25
Ethanol
Anhydrous and Hydrated Ethanol Close Lower in a Week Sho...
10/03/25
International Women's Day
Celebrating Women's Day, Mobil™ Brings Drivers Antonella...
10/03/25
International Women's Day
Female Leadership in the Chemical Industry: Braskem Rein...
10/03/25
International Women's Day
Women in the Electric Sector: Driving Advances and Trans...
10/03/25
Merger
Saipem and Subsea7 join forces to create Saipem7
25/02/25
Royalties
Values related to December's production for production-s...
24/02/25
Drilling Operations
Constellation Oil Services Holding S.A. announces intent...
21/02/25
Permanent Offer
CNPE Approves Inclusion of Four New Pre-Salt Blocks in t...
21/02/25
Royalties
Values related to December production for concession and...
21/02/25
Natural Gas
Eneva and Samarco Sign Contract for Natural Gas Supply i...
21/02/25
Results
Four FPSOs operated by MODEC rank among the 10 largest o...
20/02/25
Record
Fulkrum Achieves Record Growth in 2024 with Global Expan...
20/02/25
Results
Foresea Closes 2024 with a Net Profit of $18 Million and...
20/02/25
Results
Sergipe Maintains 1st Place in the Free Gas Market Ranking
10/02/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.