Auction

With a forecast of R$ 21.7 billion in investments, the bidding documents for the second transmission auction of 2023 are being sent to the Federal Court of Accounts (TCU).

Lot 1, estimated at R$ 18.1 billion, will be subdivided into four sub-lots to increase competition, alongside the full lot.

T&B Petroleum/Press Office
02/08/2023 17:15
With a forecast of R$ 21.7 billion in investments, the bidding documents for the second transmission auction of 2023 are being sent to the Federal Court of Accounts (TCU). Imagem: Divulgation Visualizações: 1452 (0) (0) (0) (0)

Transmission Auction No. 2/2023 will be both one of the smallest and the largest event of its kind ever held by the National Electric Energy Agency (ANEEL). It will be one of the smallest in terms of the number of lots - only three - and the largest in terms of the estimated investment value: R$ 21.7 billion. The Collegiate Board of the Agency approved the auction notice draft on Tuesday (01/08) for the construction and maintenance of over 3,000 kilometers of transmission lines and substations, with a capacity of 9,840 megawatts (MW) in conversion capacity. The draft will be sent to the Federal Court of Accounts for review in the coming days. The auction is scheduled for December 15th at the B3 headquarters in São Paulo.

The three lots in question involve the construction of 11 projects in five states - Goiás, Maranhão, Minas Gerais, São Paulo, and Tocantins. With construction periods ranging from 60 to 72 months, they are expected to generate 36.9 thousand jobs.

One of the offered lots, Lot 1, has an estimated investment of R$ 18.1 billion. It includes the delivery of approximately 1,468 km of direct current transmission lines, crossing three states (Maranhão, Tocantins, and Goiás). Due to its complexity, Lot 1 has the longest completion period ever granted by the Agency: 72 months. This period is justified by the size of the project and the capacity of the market to meet construction demands.

After receiving 120 contributions from 21 entities during the Public Consultation No. 008/2023, ANEEL decided to subdivide Lot 1 into four sub-lots to increase competitiveness. The bidding in this case will follow the following dynamics:

  1. Interested bidders in the complete Lot 1 or any of the sub-lots must submit five envelopes to the auctioneer, with or without a valid bid for the lot and the four sub-lots. For this, they will previously register in this block, by providing a single proposal guarantee;
  2. The auctioneer will conduct two rounds: in the first, the choice will be made whether the grant will be for one contract (complete Lot 1) or 4 contracts (sub-lots), based on a comparison of the proposals presented in the envelopes. In this phase, regardless of the difference between the proposal composed of the sum of the lowest bids for the sub-lots and the best offer for the complete Lot 1, only the solution with the lowest overall value will advance;
  3. In the second round, there will be a live bid phase if there are proposals at most 5% above the lowest proposal, for the complete Lot or for each sub-lot individually, as decided in the previous stage.

A technical clarification workshop on the main points of the event is scheduled for October. After the review by the Federal Court of Accounts, the ANEEL Board foresees the publication of the notice and the bidding announcement in November.

Most Read Today
see see
International Company News
Fulkrum Successfully Completes Vendor Surveillance for S...
14/03/25
E&P
Operational Safety: ANP Launches Dynamic Incident Panel ...
10/03/25
Ethanol
Anhydrous and Hydrated Ethanol Close Lower in a Week Sho...
10/03/25
International Women's Day
Celebrating Women's Day, Mobil™ Brings Drivers Antonella...
10/03/25
International Women's Day
Female Leadership in the Chemical Industry: Braskem Rein...
10/03/25
International Women's Day
Women in the Electric Sector: Driving Advances and Trans...
10/03/25
Merger
Saipem and Subsea7 join forces to create Saipem7
25/02/25
Royalties
Values related to December's production for production-s...
24/02/25
Drilling Operations
Constellation Oil Services Holding S.A. announces intent...
21/02/25
Permanent Offer
CNPE Approves Inclusion of Four New Pre-Salt Blocks in t...
21/02/25
Royalties
Values related to December production for concession and...
21/02/25
Natural Gas
Eneva and Samarco Sign Contract for Natural Gas Supply i...
21/02/25
Results
Four FPSOs operated by MODEC rank among the 10 largest o...
20/02/25
Record
Fulkrum Achieves Record Growth in 2024 with Global Expan...
20/02/25
Results
Foresea Closes 2024 with a Net Profit of $18 Million and...
20/02/25
Results
Sergipe Maintains 1st Place in the Free Gas Market Ranking
10/02/25
International Company News
Interocean awarded Morgan, Mona, and Morven Offshore Win...
06/02/25
Natural Gas
ANP approves prior consultation aiming at new regulation...
06/02/25
Permanent Offer
Permanent Sharing Offer (OPP): ANP approves update of th...
06/02/25
Paraná
Renewable energy with savings of up to 35% drives the ex...
06/02/25
Pre-Salt
PPSA launches a new spot sale process for Union oil carg...
06/02/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.