Njord field cutting 130 000 tonnes of CO2 emissions per year from 2027

Based on a collaboration project with OKEA, Njord A will be electrified to cut greenhouse gas emissions from production. Equinor has, on behalf of the Njord licence partners, submitted a revised plan for development and operation (PDO) to the Ministry of Petroleum and Industry.

Press Office
15/12/2022 19:40
Njord field cutting 130 000 tonnes of CO2 emissions per year from 2027 Imagem: Divulgation Equinor Visualizações: 2807 (0) (0) (0) (0)

“Njord A and the Njord Bravo floating storage and offloading (FSO) vessel returned to the field this autumn after extensive upgrading and will soon be ready for 20 more years of production and value creation. We are now continuing the modernization of Njord by converting to electric operation. This will cut emissions from production and reduce Norwegian CO2 emissions by more than 130 000 tonnes per year from 2027,” says Trond Bokn (photo), Equinor’s senior vice president for project development.

Electrification of Njord will also benefit the Hyme, Bauge and Fenja tie-back fields. These fields help finance the project.

As operator of Draugen, OKEA will be responsible for developing the power infrastructure from shore to Draugen. Equinor will be responsible for the cable from Draugen to Njord as well as modifications and upgrading on Njord A, where the two existing gas turbines for main power production will be replaced by electric power from shore via Draugen. Based on this, around 60 per cent of the power needed by Njord A will be covered by electricity, and the Njord Bravo FSO will be fully electrified.

In total, the electrification of Draugen and Njord will cut 330 000 tonnes of CO2 emissions per year.

The fields will have a total power demand of up to 80 MW per year and will be connected to the power grid at a transformer station at Straum in Åfjord municipality. Operated by Tension, the transformer station has a capacity of 200 MW, and the project does not require a grid upgrading.

The investment estimate for the whole project is around NOK 7.3 billion, of which a good NOK 3 billion covers the share of the Njord licence. The revised plans for development and operation (PDO) and for installation and operation (PIO) must be approved by the Ministry of Petroleum and Energy.

Start-up is expected in the first quarter of 2027.

Most Read Today
see see
Fenasucro
Future Fuel consolidates Brazilian pioneering role and b...
20/05/26
Partnership
Radix partners with Repsol Sinopec Brasil and PUCRS to c...
20/05/26
Communication
The behind-the-scenes story of communication and adverti...
20/05/26
Result
Total oil production under production-sharing regime hit...
20/05/26
BOGE2026
Global geopolitics’ impact on the local oil sector to be...
19/05/26
International Women's Day
IBP celebrates International Women at Sea Day and reinfo...
19/05/26
Pre-Salt
Mero Field in the Santos Basin Pre-Salt Receives Unprece...
14/05/26
Results
Petrobras reports net profit of R$ 32.7 billion in the f...
14/05/26
Partnership
Halliburton and Shape Digital establish strategic collab...
06/05/26
ROG.e 2026
ROG.e 2026 will bring together CEOs from TotalEnergies, ...
06/05/26
International
At OTC Houston 2026, Firjan SENAI SESI expands its reach...
06/05/26
International
At OTC Houston 2026, Firjan SENAI holds international ed...
04/05/26
Recognition
BRAVA Energia receives top global industry award for Atl...
04/05/26
International
Brazil reaffirms technological leadership at OTC Houston...
04/05/26
Pre-Salt
PPSA closes 2025 with a net profit of R$ 30.1 million
04/05/26
Results
With 5.531 million boe/d, Brazil continues with record o...
04/05/26
International
Brazil reaffirms technological leadership at OTC Houston...
02/05/26
Environment
Brazil appears among world's largest methane emitters in...
30/04/26
PPSA
Federal Government receives R$ 917.32 million from Tupi ...
07/04/26
Study
Brazil increases dependence on thermal power, but lack o...
07/04/26
Permanent Offer
Permanent Production Sharing Offer (OPP): ANP publishes ...
07/04/26
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.