McDermott discusses its work on Papa Terra TLP

First production occurred in November 2013.

McDermott
06/02/2014 16:16
Visualizações: 2312 (0) (0) (0) (0)

 

McDermott discusses its work on Papa Terra TLP
McDermott International Inc., is highlighting its recent work on the Papa Terra TLP at the Topsides, Platforms and Hulls Conference & Exhibition being held at the Moody Gardens Hotel & Convention Center in Galveston, Texas.
McDermott says the project involved the first use of dry-tree floating technology offshore Brazil and the first TLP installation offshore South America. The company also says that project drew upon the proprietary technology, engineering, and construction resources of McDermott, Keppel, and FloaTEC, the joint venture company between McDermott and Keppel.
The facilities developed included the tension leg wellhead platform (TLWP), hull, topsides, tendons, and risers. Work was allocated as follows: 
Topsides engineering was by McDermott while the hull engineering was by FloaTEC. Partial procurement services were provided by the cross-company project team.
Fabrication of the piles and tendons was by McDermott’s Morgan City multi-joint welding facility. Major installation components, such as tendon buoyancy modules, were provided by McDermott Wuchuan fabrication yard in Qingdao and at McDermott's Morgan City facility. Risers, well systems, and tendon components were supplied by FloaTEC. The TLWP hull and topsides are being constructed by Keppel.
McDermott performed float-over project management and TLWP installation offshore, as well as installation of the anchor piles and tendons; with the cross-company project team responsible for commissioning.
FloaTEC will perform operations and maintenance of the TLWP for the initial three-year period of operations.
Papa Terra is a heavy crude oil field in block BC-20 of the Campos basin 110 km (68 mi) offshore Brazil in 1,190 m (3,903 ft) water depth. Petrobras is operator with 62.5% interest while Chevron holds the remaining 37.5%.
The partners made the final investment decision in January 2010 and will invest $5.2 billion on field development. First production occurred in November 2013.

McDermott International Inc., is highlighting its recent work on the Papa Terra TLP at the Topsides, Platforms and Hulls Conference & Exhibition being held at the Moody Gardens Hotel & Convention Center in Galveston, Texas.

 

McDermott says the project involved the first use of dry-tree floating technology offshore Brazil and the first TLP installation offshore South America. The company also says that project drew upon the proprietary technology, engineering, and construction resources of McDermott, Keppel, and FloaTEC, the joint venture company between McDermott and Keppel.

 

The facilities developed included the tension leg wellhead platform (TLWP), hull, topsides, tendons, and risers. Work was allocated as follows: 

 

Topsides engineering was by McDermott while the hull engineering was by FloaTEC. Partial procurement services were provided by the cross-company project team.

 

Fabrication of the piles and tendons was by McDermott’s Morgan City multi-joint welding facility. Major installation components, such as tendon buoyancy modules, were provided by McDermott Wuchuan fabrication yard in Qingdao and at McDermott's Morgan City facility. Risers, well systems, and tendon components were supplied by FloaTEC. The TLWP hull and topsides are being constructed by Keppel.

 


McDermott performed float-over project management and TLWP installation offshore, as well as installation of the anchor piles and tendons; with the cross-company project team responsible for commissioning.
FloaTEC will perform operations and maintenance of the TLWP for the initial three-year period of operations.

 

Papa Terra is a heavy crude oil field in block BC-20 of the Campos basin 110 km (68 mi) offshore Brazil in 1,190 m (3,903 ft) water depth. Petrobras is operator with 62.5% interest while Chevron holds the remaining 37.5%.

 

The partners made the final investment decision in January 2010 and will invest $5.2 billion on field development. First production occurred in November 2013.

Most Read Today
see see
OTC Brasil 2025
Event brings together global offshore industry leaders a...
28/10/25
OTC Brasil 2025
Petrobras participates in OTC Brasil 2025, in Rio de Janeiro
28/10/25
Petrobras
Petrobras produced 3.14 million barrels of oil equivalen...
27/10/25
FIRJAN
By 2035+, Rio de Janeiro State’s Energy Potential Could ...
23/10/25
Pre-Salt
PPSA to auction in December the first share of governmen...
23/10/25
Auction
Petrobras wins auction and leases RDJ07 terminal at the ...
23/10/25
Permanent Offer
Equinor acquires two new blocks in the Campos Basin duri...
23/10/25
OTC Brasil 2025
OTC Brasil 2025 Kicks Off in One Week with a Packed Prog...
22/10/25
Agreement
Wärtsilä Lifecycle agreement renewed to maintain safe, r...
22/10/25
Petrobras
Petrobras receives operating license for deepwater explo...
20/10/25
Equatorial Margin
License Grant for Drilling in the Equatorial Margin Is P...
20/10/25
Equatorial Margin
ABESPetro Statement on the Licensing of the Equatorial M...
20/10/25
Energy Transition
BNDES, Petrobras, and Finep select Valetec to manage the...
20/10/25
Pre-Salt
Petrobras and PPSA sign equalization agreement for Jubar...
20/10/25
WPC Energy Youth Forum
Kuwait to Host 8th WPC Energy Youth Forum in October 2025
20/10/25
Exports
Petrobras signs contract to sell six million barrels of ...
20/10/25
Petrobras
Petrobras puts the Harpia supercomputer into operation
10/10/25
PPSA
PPSA Publishes Notice for the Non-Contracted Areas Auction
10/10/25
ROG.e
IBP Launches the New ROG.e: The World’s Largest Energy F...
10/10/25
Pre-Salt
CNPE Sets Minimum Value of BRL 10.2 Billion for the Unio...
08/10/25
Natural Gas
Petrobras Carries Out First Natural Gas Import from Arge...
08/10/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.