Dudgeon Offshore wind farm contracts to Siemens plc

Statoil ia a as operator.

Statoil
14/01/2014 12:14
Visualizações: 1671 (0) (0) (0) (0)

 

As operator, Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project.
The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and three separate rotor blades (154-metre rotor diameter).
The engineering work will commence in January 2014 and contributes to design development of the project's design work for foundations and electrical infrastructure. The first batch of turbines shall be ready for load out and installation January 2017.
The service contract will cover operations and maintenance of the WTGs through the first two years after installation is completed, followed by three years where Siemens plc provides Dudgeon with technicians and other agreed services.  The estimated value for both contracts is GBP 516 million.
Statoil renewable energy senior vice president Siri Espedal Kindem states that this is a significant milestone for the Dudgeon offshore wind project and its owners.
"The new turbine contract will secure planned progress in the Dudgeon project towards full operation during 2017. Technology development is fundamental to optimising offshore wind industry costs and solutions, and the use of new large turbines such as these is a main contributor to reducing offshore wind costs."
The Dudgeon Offshore Wind Farm is Statoil's second full-scale commercial offshore wind project, and a key project in Norfolk.
Once in operation, the wind farm will provide renewable energy to approximately 400,000 households in the UK market.
"This WTG contract is important for further developing the Dudgeon project towards concept selection and a final investment decision in 2014. We have gained valuable experience to build on from Sheringham Shoal from both the installation and operational phases," says Statoil offshore wind project vice president Halfdan Brustad.
"In Dudgeon we seek to optimise solutions even further to bring down electricity costs, and we will have a strong cooperation with Siemens in operation and maintenance to ensure high regularity."


As operator, Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project.


The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and three separate rotor blades (154-metre rotor diameter).


The engineering work will commence in January 2014 and contributes to design development of the project's design work for foundations and electrical infrastructure. The first batch of turbines shall be ready for load out and installation January 2017.


The service contract will cover operations and maintenance of the WTGs through the first two years after installation is completed, followed by three years where Siemens plc provides Dudgeon with technicians and other agreed services.  The estimated value for both contracts is GBP 516 million.


Statoil renewable energy senior vice president Siri Espedal Kindem states that this is a significant milestone for the Dudgeon offshore wind project and its owners.


"The new turbine contract will secure planned progress in the Dudgeon project towards full operation during 2017. Technology development is fundamental to optimising offshore wind industry costs and solutions, and the use of new large turbines such as these is a main contributor to reducing offshore wind costs."


The Dudgeon Offshore Wind Farm is Statoil's second full-scale commercial offshore wind project, and a key project in Norfolk.


Once in operation, the wind farm will provide renewable energy to approximately 400,000 households in the UK market.


"This WTG contract is important for further developing the Dudgeon project towards concept selection and a final investment decision in 2014. We have gained valuable experience to build on from Sheringham Shoal from both the installation and operational phases," says Statoil offshore wind project vice president Halfdan Brustad.


"In Dudgeon we seek to optimise solutions even further to bring down electricity costs, and we will have a strong cooperation with Siemens in operation and maintenance to ensure high regularity."

Most Read Today
see see
ANP
A\Sense wins ANP technology challenge with advanced opti...
09/09/25
Rio Pipeline & Logistics 2025
Rio Pipeline & Logistics 2025 kicks off today, September 9
09/09/25
Minas Gerais
With R$ 314 million investment, pioneering macaúba biofu...
03/09/25
Recognition
Supergasbras earns Gold Seal in the Brazilian GHG Protoc...
03/09/25
FIRJAN
Brazilian industry records four consecutive months witho...
03/09/25
Copel
EPE President presents future outlook for the power sector
03/09/25
FIRJAN
Together with CNI, Firjan launches business mission in t...
03/09/25
Gulf of America
C-Innovation completes successful decommissioning projec...
28/08/25
Equatorial Margin
Rig chartered by Petrobras arrives in Amapá to take part...
19/08/25
FIRJAN
Rio gains Firjan SENAI Metalworking Reference Center
19/08/25
RD&I
CEPETRO develops for Petrobras a tool that integrates mu...
19/08/25
Pre-Salt
Búzios Field surpasses the record level of 900 thousand ...
19/08/25
Logistics
PetroReconcavo and Dislub build an unprecedented oil out...
19/08/25
IBP
NAVE Program advances with 21 energy sector startups
19/08/25
International Event
The 3rd Annual World ReAM Show Returns to Dubai, Bridgin...
13/08/25
Sustainability
ATPI Expands Global Sustainability Portfolio with Brazil...
06/08/25
Results
ANP releases consolidated 2024 data in English for the r...
29/07/25
Sergipe Oil & Gas 2025
SOG25 Surpasses Expectations in Its 4th Edition and Sets...
28/07/25
Sergipe
Government of Sergipe and Petrobras Strengthen Partnersh...
28/07/25
Sergipe Oil & Gas 2025
Sergipe Oil & Gas 2025 Highlights the Competitiveness of...
25/07/25
Sergipe Oil & Gas 2025
Márcio Félix, President of ABPIP, Sees a Promising Futur...
25/07/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.

2