Santos Basin

Petrobras on the start of P-71 production

T&B Petroleum/Petrobras Agency
26/12/2022 16:35
Petrobras on the start of P-71 production Imagem: Petrobras Agency Visualizações: 3168 (0) (0) (0) (0)

Petrobras informs that it put into operation, last Wednesday (Dec,21), the P-71 platform vessel, installed in the Itapu field, in the Santos Basin pre-salt area, 200 km off the coast of Rio de Janeiro. The start of production has been anticipated, as it was originally scheduled for 2023.

From Petrobras' own platform portfolio, the P-71 is an FPSO (floating unit for the production, storage, and transfer of oil and gas) type with capacity to process up to 150,000 barrels of oil and 6 million m³ of gas per day, in addition to storing up to 1.6 million barrels of oil.

“We were able to anticipate the production of the P-71 platform, which was originally scheduled for 2023. We will also be able to anticipate the ramp-up (production evolution), which is excellent news not only for Petrobras but also for the country, which will receive the royalties from this production earlier," says Petrobras' Chief Production Development Officer, João Henrique Rittershaussen.

Positioned in a water depth of 2,010 meters, the P-71 will be the only one to produce in the Itapu field, fully operated by Petrobras under the Transfer of Rights and Production Sharing regimes. The company expects the unit to reach its maximum production capacity in 2023.

The P-71 is the sixth and last of the series of replicant platforms operated by Petrobras. These units are characterized by a standardized engineering design, high production capacity, and advanced technologies for operation and reduction of greenhouse gas emissions. One of the unit's low-carbon technologies is the so-called FGRU (Flare Gas Recovery Unity) system, which contributes to a greater utilization of the produced gas and reduction of emissions.

Most Read Today
see see
ROG.e
IBP Launches the New ROG.e: The World’s Largest Energy F...
10/10/25
Pre-Salt
CNPE Sets Minimum Value of BRL 10.2 Billion for the Unio...
08/10/25
Natural Gas
Petrobras Carries Out First Natural Gas Import from Arge...
08/10/25
Agreement
Seagems renews Wärtsilä Lifecycle Agreement to support t...
07/10/25
Pre-Salt
Petrobras begins contracting for the construction of FPS...
03/10/25
International Company News
Alkhorayef Petroleum Company acquires GRC Technologies, ...
01/10/25
Pre-Salt
FPSO P-78 arrives at the Búzios Field
01/10/25
RD&I
Brazil Has the Capacity to Develop Its Own Technology fo...
01/10/25
Equatorial Margin
Ibama Approves Pre-Operational Assessment (APO) Conducte...
26/09/25
Sustainable Aviation
Embraer Advances SAF Studies Following Acquisition of Bi...
26/09/25
International Company News
ExxonMobil Guyana Expands Capacity With Seventh Offshore...
24/09/25
International Company News
More LNG for Europe
24/09/25
International Company News
Viking Completes Milestone Delivery to African Energy Pr...
24/09/25
Company News
CHC Helicopter Opens Hangar at Farol de São Tomé Helipor...
22/09/25
International Company News
“Sercel supplies sensors and trucks for major North Afri...
22/09/25
Geological Studies
R&D Clause Enables Project to Strengthen Critical Minera...
15/09/25
Fuels
ANP Approves Pilot Project with New Fuel Inspection Equi...
15/09/25
RD&I
Sensor Developed by Unicamp and UnB Advances in Internat...
15/09/25
Event
ABPIP Hosts SMS Oil & Gas Meeting Focused on Leadership,...
15/09/25
International
Petrobras announces participation in exploratory block i...
15/09/25
REVAP
Revap Maintenance Shutdown Involves R$ 1 Billion Investment
15/09/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.