Technology

Wood Group GTS completes $2M maintenance and optimization solution for Jamaican power station

Service was in Bogue Power Plant.

Wood Group
17/12/2013 11:12
Visualizações: 2199 (0) (0) (0) (0)

 

Wood Group GTS has completed the major maintenance service and gas turbine optimization of Jamaica Public Service Company's (JPS) Bogue Power Plant, located in Montego Bay Jamaica. Wood Group GTS executed a hot gas path inspection and provided the necessary parts and repairs, completing the outage event in only nine days, meeting JPS' required maintenance schedule. 
Wood Group GTS also provided its EcoValueTM compressor water wash technology, which will be installed by the customer for two GE Frame 6B gas turbines, which will increase its efficiency at the combined cycle plant. In similar applications, Wood Group GTS customers have experienced improved power output of up to 2.1 per cent on a 2x1 power block, resulting in additional revenue and fuel cost savings. 
"Wood Group GTS' maintenance leadership team assured our contractual and service requirements were met. The completion of this hot gas path inspection in only nine days was the fastest JPS has ever seen performed on our unit," said Ruben Thomas, station manager of JPS. "This service delivery was done successfully through Wood Group GTS' proven process, work packages and organizational support. We are confident that the compressor water wash technology will improve the gas turbine efficiency and generate a rapid return on our investment."
"We're proud to be a service provider for JPS. The success of this outage affirms our commitment to service excellence and helping our customers meet their performance needs. In addition to the cost-effective outage work, JPS will benefit from the long-term sustained improvement in output and efficiency gained from the EcoValue water wash system," said Frank Avery, president of Wood Group GTS - Power Plant Services. 
EcoValue compressor water wash technology is part of Wood Group GTS' overall products and services designed to maximize the return on our customer's investment in gas turbine technology

Wood Group GTS has completed the major maintenance service and gas turbine optimization of Jamaica Public Service Company's (JPS) Bogue Power Plant, located in Montego Bay Jamaica. Wood Group GTS executed a hot gas path inspection and provided the necessary parts and repairs, completing the outage event in only nine days, meeting JPS' required maintenance schedule. 


Company also provided its EcoValueTM compressor water wash technology, which will be installed by the customer for two GE Frame 6B gas turbines, which will increase its efficiency at the combined cycle plant. In similar applications, Wood Group GTS customers have experienced improved power output of up to 2.1 per cent on a 2x1 power block, resulting in additional revenue and fuel cost savings. 


"Wood Group GTS' maintenance leadership team assured our contractual and service requirements were met. The completion of this hot gas path inspection in only nine days was the fastest JPS has ever seen performed on our unit," said Ruben Thomas, station manager of JPS. "This service delivery was done successfully through Wood Group GTS' proven process, work packages and organizational support. We are confident that the compressor water wash technology will improve the gas turbine efficiency and generate a rapid return on our investment."


"We're proud to be a service provider for JPS. The success of this outage affirms our commitment to service excellence and helping our customers meet their performance needs. In addition to the cost-effective outage work, JPS will benefit from the long-term sustained improvement in output and efficiency gained from the EcoValue water wash system," said Frank Avery, president of Wood Group GTS - Power Plant Services. 


EcoValue compressor water wash technology is part of Wood Group GTS' overall products and services designed to maximize the return on our customer's investment in gas turbine technology

 

Most Read
see see
PPSA
PPSA Publishes Notice for the Non-Contracted Areas Auction
10/10/25
ROG.e
IBP Launches the New ROG.e: The World’s Largest Energy F...
10/10/25
Pre-Salt
CNPE Sets Minimum Value of BRL 10.2 Billion for the Unio...
08/10/25
Natural Gas
Petrobras Carries Out First Natural Gas Import from Arge...
08/10/25
Agreement
Seagems renews Wärtsilä Lifecycle Agreement to support t...
07/10/25
Pre-Salt
Petrobras begins contracting for the construction of FPS...
03/10/25
International Company News
Alkhorayef Petroleum Company acquires GRC Technologies, ...
01/10/25
Pre-Salt
FPSO P-78 arrives at the Búzios Field
01/10/25
RD&I
Brazil Has the Capacity to Develop Its Own Technology fo...
01/10/25
Equatorial Margin
Ibama Approves Pre-Operational Assessment (APO) Conducte...
26/09/25
Sustainable Aviation
Embraer Advances SAF Studies Following Acquisition of Bi...
26/09/25
International Company News
ExxonMobil Guyana Expands Capacity With Seventh Offshore...
24/09/25
International Company News
More LNG for Europe
24/09/25
International Company News
Viking Completes Milestone Delivery to African Energy Pr...
24/09/25
Company News
CHC Helicopter Opens Hangar at Farol de São Tomé Helipor...
22/09/25
International Company News
“Sercel supplies sensors and trucks for major North Afri...
22/09/25
Geological Studies
R&D Clause Enables Project to Strengthen Critical Minera...
15/09/25
Fuels
ANP Approves Pilot Project with New Fuel Inspection Equi...
15/09/25
RD&I
Sensor Developed by Unicamp and UnB Advances in Internat...
15/09/25
Event
ABPIP Hosts SMS Oil & Gas Meeting Focused on Leadership,...
15/09/25
International
Petrobras announces participation in exploratory block i...
15/09/25
VEJA MAIS
Newsletter TN

Contact us

We use cookies to ensure you have the best experience on our website. If you continue to use this site, we will assume that you agree with our Privacy Policy, terms of use and cookies.